CBCA 1198

Global Construction, Inc.

Jan 28, 2010Judge SomersDEPARTMENT OF VETERANS AFFAIRS
Not published in the listingDenied

Key Facts

Appellant
Global Construction, Inc.
Respondent agency
DEPARTMENT OF VETERANS AFFAIRS
Judge
Somers
Case number
CBCA 1198
Decided
Jan 28, 2010The decision states Jan 28, 2010 on its own face, which agrees with the listing.
Decision type
Not published in the listingThe Board's year tables for 2007 through 2014 carry no Type column, so no disposition was published for this decision. It is not missing data and nothing is inferred from the document.
Law firm for the appellant
Emerson Law Firm P.C.
Outcome
Denied
The appeal is DENIED.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Termination for defaultDelay, suspension and accelerationChanges and equitable adjustmentTermination for convenienceProcedure and sanctions

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Cynthia S. Emerson
Emerson Law Firm P.C.
Eureka Springs, AR
For the appellant
Joree G. Brownlow
Cordova, TN
For the respondent
Deborah K. Morrell and Harold W. Askins
Office of Regional Counsel, Department of Veterans Affairs
Decatur, GA
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision11 pages, 25,554 characters, read from the Board's own documentDecided Jan 28, 2010 on its own faceRespondent DEPARTMENT OF VETERANS AFFAIRS Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

3 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Federal Acquisition Regulation3

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

9 cases this decision cites, grouped by the forum that decided each, in the order it first names them. 8 of them open at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

DENIED: January 28, 2010

CBCA 1198

GLOBAL CONSTRUCTION, INC.,

Appellant,

v.

DEPARTMENT OF VETERANS AFFAIRS,

Respondent.

Cynthia S. Emerson of Emerson Law Firm P.C., Eureka Springs, AR; and Joree G.

Brownlow, Cordova, TN, counsel for Appellant.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Deborah K. Morrell and Harold W. Askins, Office of Regional Counsel, Department of Veterans Affairs, Decatur, GA, counsel for Respondent.

Before Board Judges SOMERS, GOODMAN, and STEEL.

SOMERS, Board Judge.

Appellant, Global Construction, Inc. (Global), has challenged a contracting officer’s decision to terminate for default a contract for construction work at the Department of Veterans Affairs Medical Center, located in Augusta, Georgia. We find that the Government has sustained its burden to justify the termination and deny the appeal.

2 CBCA 1198

Findings of Fact

On September 16, 2004, the Department of Veterans Affairs (VA or the Government) awarded a contract to Global. The contract required Global to provide all labor, materials, equipment, and supervision for the demolition and reconstruction of the Spinal Cord Injury Unit in the downtown division of the Augusta VA Medical Center, Augusta, Georgia.

Appeal File, Exhibit 1.1 The specifications included the building of a courtyard with a greenhouse, the construction of a cystoscopy suite comprised of three lead-lined rooms, and the installation of litter baths with corresponding plumbing features to be used for the specialized treatment of spinal cord injury patients. Exhibit 3 (Contract Specifications). The original contract contained three construction phases. The contracting officer issued a notice to proceed on October 18, 2004. Exhibit 2. The contract required that all work be completed within 660 days from receipt of the notice to proceed, or, in other words, no later than August 29, 2006. Id. Phase 1 was completed in June 2005. Phase 2 began on June 13, 2005. Starting on July 11, 2006, during Phase 2, the parties met on a bi-weekly basis to inspect the progress of the construction and to address issues as the project progressed.

Over the course of the contract, the parties extended the time for contract performance through the issuance of bilateral contract modifications. See, e.g., Exhibit 110, Supplemental Agreement No. 2 and Time Extension No. 1 at 3. Even with these extensions, however, subcontractor coordination issues and turnover of contractor management, combined with Global’s apparent misunderstanding of certain contract requirements, caused repeated delays to the project.

Thus, in October 2006, Global submitted a revised schedule changing the anticipated completion date of Phase 2 from the beginning of November to the end of December 2006. The schedule did not address Phase 3 of the project. On November 22, 2006, the contracting officer noted that, based upon the current pace of construction, it did not appear that Global could complete Phase 2 on time. The contracting officer suggested that Global review the current schedule and initiate action to ensure completion or submit a revised schedule. Exhibit 162.

1All exhibits are found in the appeal file, unless otherwise noted.

