CBCA 1798

Doracon Contracting, Inc.

Mar 17, 2011Judge PollackGENERAL SERVICES ADMINISTRATION
Not published in the listingDismissed on other grounds

Key Facts

Appellant
Doracon Contracting, Inc.
Respondent agency
GENERAL SERVICES ADMINISTRATION
Judge
Pollack
Case number
CBCA 1798
Decided
Mar 17, 2011The decision states Mar 17, 2011 on its own face, which agrees with the listing.
Decision type
Not published in the listingThe Board's year tables for 2007 through 2014 carry no Type column, so no disposition was published for this decision. It is not missing data and nothing is inferred from the document.
Law firm for the appellant
The decision's own appearances block names no outside firm, which happens when the appellant appeared pro se, through one of its own officers, or through its in-house counsel.
Outcome
Dismissed on other grounds
The appeal is DISMISSED WITH PREJUDICE.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Procedure and sanctionsJurisdiction and timeliness

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Ronald Lipscomb
Doracon Contracting, Inc.
Baltimore, MD
For the appellant
James Vidmar
Logan, Yumkas, Vidmar & Sweeney
Annapolis, MD
For the respondent
Leonard E. Lucas III
Office of General Counsel, General Services Administration
Washington, DC
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision4 pages, 6,268 characters, read from the Board's own documentDecided Mar 17, 2011 on its own faceRespondent GENERAL SERVICES ADMINISTRATION Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Contract Disputes Act1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

DISMISSED WITH PREJUDICE: March 17, 2011

CBCA 1798

DORACON CONTRACTING, INC.,

Appellant,

v.

GENERAL SERVICES ADMINISTRATION,

Respondent.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Ronald Lipscomb, President of Doracon Contracting, Inc., Baltimore, MD; and James Vidmar of Logan, Yumkas, Vidmar & Sweeney, Annapolis, MD, appearing for Appellant. Leonard E. Lucas III, Office of General Counsel, General Services Administration, Washington, DC, counsel for Respondent.

Before Board Judges POLLACK, DRUMMOND, and KULLBERG.

POLLACK, Board Judge.

This dispute arises between Doracon Contracting, Inc. (Doracon or appellant) of Baltimore, Maryland, and the General Services Administration (GSA), involving contract no. GS-11P-07-YM-C0108. The contract called for design and remediation of the GSA’s Central Heating and Refrigeration Plant (CHRP) and West Heating Plant (WHP) oil tank farms located in Washington, D.C.

On November 19, 2009, appellant filed its appeal from a contracting officer’s (CO’s) final decision, where the CO terminated appellant’s contract for default for failure to perform. While the final decision also provided that GSA might purchase the terminated supplies and services against appellant’s account and that appellant would be held liable for 2 CBCA 1798

any excess costs, the decision did not assess re-procurement costs. After receiving the appeal, the Board issued an order providing various filing deadlines, which included calling for appellant to file a complaint. Appellant complied with that order and on December 21, 2009, submitted its original appeal notice and supporting documentation as its complaint. While not presented in the standard legal complaint format, the Board determined that appellant’s filing was susceptible of answer and directed GSA to provide an answer to the filing. In the complaint, appellant not only challenged the default, but also raised dollar claims. On February 14, 2010, the Government filed its answer and as an affirmative defense, GSA stated that all of appellant’s claims, except for its wrongful termination claim, should be dismissed for lack of subject matter jurisdiction. GSA pointed out that appellant had failed to comply with the Contract Disputes Act in regard to these claims.

From that point forward, appellant repeatedly failed to diligently pursue the claim and repeatedly failed to communicate with counsel for GSA and with the Board. After several failed telephone attempts to set up a conference, the Board by order dated May 5, 2010, scheduled a conference to be held on May 11, 2010. In the order, the Board reviewed its concerns and the history as to appellant’s lack of response and communication.

Appellant reacted positively to the order, and on May 11, 2010, the Board held a telephone conference with Government counsel and the president of appellant, Mr. Ronald Lipscomb. In the conference, Mr. Lipscomb advised the Board that he was in the process of securing counsel. Up to that point, Mr. Lipscomb was operating pro se. So as to allow time for a new counsel to become familiar with the case, the Board directed the parties provide it a schedule by June 11, 2010.

Appellant again failed to meet that deadline and on June 28, 2010, the Board issued another order giving appellant until July 7 to contact GSA counsel as to scheduling. Again, appellant did not reply. Accordingly, the Board issued another order on July 29, 2010, stating that “further difficulties, without explanation, will be viewed unfavorably and may constitute a basis for dismissing for failure to prosecute.”

On August 11, 2010, it appeared that matters had changed, and on that date, the Board conducted a telephone conference with counsel for GSA and Mr. James Vidmar, who identified himself as counsel for Doracon. Mr. Vidmar, however, had not filed a formal appearance. In the conference, the Board addressed the issue of the dollar claims and suggested to the parties that while the Board had jurisdiction over the default, it did not have jurisdiction over the dollar claims, which had not been presented to the CO and were not the subject of a CO final decision. The Board proposed a process through which it would hold the termination case in abeyance, allowing appellant to submit its dollar claims and GSA time to consider the claims and issue a final decision, if warranted. The Board directed GSA _______________________________

3 CBCA 1798

counsel and Mr. Vidmar to confer on the above and get back to the Board by September 16, 2010, as to how appellant intended to proceed.

The promise of change, however, did not bear fruit. Appellant again became non-communicative as to GSA counsel and it filed no response by September 16. The Board then issued another order setting a due date of October 15, 2010, for status. When no response was received from appellant or its counsel, the Board, on October 28, 2010, issued an order to show cause. There the Board reviewed appellant’s repeated failure to pursue the appeal and provided that absent appellant providing a detailed response and explanation as to how it intended to proceed, the Board would dismiss for failure to prosecute. This order was sent separately to Mr. Vidmar and to Mr. Lipscomb. Appellant was given until November 9, 2010, to respond. The Board received no reply.

On December 14, 2010, the Government filed a motion to dismiss for failure to prosecute. On December 15, 2010, the Board issued an order that gave appellant until January 4, 2011, to respond to the motion. Again the order was sent to both Mr. Vidmar and Mr. Lipscomb. Again, the Board received no response.

Discussion

Dismissing a case for failure to prosecute is a drastic sanction, which is not done lightly. However, if a party fails to pursue its case, as has been the situation in this appeal, and further repeatedly ignores and fails to honor Board directions, then dismissal is clearly warranted. CCJN & Co., Architects & Planners, P.C. v. General Services Administration, CBCA 821, et al., 10-1 BCA ¶ 34,420. Appellant’s actions in this case justify dismissal with prejudice.

Decision

The appeal is DISMISSED WITH PREJUDICE.

HOWARD A. POLLACK

Board Judge

____________________________ _______________________________

4 CBCA 1798

We concur:

JEROME M. DRUMMOND

Board Judg

H. CHUCK KULLBERG

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Doracon Contracting, Inc., CBCA 1798. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.