In light of the foregoing, the appeal is GRANTED IN PART.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Delay, suspension and accelerationChanges and equitable adjustmentCosts and quantumSmall claims and accelerated procedureJurisdiction and timeliness

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Sean Milani-nia and Ryan Stalnaker
Fox Rothschild LLP
Washington, DC
For the respondent
Neil S. Deol
Office of General Counsel, Department of Veterans Affairs
Decatur, GA
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision5 pages, 10,639 characters, read from the Board's own documentDecided Feb 22, 2016 on its own faceRespondent DEPARTMENT OF VETERANS AFFAIRS Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

2 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Federal Acquisition Regulation1
Agency FAR supplements1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

5 cases this decision cites, grouped by the forum that decided each, in the order it first names them. 3 of them open at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Court of Federal Claims1
Advanced Materials, Inc. v. United States54 Fed. Cl. 207(2002)
Court of Claims and Claims Court3

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

GRANTED IN PART: February 22, 2016

CBCA 4957

HAMILTON PACIFIC CHAMBERLAIN, LLC,

Appellant,

v.

DEPARTMENT OF VETERANS AFFAIRS,

Respondent.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Sean Milani-nia and Ryan Stalnaker of Fox Rothschild LLP, Washington, DC, counsel for Appellant.

Neil S. Deol, Office of General Counsel, Department of Veterans Affairs, Decatur, GA, counsel for Respondent.

WALTERS, Board Judge.

Appellant, Hamilton Pacific Chamberlain, LLC (HPC), a small business entity, has elected to proceed under the small claims procedure of Board Rule 52, Small Claims Procedure, requiring a decision on the appeal within 120 calendar days from receipt of the election. Under the small claims procedure, “[t]he presiding judge may issue a decision, which may be in summary form, orally or in writing. . . . A decision shall be final and conclusive and shall not be set aside except in the case of fraud. A decision shall have no value as precedent.” 48 CFR 6101.52 (2014). The parties, HPC and the Department of Veterans Affairs (VA), also both elected to have this appeal processed under Board Rule 19, Submission on the Record Without a Hearing, and have each submitted briefs and relevant documents which have been admitted into the record.

Background

The instant appeal arises from a three-phase contract awarded by VA to HPC, contract VA245-13-C-0069, for renovation of certain areas of buildings 217 and 500 at the VA Medical Center in Martinsburg, West Virginia. At issue is the pricing of two contract modifications – modifications P00002 and P00006. These modifications correspond to two requests for proposal (RFPs) – RFP 4 and RFP 7. Extensive negotiations between the parties failed to yield agreement as to the equitable adjustments for either modification. VA issued modification P00002, expressly characterizing it as “unilateral modification” in the February 28, 2014, email message to HPC that forwarded the modification document.

Notwithstanding that characterization, the document contained a signature line on the first page for “Paul Hamilton, VP,” HPC’s Executive Vice President, Mr. Paul Hamilton, as well as the following release language on the document’s second page: The consideration represents a complete equitable adjustment for all costs, direct and indirect, associated with the work and time agreed to herein, including but not limited to all costs incurred for extended overhead, supervision, disruption or suspension of work, labor inefficiencies, and this change’s impact on unchanged work.

In his affidavit, Mr. Hamilton indicates he took the signature line with his name to be an “instruction that the Contractor was required to sign the modification.” Mr. Hamilton did sign the modification document, but states that he did not notice the release language on the document’s second page. HPC maintains that Mr. Hamilton had no intention to waive HPC’s claim for the amounts in dispute when signing modification P00002.

Modification P00006, Mr. Hamilton asserts, was likewise provided to HPC for signature, despite the VA’s awareness “that HPC disputed the costs included in that modification.” He signed that modification on July 25, 2014, but, upon discovering release language on the second page (the same language that had appeared on the second page of modification P00002), crossed it out and signed where the language had been excised. HPC submitted a request for equitable adjustment (REA) in January 2015, seeking additional reimbursement for the work under the two modifications. The parties were unable to come to agreement on the REA, and HPC submitted a “certified claim” to the VA contracting officer on May 20, 2015, in the total amount of $99,372.89, to recover the pricing differences between the amounts specified under the modifications and the amounts it had proposed for each modification, as well as additional amounts of alleged damages for delay to its contract performance purportedly caused by VA’s delay in issuing the two modifications, plus $7426 allegedly incurred in preparation of the “certified claim.” By letter dated July 14, 2015, the contracting officer issued a final decision denying the claim in its entirety. HPC timely appealed the denial to the Board.