Multiple job superintendents had been assigned to the project, apparently delaying the project and ultimately resulting in a sixty-day time extension to the contract at the request of the contractor. Exhibit 110 at 33. The last contract modification extended the contract completion date to May 15, 2007. Exhibit 110 at 54-55.

3 CBCA 1198

On December 19, 2006, when it became apparent that Global would not complete Phase 2 in accordance with its schedule, the contracting officer asked Global to submit a revised schedule, stating as follows:

Please resubmit a revised timeline reflecting a realistic attainable completion date. In addition you must address the additional time required for completion and request time extensions with consideration. Even though this job is behind schedule, it is our hope that the current hurdles can be rectified and this contract completed in a timely manner.

Exhibit 163.

Global submitted a revised schedule on January 17, 2007. In addition, Global requested a sixty-day time extension, citing problems with subcontractors, management inefficiency, and lack of sufficient construction personnel. The contracting officer rejected that request, stating that Global would need to make an offer of consideration before the contracting officer could justify an extension of time on those grounds. Exhibit 164. When Global did not resubmit the revised schedule, the contracting officer stated in a letter dated February 8, 2007:

This job is behind schedule and you are currently in a technical default status. In accordance with Specification Section 01001, 52.236-15, Schedules for Construction Contracts (APR 1984) and as previously stated in our January 4, 2007 letter, you are directed to submit a revised timeline reflecting [an] attainable completion date for the entire project, as well as the completion date for the Phase 2 portion. The Phase 2 completion date is essential to our planning the relocation of staff from the Phase 3 area to the Phase 2 area. In addition, you must address the additional time required for completion and request required time extensions with consideration acceptable to the government.

Exhibit 165 (emphasis omitted). Global submitted a revised schedule on March 13, 2007, with a proposed completion date of October 1, 2007. The Government found multiple errors in the schedule, and, in light of continuing performance issues, the Government contemplated terminating the contractor at that time. It rejected the revised schedule. Exhibit 166 at 25. 4 CBCA 1198

Global resubmitted its revised schedule on April 3, 2007, indicating that Phase 2 would be complete by June 15, 2007. Again, Global did not include Phase 3 in its schedule. In April 2007, Carl Lanier, Vice President of Global, took over as job superintendent. On April 24, 2007, Mr. Lanier requested that the bi-weekly meetings be changed to weekly meetings.

At a meeting on April 25, 2007, Mr. Lanier advised the Government that Global was approximately one week behind the schedule it had just submitted. Exhibit 167 at 26. By letter dated May 29, 2007, the Government requested that Global submit another revised schedule. Exhibit 168 at 16.

On June 15, 2007, Global submitted a new schedule, which the Government rejected because it failed to address all phases of the project. By e-mail message dated June 22, 2007, Global assured the contracting officer that the “scheduled completion [date] of July 31 remains the same for all phases of work except the entrance front, handrails, and automatic doors,” which could be delayed due to supplier delay. Exhibit 169 at 29. The Government responded that the supply submittals had been approved back in July 2005 and November 2006, and noted that the potential problems identified by Global did not provide adequate justification for any delays and further delays would impact payments to Global. Id. On June 30, 2007, the Government presented Global with a “pre-punch” list, identifying pages of items needing correction prior to final inspection.

Over the course of the next few months, the parties met regularly, and the Government provided Global with lists of items that needed correction or had been rejected outright and sought revised schedules. In August 2007, using input provided by Global, the Government prepared a schedule identifying the Phase 2 completion date of October 8, 2007, and scheduling Phase 3 to begin on October 19, 2007. Global concurred with the schedule by e-mail message dated August 10, 2007. Exhibit 171 at 5-6. Again, however, it soon became apparent that Global could not meet the new completion date, so, by letter dated August 24, 2007, the contracting officer requested that Global submit another revised schedule. During the September 19, 2007, meeting, Mr. Lanier requested that the Government consider dropping Phase 3 from the contract. The Government requested that Global submit this request in writing to the contracting officer. Exhibit 172 at 8. Global did not do so. On November 13, 2007, when Global failed to submit a revised schedule despite numerous requests, the Government issued a show cause notice. The notice stated, in part, as follows:

5 CBCA 1198

Since you have failed to perform Contract No. V247C0348(a) within the time required by its terms, or cure the conditions endangering performance under Contract No. V247C0348(a) as described to you on numerous occasions, the Government is considering terminating the contract under the provisions for default of this contract.

