CBCA 5826

CTA I, LLC

Mar 9, 2018Judge ChadwickDEPARTMENT OF VETERANS AFFAIRS
OrderRuled on a motion

Key Facts

Appellant
CTA I, LLC
Respondent agency
DEPARTMENT OF VETERANS AFFAIRS
Judge
Chadwick
Case number
CBCA 5826
Decided
Mar 9, 2018The decision states Mar 9, 2018 on its own face, which agrees with the listing.
Decision type
Order
Law firm for the appellant
Manfredonia Law Offices, LLC
Outcome
Ruled on a motion
CTA would be at risk of seeing its claim for delay costs through September 2016 denied for lack of proof, a result VA would presumably welcome.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Delay, suspension and accelerationProcedure and sanctionsTermination for default

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
John M. Manfredonia and James Petersen
Manfredonia Law Offices, LLC
Cresskill, NJ
For the respondent
Neil S. Deol
Office of General Counsel, Department of Veterans Affairs
Decatur, GA
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision3 pages, 6,301 characters, read from the Board's own documentDecided Mar 9, 2018 on its own faceRespondent DEPARTMENT OF VETERANS AFFAIRS Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

2 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Federal Acquisition Regulation1
Agency FAR supplements1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

4 cases this decision cites, grouped by the forum that decided each, in the order it first names them. 4 of them open at a publisher.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

RESPONDENT’S MOTION GRANTED IN PART: March 9, 2018

CBCA 5826

CTA I, LLC,

Appellant,

v.

DEPARTMENT OF VETERANS AFFAIRS,

Respondent.

John M. Manfredonia and James Petersen of Manfredonia Law Offices, LLC,

Cresskill, NJ, counsel for Appellant.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Neil S. Deol, Office of General Counsel, Department of Veterans Affairs, Decatur, GA, counsel for Respondent.

CHADWICK, Board Judge.

Order

Just after Thanksgiving 2017, the Board adopted the discovery schedule proposed by the parties in this construction case. The schedule included three months of fact discovery, ending in February 2018. Expert discovery is scheduled to end on April 30, 2018. By March 30, 2018, the parties owe the Board a joint proposal of at least two dates and times for a telephonic conference to schedule prehearing filings and a hearing in May or June 2018. On the last day of fact discovery, February 28, 2018, the Department of Veterans Affairs (VA) moved to stay the case “until the project is complete” or, in the alternative, to extend fact discovery by two months, to April 30, 2018, and to adjust other dates in the schedule accordingly. The appellant, CTA I, LLC (CTA), objects. We deny VA’s motion to stay and decline to amend the schedule except as noted below.

VA’s Motion to Stay Until Project Completion CTA is performing the subject contract to rebuild a dialysis center at a VA facility in Richmond, Virginia. CTA states that its current schedule shows completion in November 2018, more than three years late. In this appeal, filed in August 2017, CTA seeks about $2 million in delay, inefficiency, and other costs incurred from the date of the notice to proceed through September 30, 2016. CTA blames VA for mounting delays and plans to submit another claim for additional compensation once the project is finished.

VA’s primary argument for staying the appeal until project completion is that CTA will not be able to prove at a hearing that VA “delayed project completion as a whole,” Versar, Inc., ASBCA 56857, et al., 12-1 BCA ¶ 35,025, at 172,128, unless and until we know the total amount of project delay. Even if this were correct, it would be CTA’s problem, not VA’s. CTA would be at risk of seeing its claim for delay costs through September 2016 denied for lack of proof, a result VA would presumably welcome. In any event, VA’s categorical position is wrong. CTA is entitled to try to prove at this juncture that VA caused compensable delay to activities on the project critical path up to and including September 30, 2016, thereby delaying the future completion date. CTA need not wait until contract completion to litigate its delay claim for that completed, discrete period. Indeed, the very thing that defines work on the critical path is that the work has “no leeway and must be performed on schedule; otherwise, the entire project will be delayed.” Haney v. United States, 676 F.2d 584, 595 (Ct. Cl. 1982) (emphasis added); see Wilner v. United States, 24 F.3d 1397, 1399 n.5 (Fed. Cir. 1994) (en banc). CTA either can prove and quantify Government-caused impact to work on the as-built critical path prior to October 2016, or it cannot. We need not wait until CTA’s performance has ended to find out.

The Suspension of Work clause in this contract specifically directs CTA to submit a claim for delay costs “in writing as soon as practicable after the termination of [a] suspension, delay, or interruption,” not after contract performance. 48 CFR 52.242-12(c) (2013). That the contractor is still performing the contract is obviously not grounds for the contracting officer—or, later, the Board—to deny such a claim. See Industrial Maintenance Services, Inc. v. Department of Veterans Affairs, CBCA 5618, 17-1 BCA ¶ 36,850 (during contract performance, addressing claim for delay costs). Analogously, when a construction contract is terminated for default, the contractor, by definition, did not complete the work, yet may argue that the Government caused critical path delay that excused the contractor’s nonperformance. E.g., McDonnell Douglas Corp. v. United States, 323 F.3d 1006, 1015-17 (Fed. Cir. 2003); Morganti National, Inc. v. United States, 49 Fed. Cl. 110, 132 (2001), aff’d, 36 F. App’x 452 (Fed. Cir. 2002). Delay claims covering discrete periods of contract performance are often consolidated for litigation after a project is complete, but that is by no means a substantive legal requirement as VA implies.

VA also argues that “permitting the current appeal to proceed when Appellant has made clear that a second Claim is forthcoming will cause unnecessary duplication of discovery, witness preparation, and, potentially, more than one hearing.” The Board aims “to secure the just, informal, expeditious, and inexpensive resolution of every case before [it].” Board Rule 1(d) (48 CFR 6101.1(d) (2016)). This appeal is the case before us. VA presents no facts to support its assertion that litigating a future appeal about a different period of contract performance would “duplicat[e]” the litigation of this appeal, as opposed to merely complementing or supplementing the parties’ efforts here. We will not stay the appeal over the appellant’s objection.

VA’s Motion to Extend Discovery

Alternatively, VA requests two additional months of fact discovery. VA explains that it served written discovery requests in mid-January 2018 but received interrogatory responses fifteen days late, on February 28, the last scheduled day of fact discovery, and, as of that date, had not received CTA’s document production, so the agency “cannot determine if it desires to take depositions.” Having agreed last fall to a three-month discovery period, VA should have planned better. It should have served discovery requests in the first month, not the second, if it planned to review CTA’s document production before scheduling depositions. Nonetheless, it will do the Board little good to have VA flying blind at the hearing. Expert discovery runs through April 30. Concurrently with expert discovery, VA may take up to three fact depositions. The schedule entered on November 28, 2017, otherwise remains in place, and the parties should anticipate a hearing in May or June 2018.

Decision

VA’s motion is GRANTED IN PART as stated in the preceding paragraph and otherwise denied.

Kyle Chadwick

Board Judge

This is a verbatim capture of the text layer of the Board's own document in CTA I, LLC, CBCA 5826. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.