GRANTED IN PART: October 3, 2024
CBCA 7893
HENSEL PHELPS CONSTRUCTION COMPANY,
Appellant,
v.
GENERAL SERVICES ADMINISTRATION,
Respondent.
Hal J. Perloff of Husch Blackwell LLP, Washington, DC, counsel for Appellant.
Jay Bernstein and David C. Charin, Office of General Counsel, General Services
Administration, Washington, DC, counsel for Respondent.
The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.
Before Board Judges RUSSELL, SHERIDAN, and CHADWICK.
SHERIDAN, Board Judge.
On September 19, 2024, the parties jointly moved for entry of a stipulated judgment in the amount of $1,575,000, inclusive of interest and attorneys fees, to be paid by the respondent, General Services Administration (GSA), to the appellant, Hensel Phelps Construction Company (HP), through the permanent, indefinite judgment fund in accordance with 31 U.S.C. § 1304 (2018). See Rule 25(b) (48 CFR 6101.25(b) (2023)). In their joint motion, the parties further stipulated that, pursuant to Rule 25(b)(2), they will not seek reconsideration of, seek relief from, or appeal the Board’s decision awarding the stipulated amount.
Decision
The appeal is GRANTED IN PART. GSA shall pay HP the amount of $1,575,000. Payment may be made pursuant to Rule 31.
Patricia J. Sheridan
Board Judge
We concur:
Beverly M. Russell
Board Judge
Kyle Chadwick
Board Judge
This is a verbatim capture of the text layer of the Board's own document in Hensel Phelps Construction Company, CBCA 7893. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.