CBCA 7767

Woirhaye Logging Company, LLC

Mar 12, 2024Judge O’RourkeDEPARTMENT OF AGRICULTURE
DecisionRuled on a motion

Key Facts

Appellant
Woirhaye Logging Company, LLC
Respondent agency
DEPARTMENT OF AGRICULTURE
Judge
O’Rourke
Case number
CBCA 7767
Decided
Mar 12, 2024The decision states Mar 12, 2024 on its own face, which agrees with the listing.
Decision type
Decision
Law firm for the appellant
Schwabe Williamson & Wyatt PC
Outcome
Ruled on a motion
The agency's motion to dismiss for lack of jurisdiction is DENIED.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Jurisdiction and timeliness

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions.

Appearances

For the appellant
Lawson E. Fite
Schwabe Williamson & Wyatt PC
Portland, OR
For the respondent
Jennifer T. Newbold
Office of the General Counsel, Department of Agriculture
Missoula, MT
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision4 pages, 7,904 characters, read from the Board's own documentDecided Mar 12, 2024 on its own faceRespondent DEPARTMENT OF AGRICULTURE Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Cases cited

1 case this decision cites, in the order it first names it. 1 of them opens at a publisher.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

MOTION TO DISMISS FOR LACK OF JURISDICTION DENIED: March 12, 2024

CBCA 7767

WOIRHAYE LOGGING COMPANY, LLC,

Appellant,

v.

DEPARTMENT OF AGRICULTURE,

Respondent.

Lawson E. Fite of Schwabe Williamson & Wyatt PC, Portland, OR, counsel for

Appellant.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Jennifer T. Newbold, Office of the General Counsel, Department of Agriculture, Missoula, MT, counsel for Respondent.

Before Board Judges BEARDSLEY (Chair), SHERIDAN, and O’ROURKE.

O’ROURKE, Board Judge.

Appellant, Woirhaye Logging Company, LLC (Woirhaye), seeks reimbursement of expenses incurred when a wildfire consumed timber that had been cut and skidded but remained in the sale area. Woirhaye argues that the agency was negligent when it reassured Woirhaye that the fire would not reach the sale area, failed to take actions to protect the sale area, and then prohibited access to the sale area when there was still time to remove the timber. The agency contends that the Board lacks subject matter jurisdiction to decide disputes based on negligence because they are tort claims, not contract claims. Because we find a sufficient nexus between the agency’s alleged conduct and its obligations under the contract, we deny the motion.

Background

On September 21, 2021, the agency awarded the Tolan 1 Firewood Timber Sale contract to Woirhaye, under which the Forest Service agreed to sell, and Woirhaye to purchase, cut, harvest, and remove, timber and forest products from a specified area (the sale area). On February 1, 2022, Woirhaye ceased operations for the season.

Woirhaye resumed work for the new season on August 17, 2022. On August 26, it received notice that a fire had started approximately four miles from the sale area. According to Woirhaye, the initial report relayed that the fire was at the end of a single log on flat terrain close to two roads and that it was being monitored. Woirhaye stayed in contact with fire personnel and the timber sale administrator, who reassured Woirhaye that the fire would not reach the timber sale. The Forest Service issued a closure order for the sale area on September 8, 2022, which required Woirhaye to cease operations and leave the sale area for safety reasons. At that point, Worihaye had cut and skidded approximately 75% of the sale area but had not removed all of the processed timber.

By September 28, 2022, the fire had spread to the sale area and consumed the remaining timber product. After the closure order was lifted, Forest Service personnel surveyed the damage and determined that the remaining timber was “severely burned and no longer met minimum saw timber specifications.” The agency notified Woirhaye of its determination and formally closed the timber sale by letter dated December 20, 2022. Woirhaye submitted a claim to the contracting officer in the amount of $48,480 for “out of pocket expenses” incurred to pay for labor, equipment time, mobilization, administrative wages, fuel costs, and costs to process the product that was consumed by the fire. The contracting officer denied the claim on the basis that the contract did not permit recoupment of such expenses. Woirhaye timely appealed the decision to the Board.

