CBCA 7186

Purple Heart Heroes LLC

Mar 1, 2022Judge ChadwickDEPARTMENT OF VETERANS AFFAIRS
DecisionDenied

Key Facts

Appellant
Purple Heart Heroes LLC
Respondent agency
DEPARTMENT OF VETERANS AFFAIRS
Judge
Chadwick
Case number
CBCA 7186
Decided
Mar 1, 2022The decision states Mar 1, 2022 on its own face, which agrees with the listing.
Decision type
Decision
Law firm for the appellant
Squire Patton Boggs (US) LLP
Outcome
Denied
The appeal is DENIED.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Real property leasesContract interpretationJurisdiction and timelinessProcedure and sanctions

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
John R. Sharp and Keith Bradley
Squire Patton Boggs (US) LLP
Denver, CO
For the respondent
Hank W. Askins, III
Office of General Counsel, Department of Veterans Affairs
Charleston, SC
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision5 pages, 8,869 characters, read from the Board's own documentDecided Mar 1, 2022 on its own faceRespondent DEPARTMENT OF VETERANS AFFAIRS Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Agency FAR supplements1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

2 cases this decision cites, grouped by the forum that decided each, in the order it first names them. 1 of them opens at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Supreme Court1
Brawley v. United States96 U.S. 168(1877)

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

DENIED: March 1, 2022

CBCA 7186

PURPLE HEART HEROES LLC,

Appellant,

v.

DEPARTMENT OF VETERANS AFFAIRS,

Respondent.

John R. Sharp and Keith Bradley of Squire Patton Boggs (US) LLP, Denver, CO,

counsel for Appellant.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Hank W. Askins, III, Office of General Counsel, Department of Veterans Affairs, Charleston, SC, counsel for Respondent.

Before Board Judges ZISCHKAU, SULLIVAN, and CHADWICK.

CHADWICK, Board Judge.

The parties disagree about how to read a lease. The lessor and appellant, Purple Heart Heroes LLC (PHH), argues that it is owed $142,927 under a “unit price list” appended to the lease. The tenant and respondent, Department of Veterans Affairs (VA), argues that the lease does not by its terms require payment of the disputed amount in the price list. We agree with VA and deny the appeal.

Background

VA awarded PHH the subject lease for office space in Norristown, Pennsylvania, in August 2019. The annual rent for the first five years is $424,215.36 plus fixed operating expenses. The lease includes multiple exhibits. The dispute centers on exhibit L, a ten-page schedule of prices with no title. VA’s solicitation for the lease, issued in April 2019, included a spreadsheet in the same format titled “Unit Price List.” Apparently on that basis, both parties refer to untitled lease exhibit L as the “unit price list.”

The last two rows in exhibit L state:

SHEET TOTAL $374,527.00

SHEET TOTAL, EXCLUDING ITEMS THAT ARE

PART OF TI [tenant improvement] BUDGET $142,927.00 PHH first sent VA the data shown in exhibit L in June 2019, during the solicitation process. PHH’s transmittal email emphasized, “The Sheet Totals . . . provide two amounts—one for the Total Amount, and one for the Total Amount, Excluding items that are part of the TI budget.”

Neither party cites any language in the August 2019 executed lease that cross-references exhibit L or explains its purpose. PHH contends that exhibit L relates to paragraph 1.09 of the lease. Paragraph 1.09 is titled “Tenant Improvement Fee Schedule (Jun 2012)” and states:

For pricing TI costs, the following rates shall apply for the initial build-out of the Space and are included in the total cost of TI.

ARCHITECT ENGINEER FEES: $84,642.25

TOTAL TI CONSTRUCTION COSTS—

INCLUDING A/E [architect/engineer] FEES $1,446,173.27 Other lease terms deal extensively with improvements. Among them, paragraph 1.18 titled “Building Improvements (Mar 2016)” provides, “Before the Government accepts the Space, the Lessor shall complete all Building improvements as identified at design and contained in VA-approved construction drawings.” Paragraph 4.01.F states, “Construction of TIs and completion of other required construction work: The Lessor shall complete all work required to prepare the Premises” within 150 days of receipt of a notice to proceed.

Lease exhibit F is the standard form 1364. It shows the components of the total lease price and indicates that the price includes “build-out costs” totaling $2,545,135.52, which is the sum of $1,446,173.27 in “tenant improvements” (as a “lump sum” not amortized in the rent) and $1,098,962.25 in “shell build-out” costs. (Capitalization altered.) These same two “TI” and “Shell” cost figures are repeated in lease exhibit N, a schedule titled “Tenant Improvements Cost Summary (TICS).”

Surprisingly, neither party tells us whether PHH actually completed the “build-out” and the improvements, or whether VA paid PHH for such deliverables, before VA occupied the building. We see no reason to doubt it.

