CBCA 5997

SBC Archway Helena, LLC

Nov 20, 2018Judge VergilioGENERAL SERVICES ADMINISTRATION
DecisionRuled on a motion

Key Facts

Appellant
SBC Archway Helena, LLC
Respondent agency
GENERAL SERVICES ADMINISTRATION
Judge
Vergilio
Case number
CBCA 5997
Decided
Nov 20, 2018The decision states Nov 20, 2018 on its own face, which agrees with the listing.
Decision type
Decision
Law firm for the appellant
Curran Legal Services Group, Inc.
Outcome
Ruled on a motion
The Board DENIES the agency's motion for summary judgment.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Real property leasesChanges and equitable adjustmentJurisdiction and timeliness

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Diana Parks Curran and Hadeel N. Masseoud
Curran Legal Services Group, Inc.
Johns Creek, GA
For the respondent
Justin S. Hawkins
Office of General Counsel, General Services Administration
Washington, DC
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision4 pages, 6,668 characters, read from the Board's own documentDecided Nov 20, 2018 on its own faceRespondent GENERAL SERVICES ADMINISTRATION Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Agency FAR supplements1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

1 case this decision cites, in the order it first names it. No published copy of any of them was confirmed, so each is shown without a link.

Coley Properties Corp. v. United States593 F.2d 380(Ct. Cl. 1979)

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

RESPONDENT’S MOTION FOR SUMMARY JUDGMENT DENIED:

November 20, 2018

CBCA 5997

SBC ARCHWAY HELENA, LLC,

Appellant,

v.

GENERAL SERVICES ADMINISTRATION,

Respondent.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Diana Parks Curran and Hadeel N. Masseoud of Curran Legal Services Group, Inc., Johns Creek, GA, counsel for Appellant.

Justin S. Hawkins, Office of General Counsel, General Services Administration, Washington, DC, counsel for Respondent.

Before VERGILIO, KULLBERG, and CHADWICK.

VERGILIO, Board Judge.

SBC Archway Helena, LLC (lessor) seeks a sum certain denied by a contracting officer of the General Services Administration (agency) under a lease. The lessor asserts that the agency delayed issuing a notice to proceed with tenant improvements. It seeks to recover various cost increases that it attributes to the delay. The agency moves for summary judgment under Board Rule 8(f), 48 CFR 6101.8(f) (2018), asserting that, even if the agency delay is assumed to have occurred, the claimed amounts are not recoverable costs of performance under the contract and applicable law.

The Board denies the agency’s motion. The agency reads too restrictively the terms of the lease and prior decisions based upon particular contract clauses, claims, and evidence. The lessor does not seek the payment of rent prior to occupancy. The lessor is not foreclosed from demonstrating that agency delays occurred that impacted the lessor’s costs during an extended period of performance prior to or during occupancy.

Findings of Fact

With an award date of January 6, 2015, the agency and lessor entered into a lease that includes a Changes (MAR 2013) and a Disputes (JUL 2002) clause. The lease term is for fifteen years (ten firm) beginning upon acceptance by the agency of the premises. The annual rent consists of amounts for shell rent, real estate taxes, tenant improvements, operating costs, and building specific amortized capital costs. Payments would begin after occupancy. Among other obligations, the lease requires the agency to issue a notice to proceed within fifteen working days following the lessor’s submission of the tenant improvements price proposal, provided the proposal conforms to contract requirements and the parties negotiate a fair and reasonable price for the improvements. For purposes of resolving its motion, the agency posits that it untimely issued that notice to proceed, which delayed the occupancy of the premises. Such a delay could extend the period from lease signing to occupancy and result in a later than anticipated start to rental payments under the lease. The lessor states in its claim that it is entitled to relief under the Disputes clause, seeking payment (with documentation in support) as a matter of right for the agency’s delay in issuing the notice to proceed.

Discussion

The lessor contends that it has and will incur increased costs to perform the lease because of agency delay in issuing the notice to proceed. In particular, it states that the delay has resulted in base amounts (for which it is liable throughout the occupancy) for local property taxes and operating costs higher than would have occurred without the delay, and has required it to expend more on construction loan interest, return on capital, costs incurred as a result of inefficiencies and delays, and legal fees. Additionally, the lessor seeks to recover for operating cost increases, said to arise from increases in the tenant improvement budget that led to increased insurance costs over the life of the lease above those negotiated in the lease.

The standards for summary judgment are established and recognized. JDL Castle Corp. v. General Services Administration, CBCA 4717, et al., 16-1 BCA ¶ 36,249, at 176,857. The agency contends that the lessor’s costs of performance have not increased because of the purported delay such that under the contract’s Changes clause and case law, including Coley Properties Corp. v. United States, 593 F.2d 380 (Ct. Cl. 1979), and JDL, relief is not available. The agency characterizes the claim as implicitly one for lost rent, stating that the lessor seeks compensation for obligations that it would have incurred regardless of the delay.

In the claim, the lessor seeks payment that is not necessarily prohibited under the lease or case law. The lessor does not seek payment of rent. Under the lease, rent obligations begin with occupancy and continue for at least ten years. In substance, the lessor seeks compensation for costs it has paid or will be obligated to pay that are not part of the rental payments. Regarding taxes and operating costs, the lessor maintains that the base rates (for which it is liable under the lease) have increased because of the delay, such that its cost of performance increases. Other costs, relating to construction loan interest, return on capital costs, costs incurred as a result of inefficiencies and delays, and legal fees, it maintains were incurred only because of agency delays. Further, the lessor seeks payment for what it describes as operating cost increases (higher insurances costs) arising from the larger than anticipated at award budget for tenant improvements.

The agency focuses upon language in Coley that states that the purpose of the Changes clause is to compensate for the unanticipated and extra out-of-pocket expenses incurred in performing the contract, and that the loss of expected income during a period of delay does not represent an out-of-pocket expense. 593 F.2d at 385-86. However, the Court recognized the contractor’s ability to recover impact costs arising from a delay. Id. at 385 (“The delay that the changes the government ordered in the postal portion caused Coley in completing the tower portion, with its concomitant additional expenses to Coley in completing the tower, is an item of additional impact cost for which the government is liable . . . .”). In JDL, the Board concluded that the contractor provided no evidence of additional incurred costs arising from an agency delay, and sought damages in the form of delayed rental payments. The Board recognized that delayed rental payments are not compensable under Coley, and the lack of evidence precluded further relief. 16-1 BCA at 176,858. This lessor’s claim is structured differently. This lessor has provided sufficient support of costs it has incurred or will incur because of the alleged delay to move forward with the case. The lessor has the opportunity to demonstrate that these are impact costs and not mere loss of rental income.

Decision

The Board DENIES the agency’s motion for summary judgment. Joseph A. Vergilio

JOSEPH A. VERGILIO

Board Judge

We concur:

H. Chuck Kullberg

Board Judge

Kyle Chadwick

Board Judge

This is a verbatim capture of the text layer of the Board's own document in SBC Archway Helena, LLC, CBCA 5997. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.