Exhibit 174. The notice also detailed performance issues that included “failure to meet identified milestones” and “many items requiring correction” that had gone unresolved despite identification in the field reports. Id. The notice stated that the current modified completion date based upon the contract modifications granting extensions of time was May 15, 2007. Id.; see also Exhibit 110 at 54-55.

The Government conducted a pre-final inspection on November 28, 2007, and confirmed that Global had failed to fix many problems that had been previously identified during the course of contract performance. At a meeting held on December 12, 2007, the Government asked that Global provide a final date for completion of Phase 2 no later than December 21, 2007. On December 19, 2007, Global submitted a schedule with a completion date for Phase 2 of February 15, 2008. The Government rejected the date and told Global that Phase 2 must be completed no later than January 16, 2008. Exhibit 175 at 15.

On January 11, 2008, the contracting officer sent a letter to Global to advise it that the revised and final completion date for Phase 2 of the project would be January 30, 2008, and that any remaining punch list items from an inspection scheduled for that date must be completed by February 6, 2008. Exhibit 205. Phase 3 of the contract was deleted by modification on January 18, 2008. Exhibit 178. The Government conducted a final inspection on January 31, 2008, and issued a sixteen-page report identifying over 300 discrepancies, many of which had been identified during earlier inspections. Exhibit 203. The Government issued a cure notice on February 7, 2008. Exhibit 177; Trial Exhibit 3. Global requested a re-inspection, which occurred on February 15, 2008. On February 26, 2008, the Government terminated the contract for default.

Among the contract clauses included in the contract that are relevant to this appeal is Federal Acquisition Regulation (FAR) 52.236-15, which requires the contractor to submit a schedule to the contracting officer within five days after work is commenced on the project, showing the order in which the contractor proposes to perform the work and the dates on which the contractor contemplates starting and completing the work. The contract specifically required the schedule to be presented in the form of a progress chart indicating the percentage of work scheduled for completion by any given date during the period and 6 CBCA 1198

authorized the contracting officer to withhold approval of progress payments until the contractor submitted the required schedule. Exhibit 3, Specifications, at 01001-77. The Veterans Administration Acquisition Regulation 852.236-84, also included in the contract, specified that the contractor must revise the progress schedule when individual or cumulative time extensions of fifteen calendar days were granted for any reason. Id. at 01001-101. FAR 52.232-5, also included in the contract, states that “a revised construction schedule shall be submitted with each request for progress payment.” Paragraph (e) of this clause permits the contracting officer to retain a maximum of 10% of the amount of the payment if satisfactory progress has not been made. Exhibit 3, Specifications, at IN-11. The contract included the FAR’s standard clause for default termination of a fixed price construction contract. In pertinent part, this clause provides: If the contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or separable part of the work) that has been delayed.

FAR 52.249-10(a); Exhibit 1.

At a hearing held in this matter on March 24-28, 2009, in Atlanta, Georgia, the parties presented fact and expert witnesses. After the hearing, the parties submitted posthearing briefs over the next few months.

Discussion

Termination for Default

The Government terminated its contract with Global under the provision of the Default clause that allows termination if the contractor’s failure to make progress endangers performance. A termination for default for failure to prosecute the work requires “a reasonable belief on the part of the contracting officer that there was ‘no reasonable likelihood that the [contractor] could perform the entire contract effort within the time remaining for contract performance.’” Lisbon Contractors, Inc. v. United States, 828 F.2d 759, 765 (Fed. Cir. 1987) (quoting RFI Shield-Rooms, ASBCA 17374, et al., 77-2 BCA ¶ 12,714, at 61,735). A termination for failure to make progress usually occurs 7 CBCA 1198

where the contractor has fallen so far behind schedule that timely completion becomes unlikely. Hannon Electric Co. v. United States, 31 Fed. Cl. 135, 143 (1994), aff’d, 52 F.3d 343 (Fed. Cir. 1995) (table). The Government is not required to prove that it was impossible for the contractor to complete performance on time. Lisbon Contractors, 828 F.2d at 765. Rather, a termination for default will be upheld where “a demonstrated lack of diligence indicates that [the Government] could not be assured of timely completion.” Id. (citations omitted).

