No. 2009-1214

Vantage Assocs. v. Sec'y of Defense

Aug 7, 2009Appeal from the ASBCA
Contract disputeNonprecedentialContractor appealed

Key Facts

Appellant
Vantage Associates, Inc.
Appellee
Sec'y of Defense
Appeal taken by
Contractor appealed

The contractor or protester lost below and brought the appeal.

Docket number
No. 2009-1214
Decided
Aug 7, 2009

From the opinion's own decided line.

Matter
Contract dispute
Panel
RADER, PLAGER, SCHALL
Opinion by
SCHALL

Appealed From

ASBCA

The Armed Services Board of Contract Appeals, the Contract Disputes Act board for the defense agencies and NASA.

Appealed from: Armed Services Board of Contract Appeals Administrative Judge Michael T. Paul -

Opinion PDF (cafc.uscourts.gov)The disposition, the side that appealed and the appearances above are read deterministically from the opinion's own words. The court's document is the source of record.

Research This Decision

Create a free account to open this decision in the Federal Circuit workspace: the filtered browser over every appeal, the outcome dashboard, and the reading that follows an appeal down to the decision under review and across the cases it cites.

Browse with Filters

Every government-contracts appeal in the corpus, filtered by the tribunal below, the disposition, precedential status and matter, with full-text search over the opinions.

Insights

Contractor relief by disposition and by the side that appealed, per tribunal below and per year, with every denominator visible beside its rate.

Cross-Corpus Reading

The Appealed-from join into the Court of Federal Claims, ASBCA and CBCA corpora, and the cited-cases panel that names every prior decision this opinion relies on.

Full Opinion

Full text of the opinion5 pages, 6,233 characters, read from the court's own documentDecided Aug 7, 2009 on the opinion's own line Decision documentOfficial source: U.S. Court of Appeals for the Federal Circuit opinions and orders
PanelRADER, PLAGER, SCHALLOpinion bySCHALLNonprecedential
Appealed fromArmed Services Board of Contract Appeals Administrative Judge Michael T. PaulJudge Michael T. PaulThe opinion states: Appealed from: Armed Services Board of Contract Appeals Administrative Judge Michael T. Paul -

Authorities cited

2 authorities read from this opinion's own text, grouped by the body of law each comes from. 1 open at a publisher or in this app; the rest are shown without a link because no published page for them was confirmed.

Tucker Act and the Judicial Code1
Decisions of other forums1
ASBCA No. 55647

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

1 case this opinion cites, in the order it first names it. No published copy of any of them was confirmed, so each is shown without a link.

Vantage Associates, Inc.ASBCA No. 55647

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit

2009-1214

VANTAGE ASSOCIATES, INC.,

Appellant,

v.

Robert M. Gates, SECRETARY OF DEFENSE,

Appellee.

Brian J. Donovan, Jones & Donovan, of Newport Beach, California, for appellant.

Patryk J. Drescher, Trial Attorney, Commercial Litigation Branch, Civil Division,

United States Department of Justice, of Washington, DC, for appellee. With him on the

brief were Michael F. Hertz, Deputy Assistant Attorney General, Jeanne E. Davidson,

Director, and Harold D. Lester, Jr., Assistant Director.

Appealed from: Armed Services Board of Contract Appeals

Administrative Judge Michael T. Paul

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit

2009-1214

VANTAGE ASSOCIATES, INC.,

Appellant,

v.

Robert M. Gates, SECRETARY OF DEFENSE,

Appellee.

Appeal from the Armed Services Board of Contract Appeals in no. 55647,

Administrative Judge Michael T. Paul.

DECIDED: August 7, 2009

The case caption as the opinion prints it. Every word is kept; only a line that is nothing but a drawn rule is left out.

Before RADER, PLAGER, and SCHALL, Circuit Judges.

SCHALL, Circuit Judge.

DECISION

Vantage Associates, Inc. (“Vantage”) appeals from the final decision of the Armed Services Board of Contract Appeals (“Board”), which granted the government’s motion for summary judgment and denied Vantage’s breach of contract claim for $81,283 in damages arising from the cancellation of a purchase order issued by the Defense Supply Center Columbus (“DSCC”). Vantage Associates, Inc., ASBCA No. 55647, slip op. at 6 (Dec. 31, 2008). We affirm.