Discussion

The parties are in agreement that HPC was entitled to an equitable adjustment for the changes effected by modifications P00002 and P00006. They disagree as to the amounts due for each modification. As a preliminary matter, VA asserts that any entitlement to further compensation for modification P00002 was relinquished when Mr. Hamilton executed that modification, including its release language, without noting any exceptions. Under the circumstances presented, it is not at all clear that HPC had any intention of waiving further claim to adjustment under modification P00002, notwithstanding the release language. Mr. Hamilton disclaims any awareness of the inclusion of that language at the time he signed the modification document, and the contracting officer’s having presented modification P00002 as a “unilateral modification” belies the notion that both parties intended it to represent a complete resolution of all claims regarding the additional work. Having dispensed with the argument that further recovery here is barred by reason of accord and satisfaction, we turn to proof of quantum. In Nu-Way Concrete Co. v. Department of Homeland Security, CBCA 1411, 11-1 BCA ¶ 34,636 (2010), the Board provided the following guidance:

An equitable adjustment encompasses the quantitative difference between the reasonable cost of performance without the added, deleted, or substituted work, and the reasonable costs of performance with the addition, deletion, or substitution. J.L. Simmons Co. v. United States, 412 F.2d 1360, 1370 (Ct. Cl. 1969) (citing Bruce Construction Corp. v. United States, 324 F.2d 516, 519 (Ct. Cl. 1963)). “When a party seeks recovery of costs incurred, it has ‘the burden of proving the amount . . . with sufficient certainty so that the determination of the amount . . . will be more than mere speculation.”’ Benmol Corp. v. Department of the Treasury, GSBCA 16374-TD, 05-1 BCA ¶ 32,897, at 162,979 (citing Lisbon Contractors, Inc. v. United States, 828 F.2d 759, 767 (Fed. Cir. 1987) (quoting Willems Industries, Inc. v. United States, 295 F.2d 822, 831 (Ct. Cl. 1961)); Advanced Materials, Inc. v. United States, 54 Fed. Cl. 207, 209 (2002); Twigg Corp. v. General Services Administration, GSBCA 14386, et al., 00-1 BCA ¶ 30,772, at 151,975). “It is true, of course, that the proof of damages need not be exact. A reasonable basis is enough – but some convincing basis must be advanced.” Twigg Corp., 00-1 BCA at 151,976.

Id. at 170,698.

In the present case, in terms of pricing the costs of the changed work, the work added under both modifications and the work deleted in conjunction with modification P00006, HPC posits that its pricing – which is based on actual costs incurred by HPC for its own work and paid to subcontractors and suppliers for the added work, as well as actual credits provided by its subcontractors for work deleted – should trump the cost estimates developed by VA and incorporated into its pricing of the two modifications, since the work has been completed. Case precedent clearly favors the use of actual costs for contract modifications when work has been completed. Indeed, we note that in another Board case, Reliable Contracting Group, LLC v. Department of Veterans Affairs, CBCA 1539, 11-2 BCA ¶ 34,882, VA itself put forth this very proposition: “The VA argues it should not have to pay the labor costs because the claimed amount should be based on actual costs as opposed to estimated costs, since the change has been performed.” Id. at 171,563. In Reliable, VA sought to avoid having to pay for any labor costs, where the contractor had not kept track of actual labor costs as they were being incurred to perform changed work. The Board, in that instance, recognized that labor was part of the additional costs involved and found acceptable the use of cost estimates to price that one cost element. Id. (citing Environmental Safety Consultants, Inc., ASBCA 53485, 05-1 BCA ¶ 32,903, at 163,019). Here, as evidenced in Mr. Hamilton’s affidavit, HPC kept track of its actual labor hours and costs and was able to substantiate with actual cost records each of the other cost elements involved in the performance of both modifications. Under such circumstances, the Board finds HPC to have borne its burden of proving quantum, at least insofar as it pertains to pricing the cost of performing the new work.

By the same token, aside from questions the Board might have regarding the manner in which HPC quantified delay damages in conjunction with the two modifications, HPC has failed to provide proof of entitlement to such damages. HPC argues that it lacks funds to afford a scheduling expert to prove critical path delay, and that the Board should accordingly apply a “jury verdict” approach when addressing delay damages. Whether or not the modifications, as HPC asserts, were aimed at correcting government design deficiencies – and whether or not delays associated with obtaining direction to proceed with the new work would thus be rendered “unreasonable” per se for purposes of recovery of delay damages under the standard Suspension of Work clause, see, e.g., P.J. Dick Inc., VABCA 5597, et al., 01-2 BCA ¶ 31,647, at 156,345, and cases cited therein – HPC has not explained, let alone demonstrated, how any delay to the work under the two modifications caused its overall contract performance time to be extended such that delay damages would even be appropriate. Here, without proof of some delay to the project’s critical path, with or without the use of a scheduling expert, the Board cannot entertain alternative methods for quantifying delay damages. Such damages simply are not recoverable.

Finally, in terms of the claim preparation costs HPC had sought, we note that HPC has properly withdrawn its claim to such costs, acknowledging that their recovery is not allowable under the provisions of the Federal Acquisition Regulation (FAR) Cost Principles, FAR 31.205-47. 48 CFR 31.205-47 (2014).

Applying the above analysis to the dollars HPC had claimed, the Board holds that HPC is entitled to a total of $59,013.96, which amount is derived as follows: Modification P00002 (RFP 4) Cost Difference (Government Estimates versus Actual Costs) $11,897.07 Modification P00006 (RFP 7) Cost Difference 47,116.89 Total Due $59,013.96

Decision

In light of the foregoing, the appeal is GRANTED IN PART. HPC should be paid $59,013.96.

_____________________________

RICHARD C. WALTERS

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Hamilton Pacific Chamberlain, LLC, CBCA 4957. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.