The initial burden of proving that there are good grounds and solid evidence to support the termination action falls to the VA, which must establish that its decision to terminate for default Global’s right to perform was justified in light of the circumstances as they existed at the time the decision was made. Lisbon Contractors, 828 F.2d at 765; Ranco Construction, Inc. v. General Services Administration, GSBCA 11923, 94-2 BCA ¶ 26,678, at 132,702. The Government can meet its burden by showing that the contractor failed to perform in accordance with the contract terms and that timely performance was beyond its reach. See, e.g., Lisbon Contractors; Florida Engineered Construction Products Corp. v. United States, 41 Fed. Cl. 534, 538-39 (1998); American Sheet Metal Corp. v. General Services Administration, GSBCA 14066, et al., 99-1 BCA ¶ 30,329. In determining whether to terminate a contractor for default, the contracting officer may consider, among other things, the contractor’s failure to meet its own representations concerning the progress of the work, e.g., Guenther Systems, Inc., ASBCA 14032, 72-1 BCA ¶ 9443, at 43,869, and the contractor’s performance history, e.g., Decker & Co. v. West, 76 F.3d 1573, 1581 (Fed. Cir. 1996).

In this case, the Government established that following the issuance of the notice to proceed on October 18, 2004, the contract obligated Global to submit a schedule for approval and to proceed with the work so as to complete the construction within 660 days (later extended through contract modifications). Global failed to submit revised schedules on a timely basis and did not, in response to the cure notice, provide reasonable assurances that it would perform the work remaining within the time frame required by the contract. The Court of Appeals for the Federal Circuit has stated in this regard: When the government has reasonable grounds to believe that the contractor may not be able to perform the contract on a timely basis, the government may issue a cure notice as a precursor to a possible termination of the contract for default. When the government justifiably issues a cure notice, the contractor has an obligation to take steps to demonstrate or give assurances that progress is being made toward a timely completion of the contract, or to explain that the reasons for any prospective delay 8 CBCA 1198

in completion of the contract are not the responsibility of the contractor.

Danzig v. AEC Corp., 224 F.3d 1333, 1337 (Fed. Cir. 2000) (citations omitted). Here, in response to the cure notice, appellant did nothing to assure the Government that it would perform by the contract completion date. In light of these circumstances, the contracting officer justifiably concluded that there was no reasonable likelihood that Global could or would perform the contract work within the time allotted under the contract. Thus, after establishing a final completion date, which Global failed to meet, the contracting officer had adequate justification for terminating the contract for default. Based on this indisputable evidence, the Government met its burden to establish a prima facie case supporting the termination decision. McDonnell Douglas Corp. v. United States, 323 F.3d 1006, 1013-15 (Fed. Cir. 2003); Lisbon Contractors, 828 F.2d at 765; see also NECCO, Inc. v. General Services Administration, GSBCA 16354, 05-1 BCA ¶ 32,902.

Excuses for Nonperformance

Once the Government has established its prima facie case supporting the termination decision, the burden shifts to the contractor to establish the excusability of its nonperformance. See, e.g., DCX, Inc. v. Perry, 79 F.3d 132, 134 (Fed. Cir. 1996); Lisbon Contractors, 828 F.2d at 764. Appellant asserts first that the Government waived the contract completion date. Alternatively, appellant contends that its delayed performance is attributable to the Government’s failure to respond to questions, improper directives, and ambiguity in the contract.

First, Global asserts that the Government waived the contract completion date. As Global noted in its posthearing brief, if a completion date is waived by the contracting officer, “the government can establish a new contract completion date, which will serve as a basis for default termination, either through a bilateral agreement with the contractor or by unilateral decision.” Appellant’s Posthearing Brief at 47 (citing McDonnell Douglas Corp., 323 F.3d at 1019). If the Government opts to act unilaterally, the new date that it sets must be “both reasonable and specific from the standpoint of the performance capabilities of the contractor at the time the notice is given.” Id. The reasonableness of the action turns on what the Government “knew or should have known” at the time it imposed the new schedule. Id.

As noted above, the Government set forth a new completion date after months of delay and after multiple attempts to obtain a realistic revised construction schedule from Global. In opposing the validity of the termination for default, Global contends that only four critical areas of work remained at the time of termination, and the Government’s 9 CBCA 1198

“inability to finalize designs, testing outside the scope of the contract and unwillingness to accept work performed in accordance with flawed specifications” delayed the completion of the contract. Appellant’s Posthearing Brief at 67-68. It contends that even with the four items identified, Global could have completed the job within one week, if respondent had provided appropriate specifications. Id. at 68.