DISCUSSION

I.

On November 15, 2005, DSCC issued Vantage a purchase order for the delivery of plastic carrying cases for weapons. Id. at 1. After a series of delays in delivery, on July 12, 2006, DSCC issued Modification No. P00001, extending the delivery date for the cases to August 18, 2006. Id. at 3. On August 7, 2006, Vantage sent an e-mail to DSCC stating, “[W]e are looking at not being able to ship until October as the vendor is unable to fulfill our purchase order due to some mold problems.” Id. On August 17, 2006, the contracting officer issued Modification No. P00002, cancelling the purchase order. Id. Vantage received the modification on August 18th. Id. at 4. After the contracting officer denied Vantage’s claim for “contract adjustment for cancellation” in the amount of $81,283, Vantage appealed to the Board. Id. at 4–5. In due course, the Board granted summary judgment in favor of the government, on the ground that DSCC ceased to be bound by the purchase order once Vantage notified DSCC that it would not be able to meet the August 18th delivery date set forth in Modification No. P00001. Id. at 6. Vantage now appeals to us. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10).

II.

Vantage argues that the government’s purchase order was an irrevocable offer, and that the government’s revocation of the purchase order prior to its expiration was a breach for which Vantage is entitled to compensation. Vantage’s Br. 10. The purchase order, according to Vantage, was an offer for a unilateral contract, which became irrevocable once Vantage began performance and notified the government of the

commenced performance. Id. at 11. Vantage contends that once the offer became irrevocable, the government was precluded from revoking it before either the close of business or midnight of the delivery date, August 18, 2006. Id. at 15. Vantage also contends that its August 7, 2006 e-mail notifying the government that it did not intend to deliver the cases by August 18, 2006 did not relieve the government of its obligation to keep the purchase order open until, at the very least, the close of business on August 18, 2006, because the concept of anticipatory breach does not apply to unilateral contracts. Id. at 18. Thus, in Vantage’s view, the government’s cancellation of the purchase order on August 17, 2006, was a breach of contract for which the government must compensate Vantage. Id. at 19.

We are not persuaded by Vantage’s arguments that the Board erred in holding that the government was no longer bound by the purchase order once Vantage notified DSSC that it could not meet the delivery date. We agree with Vantage that the purchase order was a unilateral offer, and that Vantage’s commencement of performance limited the government’s right to revoke the purchase order. We disagree, however, with Vantage that the August 7, 2006 e-mail communicating to DSSC that Vantage could not perform in a timely manner did not relieve the government of its obligation to keep the purchase order open until August 18, 2006. That is because the government’s promise not to revoke the offer was in exchange for Vantage’s implied promise to complete performance. Once Vantage notified the government that it would not complete performance according to the terms of the purchase order, the government was no longer bound by its promise not to revoke the offer.

We note that Vantage does not argue that, but for the government’s cancellation of the purchase order, it would have timely performed by the end of the day on August 18, 2006. In its opening brief, Vantage states that, if the government had not cancelled the order, it would have delivered the cases no later than September 30, 2006.

Vantage’s Br. 9. In other words, if the government had not cancelled the purchase order, Vantage would not have furnished the cases in accordance with the terms of the contract. Vantage argues, nevertheless, that the government prematurely cancelled its purchase order at 3:27 a.m. on August 18, 2006—hours before the purchase order would have lapsed by its own terms. In other words, despite its inability to perform, Vantage contends it can recover all of its costs because, just before the delivery deadline that it admits it would not have met, it received notice of the purchase order’s cancellation. We do not think that, under these circumstances, Vantage is entitled to damages for the costs it incurred in preparation to deliver the cases.

No costs.

This is a verbatim capture of the text layer of the court's own document in Vantage Assocs. v. Sec'y of Defense. Nothing is summarized or reworded, and the sections run in the order the court wrote them. One thing the page shows is not repeated in the text: the pagination furniture, which is the page numbers, the docket footer and the electronic filing stamp printed across the top of each page.

Related Decisions

Appeals From the ASBCA

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.