In January 2021, PHH submitted a certified claim to VA for $142,927, the “sheet total” of exhibit L excluding the tenant improvements budget. PHH argued that VA “explicitly agreed to reimburse PHH for the work and material specified in Exhibit L” and “understood, prior to executing the Lease, that PHH expected to be reimbursed for the work and material specified in Exhibit L.” The contracting officer denied the claim in August 2021, writing in part, “[Given] the clear understanding that . . . the $142,927 is not part of the TI price and that both parties signed and executed the lease identifying the total TI fees as $1,446,173.27, th[e latter] is the . . . not to exceed price.”

PHH promptly filed this appeal. The parties took discovery and submitted the appeal on the written record under Board Rule 19 (48 CFR 6101.19 (2020)).

Discussion

“We apply the usual rules of contract interpretation, which are well settled and without need of elaborate reiteration.” RocJoi Medical Imaging, LLC v. Department of Veterans Affairs, CBCA 6885, 21-1 BCA ¶ 37,899 (internal quotation marks omitted). We summarized the applicable canons in Wageworks, Inc. v. Office of Personnel Management, CBCA 6027 (Jan. 13, 2021).

PHH argues that exhibit L “clarified that a portion of th[e listed] cost was not to be counted, but then it stated explicitly what amount of Exhibit L was, indeed, contract cost not elsewhere accounted [for]. The Exhibit L cost is part of the contract[.]” We disagree. We do not see how a “contract cost” or price can be “part of” a lease absent language in the lease stating why or when the lessee will be obligated to pay the cost or price. The lease recites the annual rent, which was negotiated based on PHH’s agreement to make tenant improvements for a fixed price of $1,446,173.27. PHH points to no mechanism by which a separate amount that was “not . . . counted” when the parties agreed upon the rent for the improved premises could be payable on another basis. In short, the lease nowhere says that VA owes PHH the residual amount of $142,927 identified in the last row of exhibit L. PHH further argues that if we do not agree that the lease clearly requires payment of the disputed amount, “the terms of the [solicitation], the Lease, and the VA’s administration of the process were ambiguous.” PHH writes: It was not until June 2019 that the VA notified PHH that the Unit Price List needed to be submitted and filled in with pricing information. . . . [This was in] the third round of offers. PHH attempted to clear up the confusion created by the VA’s failure to make clear that the Unit Price List values should have already been included in the [Tenant Improvement Costs Summary] by sending an email . . . making clear that PHH understood that it expected that the Unit Price List values would be reimbursed as additional costs.

PHH argues that this course of events created a “latent ambiguity” which we must construe against “the drafting party,” VA. Again, we disagree.

Where a contract “is unambiguous, we follow the plain meaning without considering extrinsic evidence or related arguments.” P.K. Management Group, Inc. v. Secretary of Housing & Urban Development, 987 F.3d. 1030, 1033 (Fed. Cir. 2021); see JBG/Federal Center, L.L.C. v. General Services Administration, CBCA 5506, et al., 18-1 BCA ¶ 37,019, motion for reconsideration denied, 18-1 BCA ¶ 37,087. PHH does not identify and we do not find any relevant ambiguity on the face of the lease itself, which simply cannot be read to say that VA owes PHH an additional $142,927. In the absence of any grounds to consult parol evidence to construe the lease, PHH “waived or forfeited any . . . reliance on the solicitation when it accepted the [terms of the award].” Meridian Global Consulting, LLC v. Department of Homeland Security, CBCA 6906, 21-1 BCA ¶ 37,875 (citing Brawley v. United States, 96 U.S. 168, 173 (1877) (an executed contract “merge[s] all previous negotiations, and is presumed, in law, to express the final understanding of the parties”), and SCM Corp. v. United States, 595 F.2d 595, 598 (Ct. Cl. 1979) (“When legal obligations between the parties will be deferred until the time when a written document is executed, there will not be a contract until that time.”)).

Even if we were to examine pre-award evidence, PHH’s June 2019 email cannot bear the weight that PHH ascribes to it. The email simply noted that the spreadsheet that later became lease exhibit L “provide[d] two amounts” as “sheet totals.” The email did not purport to explain the significance of the residual $142,927 and certainly did not “make clear” that PHH “expected” to “be reimbursed” that amount pursuant to any specific term or language of the lease. We agree with VA that “the lease clearly called out all amounts to be paid by the Government in the properly designated” sections of the lease, and VA “is only required to pay the amounts to which the parties” expressed their agreement in the lease. Finally, to the extent that exhibit L constitutes a “price list” for deliverable improvements, PHH neither alleges nor shows that it made improvements that would have been included for an additional price of $142,927.

Decision

The appeal is DENIED.

Kyle Chadwick

Board Judge

We concur:

Jonathan D. Zischkau

Board Judge

Marian E. Sullivan

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Purple Heart Heroes LLC, CBCA 7186. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.