Woirhaye’s appeal and complaint blamed the agency for the costs it incurred due to the agency’s failure to take appropriate actions at the outset of the fire, when it could have easily been put out. Woirhaye contends that the agency was negligent because it allowed the fire to grow and expand into the sale area and consume timber that Woirhaye had purchased and cut but had not yet removed. Woirhaye further maintains that twenty days elapsed between the time that it received the notice of closure and when the fire burned through the remaining timber product. Woirhaye stated that it needed only four days to remove the processed timber, but the agency’s actions, and inaction, deprived Woirhaye of that opportunity. Had Woirhaye not received constant reassurance from agency personnel that the fire would not reach the sale, it would have ceased all other operations and removed the remaining cut timber.

After docketing and submission of pleadings, the agency filed a motion to dismiss the appeal for lack of jurisdiction, arguing that Woirhaye’s claim of negligence cannot be heard by the Board because it sounds in tort, not in contract. “Appellant’s claim is not and cannot be that the United States breached the Contract, but that the Government acted negligently. This is a tort claim for which the sole Congressional waiver of sovereign immunity is the [Federal Tort Claims Act].” As such, the agency urges the Board to dismiss the claim for lack of subject matter jurisdiction.

Discussion

“[W]here a plaintiff alleges the existence of a contract between it and the Federal Government, a court or board of contract appeals has jurisdiction to consider the case.” Bear Mountin Cutters, Inc. v. Department of Agriculture, CBCA 7323, 22-1 BCA ¶ 38,189, at 185,460 (quoting Griz One Firefighting, LLC v. Department of Agriculture, CBCA 6358, 20-1 BCA ¶ 37,514, at 182,219); see Engage Learning, Inc. v. Salazar, 660 F.3d 1346, 1353 (Fed. Cir. 2011). There is no dispute that a contract existed between the parties in this case or that Woirhaye’s claim and subsequent appeal were submitted pursuant to that contract. Nevertheless, the Forest Service contends that the Board lacks jurisdiction to hear this dispute because Woirhaye’s claim does not assert a breach of a contractual duty. Rather, the agency couches the dispute as “a traditional tort claim” that speaks to the manner in which a non-contractual duty (managing the fire) was performed. We disagree.

Although the Board lacks jurisdiction to entertain pure claims of negligence which sound in tort, it is widely recognized that the Board can decide an action “that arises primarily from a contractual undertaking even though the loss may have resulted from the negligent manner in which the contract was performed.” Griz One Firefighting, LLC v. Department of Agriculture, CBCA 6358, et al., 22-1 BCA ¶ 38,021, at 184,641 (quoting Goodfellow Brothers, Inc., AGBCA 80-189-3, 81-1 BCA ¶ 14,917, at 73,805). To make this determination, we look for a “direct nexus between the Government’s alleged tortious conduct and its obligations under the contract.” Bear Mountin Cutters, Inc., 22-1 BCA at 185,460 (quoting Asfaltos Panemenos, S.A., ASBCA 39425, 91-1 BCA ¶ 23,315, at 116,919 (1990)); see Innovative (PBX) Telephone Services, Inc. v. Department of Veterans Affairs, CBCA 12, et al., 07-2 BCA ¶ 33,685, at 166,764; TAS Group, Inc. v. Department of Justice, CBCA 52, 07-2 BCA ¶ 33,630, at 166,566-67.

When a contract defines the parties’ obligations and allocates risks between them, a “sufficient nexus” exists between the Government’s alleged tortious conduct and breach of its obligations for the Board to exercise jurisdiction over the appeal. See Bear Mountin Cutters, Inc., 22-1 BCA at 185,460 (where the Board found jurisdiction over a dispute that blamed the Forest Services’ instructions for the loss of heavy equipment destroyed by a wildfire); see also Sierra Pacific Airlines, AGBCA 82-112-1, 82-1 BCA ¶ 15,710 (jurisdiction was established where a pilot complied with a Forest Service representative’s instruction to park an aircraft in a particular location and the engine was damaged by volcanic ash). Here, Woirhaye’s claim arose under its contract with the Forest Service, which imposes obligations, both express and implied, on each party to ensure performance of the contract, including the duty not to hinder performance. Whether a party failed to comply with its duties is a matter to be decided on the merits. We have jurisdiction to consider the dispute.

Decision

The agency’s motion to dismiss for lack of jurisdiction is DENIED. Kathleen J. O’Rourke

KATHLEEN J. O’ROURKE

Board Judge

We concur:

Erica S. Beardsley

Board Judge

Patricia J. Sheridan

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Woirhaye Logging Company, LLC, CBCA 7767. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.