CBCA 7145

Team Systems International, LLC

Feb 9, 2023Judge SheridanDEPARTMENT OF HOMELAND SECURITY
DecisionDenied

Key Facts

Appellant
Team Systems International, LLC
Respondent agency
DEPARTMENT OF HOMELAND SECURITY
Judge
Sheridan
Case number
CBCA 7145
Decided
Feb 9, 2023The decision states Feb 9, 2023 on its own face, which agrees with the listing.
Decision type
Decision
Law firm for the appellant
Archer & Greiner, P.C., Venable LLP
Outcome
Denied
The appeal is DENIED.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Contract interpretationJurisdiction and timelinessChanges and equitable adjustment

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
James Y. Boland
Venable LLP
Tysons, VA
For the appellant
Christopher G. Griesedieck and Lindsay M. Reed
Venable LLP
Washington, DC
For the appellant
David W. Carickoff
Archer & Greiner, P.C.
Wilmington, DE
For the respondent
Rafael Lara, Jr. and Jeffrey D. Webb and Sarah Jaward and Matthew Lane
Office of Chief Counsel, Federal Emergency Management Agency, Department of Homeland Security
Washington, DC
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision5 pages, 9,880 characters, read from the Board's own documentDecided Feb 9, 2023 on its own faceRespondent DEPARTMENT OF HOMELAND SECURITY Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Agency FAR supplements1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

8 cases this decision cites, grouped by the forum that decided each, in the order it first names them. 7 of them open at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

DENIED: February 9, 2023

CBCA 7145

TEAM SYSTEMS INTERNATIONAL, LLC,

Appellant,

v.

DEPARTMENT OF HOMELAND SECURITY,

Respondent.

James Y. Boland of Venable LLP, Tysons, VA; Christopher G. Griesedieck and

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Lindsay M. Reed of Venable LLP, Washington, DC; and David W. Carickoff of Archer & Greiner, P.C., Wilmington, DE, counsel for Appellant.

Rafael Lara, Jr., Jeffrey D. Webb, Sarah Jaward, and Matthew Lane, Office of Chief Counsel, Federal Emergency Management Agency, Department of Homeland Security, Washington, DC, counsel for Respondent.

Before Board Judges BEARDSLEY (Chair), DRUMMOND, and SHERIDAN.

SHERIDAN, Board Judge.

The Department of Homeland Security, Federal Emergency Management Agency (FEMA) awarded Team Systems International, LLC (TSI) a contract to provide bottled drinking water. When FEMA decreased the quantity of water bottles ordered by approximately sixty-seven million liters, TSI sought $13,504,320 in restocking fees. The parties seek a decision on the record pursuant to Rule 19 (48 CFR 6101.19 (2021)).

Background

We have previously summarized many of the relevant facts. See Team Systems International, LLC v. Department of Homeland Security, CBCA 7145, 22-1 BCA ¶ 38,045, at 184,754. We repeat facts below only as necessary to explain the basis for our decision. On September 5, 2017, FEMA awarded contract number HFSE70-17-D-0021 (contract) to TSI for the provision of bottled drinking water. Contract line item number (CLIN) 0005, the subject of the instant dispute, states: “Restocking fee – The initial ordered quantity either decreases or the order is cancelled. The fee covers the costs of restocking decreased or cancelled order to the Contractor.” The unit price for CLIN 0005 was $0.20 per liter.

On September 29, 2017, FEMA awarded TSI firm-fixed-price task order HFSE70-17-J-0273 (task order) for the delivery of 80,000,640 liters of bottled drinking water to Puerto Rico, totaling $117,566,730. On November 6, 2017, FEMA issued bilateral modification P0001 (Modification 1), decreasing the quantity of bottled drinking water from 80,000,640 liters to 12,479,040 liters, a reduction of 67,521,600 liters.

Three years later, on October 20, 2020, TSI submitted an invoice to FEMA seeking $13,504,192 in restocking fees under CLIN 0005 due to the 67,521,600 liter reduction. FEMA rejected the invoice. On November 20, 2020, TSI submitted a certified claim to the contracting officer stating that TSI was entitled to a restocking fee of $.20 per liter for the 67,521,600 liter reduction, totaling $13,504,320. The contracting officer issued a final decision rejecting TSI’s argument that it was entitled to $13,504,320.

TSI appealed to the Board, where both parties filed motions for summary judgment.

The Board denied both motions, finding that there were genuine issues of material fact “as to whether TSI suffered actual harm when FEMA reduced the task order quantity.” See Team Systems International, LLC, 22-1 BCA at 184,757. The Board concluded that TSI was not entitled to recover restocking fees unless TSI could “prove that the fees were actually incurred.” Id.

Of importance here are two of TSI’s responses to FEMA’s request for admissions, wherein TSI admits that it has neither paid any restocking fees nor actually restocked any of the bottled water. Specifically, TSI stated that “TSI has not made any ‘restocking fee’ payments to any subcontractors yet” and admitted that “TSI did not physically restock any bottles of water as a result of Modification 1.”

Discussion

TSI urges the Board to look to extrinsic evidence to interpret CLIN 0005 as not requiring the incursion of costs as a trigger. TSI argues that industry custom prohibits TSI from physically restocking bottled water due to health and safety regulations. Therefore, it would be unreasonable to require TSI to physically restock bottled water before receiving a restocking fee.