At the hearing, however, Global failed to present any credible evidence showing that the contract contained flawed specifications. Rather, it became apparent during the course of the hearing that Global did not understand contract specifications governing substantial portions of the work, and its confusion created at least some of the delays. For example, Global contended that the contract did not require the cystoscopy rooms to contain radiation shielding with lead-lined walls, nor did it call for testing of the lead shielding. Appellant’s Posthearing Brief at 32-35. Global representatives testified that it interpreted certain shadings on the drawings for the cystoscopy room to indicate that no work should be performed in the area. Transcript at 65, 72 (testimony of appellant’s expert witness Timothy Fitzgerald). This interpretation is inconsistent with the drawings and specifications of the contract, which required the contractor to remove the concrete slabs in one of the cystoscopy rooms and to replace them with a five-inch thick slab and line the walls with lead. See Transcript at 483 (testimony of Roger Templeton (the contracting officer’s technical representative)); Trial Exhibits 6, 7. Among the 100 requests for information (RFIs) submitted by Global, none of the RFIs addressed the cystoscopy room. Transcript at 500. Second, appellant states that multiple constructive changes resulted in excusable delays in contract performance. Under the Excusable Delay clause, the contractor has the burden of proving that the delay was excusable under the terms of the default provision of the contract. FAR 52.249-10(b); Sauer Inc. v. Danzig, 224 F.3d 1340, 1345 (Fed. Cir. 2000). A termination for default may be converted to a termination for convenience of the Government where the contractor can establish that the delay in completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the contractor. FAR 52.249-10(b); Sauer Inc., 224 F.3d at 1345.

In addition, it is well settled that:

When a contractor is seeking extensions of contract time, for changes and excusable delay, which will relieve it from the consequences of having failed to complete the work within the time allowed for performance, it has the burden of establishing by a preponderance of the evidence not only the existence of an 10 CBCA 1198

excusable cause of delay but also the extent to which completion of the contract work as a whole was delayed thereby.

Santa Fe, Inc., VABCA 1943, et al., 84-2 BCA ¶ 17,341, at 86,410. Thus, the contractor must demonstrate that the excusable event caused a delay to the overall completion of the contract, i.e., that the delay affected activities on the critical path. Sauer Inc., 224 F.3d at 1345. The contractor must also establish the extent to which completion of the work was delayed by this excusable cause. Robert P. Jones Co., AGBCA 391, 76-1 BCA ¶ 11,824, at 56,457.

Here, as noted previously, the parties extended the time period of performance multiple times through the issuance of bilateral contract modifications. The thirty-seven contract modifications contained time extensions ranging from periods of one day up to sixty days. At the hearing, appellant’s evidence focused upon the fact that it had expended considerable efforts in its attempts to complete the contract; nonetheless, even after receiving multiple extensions of time, significant work remained to be completed at the time of contract termination.

Appellant contends that the multiple changes to the contract caused inefficiencies and other problems, which should serve to excuse its delayed performance. However, this argument fails to acknowledge the fact that each of the bilateral contract modifications contained the following release language:

This modification represents a complete equitable adjustment for all costs, direct and indirect, associated with the work and time agreed to herein, including but not limited to, all costs incurred to extended overhead, supervision, disruption or suspension of work, labor, inefficiencies, and this change’s impact on unchanged work.

See, e.g., Exhibit 110, Supplemental Agreement No. 2 and Time Extension No. 1, at 3. Therefore, to the extent that the Government issued change orders resulting in contract modifications, these modifications contained time extensions to cover the extra time needed as a result of the changes. By signing the bilateral modifications, the contractor expressly released the Government from any potential impact on its unchanged work resulting from the contract changes.

Ultimately, the contract modifications only extended the contract performance period to May 15, 2007. When, over the next few months, appellant failed to submit a reasonable project schedule for the completion of the work, the contracting officer properly acted to _________________________________

_________________________________ ________________________________

11 CBCA 1198

unilaterally reestablish a contract completion date, issue a show cause notice, issue a cure notice, and, finally, terminate the contract for default. Appellant has failed to present sufficient evidence to meet its burden of establishing by a preponderance of the evidence that an excusable event delayed contract performance.

We conclude that, based upon the evidence presented, the Government established that the contracting officer had a reasonable belief that Global could not perform the entire contract effort within the time remaining for contract performance. Global’s evidence did not meet the standard required for rebutting the Government’s evidence. Accordingly, we find that the contracting officer acted appropriately when she terminated the contract for default.

Decision

The appeal is DENIED.

JERI KAYLENE SOMERS

Board Judge

We concur:

ALLAN H. GOODMAN

Board Judge

CANDIDA S. STEEL

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Global Construction, Inc., CBCA 1198. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.