TSI argues that a prior contractual arrangement between FEMA and TSI sheds light on the parties’ intent as to and mutual understanding of CLIN 0005. FEMA had previously contracted with TSI to provide bottled drinking water. When FEMA decreased the initially ordered quantity of water, TSI sent an invoice for a restocking fee, and FEMA paid the fee without requiring proof of the costs TSI incurred as a result of the decrease. TSI argues that this demonstrates that FEMA understood the restocking fee provision to be akin to an automatic cancellation fee, which is how TSI interprets CLIN 0005.

FEMA maintains that the plain meaning of CLIN 0005 clearly requires TSI to incur costs before any obligation is placed on FEMA to pay a restocking fee, as evidenced by the latter portion of the provision. Simply put, FEMA argues that a restocking fee is only paid if restocking actually occurs. Since TSI did not restock any bottled water and incurred no costs associated with restocking, TSI cannot receive a restocking fee. FEMA also urges the Board to ignore any extrinsic evidence that TSI may present in light of CLIN 0005’s plain meaning.

The issue presented here is solely one of contract interpretation, in that we must only determine whether FEMA was obligated to pay the restocking fee automatically upon its reduction of the ordered quantity of water, or if such obligation only arises if TSI incurred costs as a result of the reduction. When interpreting a contract, the process starts with the plain language of the contract. LAI Services, Inc. v. Gates, 573 F.3d 1306, 1314 (Fed. Cir. 2009); Hunt Construction Group, Inc. v. United States, 281 F.3d 1369, 1373 (Fed. Cir. 2002). If the plain language of the contract is unambiguous, the inquiry ends there. Hunt Construction Group, Inc., 281 F.3d at 1373. Even if the parties propose differing interpretations of contractual language, this does not necessarily mean that the contract is ambiguous. See Tri-Cor, Inc. v. United States, 458 F.2d 112, 126 (Ct. Cl. 1972). Where “the contract’s requirements are unambiguous,” there is “no need to examine extrinsic evidence, such as industry standards.” Master’s Transportation, Inc. v. General Services Administration, CBCA 6565, 22-1 BCA ¶ 38,001, at 184,552 (2021). The interpretation of the contract must afford reasonable meaning to each portion of the contract and not render any portion meaningless. See Jane Mobley Associates, Inc. v. General Services Administration, CBCA 2878, 16-1 BCA ¶ 36,285, at 176,954.

Here, the Board does not need to look beyond the plain meaning of CLIN 0005 to consider the parties’ intent and prior treatment of the restocking fee provision. Such factors are only considered when the plain language of the contract is unclear. The restocking fee provision, CLIN 0005, unambiguously provides that “[t]he fee covers the costs of restocking decreased or cancelled order to the Contractor.” (Emphasis added.) This language makes it clear that costs must be incurred for the provision to be triggered, and TSI incurred no such costs. TSI’s argument that the restocking fee is not intended to cover the costs of physically restocking bottled water would render the second sentence of CLIN 0005 meaningless.

As we previously found in our January 27, 2022 decision, the plain meaning of CLIN 0005 clearly requires that TSI incur costs before the provision is triggered. TSI has provided no evidence that it was charged for or paid a restocking fee. Thus, consistent with our earlier decision, the Board rejects TSI’s argument.

Even if we were to find the contract ambiguous and look to extrinsic evidence, we could not give weight to TSI’s allegation about its prior dealings with FEMA because we have no reliable evidence, such as where the order was in the delivery process, by which to evaluate whether the circumstances of the task orders were similar. Also, while TSI argues that industry custom prohibits restocking, that does not necessarily prohibit a supplier from seeking to recover costs associated with an order cancellation such as this. Yet, it seems apparent from the record that TSI’s suppliers did not charge TSI anything for the cancellation. There is no evidence in the record that TSI or any of its suppliers actually incurred costs associated with the reduction in the number of liters ordered. TSI has never explained what happened to the water or the circumstances under which it was not charged by any of its subcontractors for the reduction.

If we interpreted CLIN 0005 as allowing for restocking fees in a matter such as this one, the claim would still fail. In general, a contractor asserting a claim for an equitable adjustment has the burden of proving “three necessary elements—liability, causation, and resultant injury.” Servidone Construction Corp. v. United States, 931 F.2d 860, 861 (Fed. Cir. 1991) (citing Wunderlich Contracting Co. v. United States, 351 F.2d 956, 968 (Ct. Cl. 1965)). Evidence of some damage resulting from the claim event is necessary to establish entitlement. See Corners & Edges, Inc. v. Department of Health & Human Services, CBCA 648, 07-2 BCA ¶ 33,706 (citing Wilner Construction Co. v. United States, 24 F.3d 1397, 1401 (Fed. Cir. 1994) (en banc); Cosmo Construction Co. v. United States, 451 F.2d 602, 606 (Ct. Cl. 1971)). Here, no such damage is present. Furthermore, to award TSI the claimed $13,504,320 after no costs were incurred would constitute a windfall for TSI and that would be inappropriate. See Hansen Bancorp, Inc. v. United States, 367 F.3d 1297, 1315 (Fed. Cir. 2004) (“Courts should avoid bestowing an unfair windfall on the plaintiff by compensating him or her above and beyond the losses suffered”) (internal quotation marks and citation omitted). As TSI has suffered no damages, TSI is not entitled to recover.

Decision

The appeal is DENIED.

Patricia J. Sheridan

Board Judge

We concur:

Erica S. Beardsley

Board Judge

Jerome M. Drummond

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Team Systems International, LLC, CBCA 7145. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.