No. 08-140

Martin Byrd Quillen, Sr. v. United States

Oct 1, 2009Judge SmithU.S. Court of Federal Claims
Contract disputeJurisdiction and the CDASplit ruling

Key Facts

Plaintiff
Martin Byrd Quillen, Sr.
Case number
No. 08-140The listing writes it as 08-140C, which names every case in a consolidated group.
Decided
Oct 1, 2009
Judge
Smith (from the court's own opinion filename)

Matter

Contract dispute

Matter is contract dispute, bid protest, or both. For a decision read from the curated listing it is the listing's own arrangement; for a decision read from the court's own feed it is the court's Nature of Suit where the official record holds one, and otherwise what the opinion's own opening states. Where the official record is available, the court's own Nature of Suit appears beside it.

Topics

Jurisdiction and the CDA
  • Listed under: Contract Disputes Act; Tucker Act; Jurisdiction; Timeliness; Standing

Topics are an editorial grouping of the decisions read from the curated listing, not a classification by the court. A decision listed under several topics carries all of them. Bid protests carry no topic at all, and neither does a decision read from the court's own feed: no grouping was published for them.

Appearances

For the United States
L. Misha Preheim
United States Department of Justice
Opinion PDF (uscourts.gov) U.S. Court of Federal Claims opinions and ordersThe opinion document is hosted by the U.S. Court of Federal Claims itself, so it is an official copy, and the court's own opinions page is the source of record. The outcome, topics and appearances above are derived deterministically from the court's record and the opinion's own text.

Research This Decision

Create a free account to open this decision in the COFC workspace: the Decision Brief workflow, the filtered browser and the outcome insights over the whole corpus.

COFC Decision Brief

A Workflows Hub brief drafted from this opinion's own text and the authorities it cites, with every citation traced back to the page it came from.

Browse and Insights

The court's opinions filtered by matter, topic, judge, outcome and year, with the outcome dashboard whose every rate divides by merits rulings.

Full Opinion

Full text of the opinion5 pages, 10,540 characters, read from the court's own documentFiled Oct 1, 2009 Decision documentOfficial source: U.S. Court of Federal Claims opinions and orders

Authorities cited

5 authorities read from this opinion's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Tucker Act and the Judicial Code2

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

13 cases this opinion cites, grouped by the forum that decided each, in the order it first names them. 13 of them open at a publisher.

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

1

In the United States Court of Federal Claims

Case No. 08-140C

FOR PUBLICATION

Filed: October 1, 2009

MARTIN BYRD QUILLEN, SR.,

Plaintiff,

* Motion to Dismiss; RCFC 12(b)(1);

v. * Contracts Dispute Act; 41 U.S.C. § 609(a);

* Computing Time; RCFC 6(a)(1

THE UNITED STATES,

Defendant.

Martin Byrd Quillen, Sr., Gate City, Virginia, Pro Se.

The case caption as the opinion prints it. The box the court draws around it is a rule rather than text, so it is not repeated here; every word is.

For the government
L. Misha Preheim
United States Department of Justice
As the opinion writes it

L. Misha Preheim, Trial Attorney, with whom were Gregory G. Katsas, Assistant Attorney General, Jeanne E. Davidson, Director and Reginald T. Blades, Jr., Assistant Director, Commercial Litigation Branch, Civil Division, Department of Justice, Washington, D.C., for Defendant.

L. Misha Preheim, Trial Attorney, with whom were Gregory G. Katsas, Assistant Attorney General, Jeanne E. Davidson, Director and Reginald T. Blades, Jr., Assistant Director, Commercial Litigation Branch, Civil Division, Department of Justice, Washington, D.C., for Defendant.

Opinion and Order

SMITH, Senior Judge:

Defendant filed a Motion to Dismiss pursuant to RCFC 12(b)(1), seeking the dismissal of Plaintiff’s claims as untimely under the twelve-month statute of limitations under the Contracts Dispute Act (CDA), 41 U.S.C. § 609 (2006). Plaintiff argues that he submitted a timely claim to the contracting officer and that the claim he filed in this Court was timely under RCFC 6(a)(1). For the reasons set forth below, the Court hereby DENIES in part and GRANTS in part Defendant’s Motion to Dismiss.

I. Background

On April 13, 2004, the Department of Agriculture Forest Service (Forest Service) awarded Martin Byrd Quillen, Sr. a contract to cut and remove timber in the George Washington and Jefferson National Forests. (Compl. at 1.) The contract terminated on April 30, 2006. (Compl. Ex. A3 at 8.) On February 27, 2007, the Forest Service’s contracting officer (CO) Dale R. Remington issued a final decision letter finding that no timber had been cut or removed from the sale area, and calculating that the Forest Service’s damages were $24,838.87. Due to an account balance with the Forest Service, Mr. Quillen owed $3,338.87 in net damages. (Compl. Ex. A6 at 1-2.)

Mr. Quillen received Mr. Remington’s final decision on March 6, 2007 via certified mail.

(Def.’s Mot. to Dismiss Ex. 1; Pl.’s Resp. at 3.) The final decision stated that Mr. Quillen could appeal the decision to the Civilian Board of Contract Appeals in Washington, D.C. within ninety days from the day he received the decision, or that Mr. Quillen could “bring an action in the U.S. Court of Federal Claims within 12 months of the date” of receipt. (Compl. Ex. A6 at 5.)

Mr. Quillen subsequently mailed a check dated March 13, 2007 to a Forest Service office in Los Angeles in the amount of $3,338.87. He wrote on the memo line: “[payment] remitted in protest and purchaser objects to contents of letter dated 2-27-07 enclosed herewith, as being true and correct.” (Pl.’s Resp. Ex. 6(A)(1) at 1-2.) Almost one year later, on March 7, 2008, Mr. Quillen filed a claim arising from the Forest Service contract in this Court. (Compl. at 1.)

II. Standard of Review

Plaintiff proceeds pro se; therefore, the Court holds his pleadings to a less stringent standard than those drafted by lawyers. See Hughes v. Rowe, 449 U.S. 5, 9 (1980). Nevertheless, claims brought by pro se litigants must satisfy the jurisdictional requirements of this Court. See Saladino v. United States, 62 Fed. Cl. 782, 787 (2004) (citing Kelley v. Sec’y, U.S. Dep’t of Labor, 812 F.2d 1378, 1380 (Fed. Cir. 1987). Thus, the Court will grant a motion to dismiss when a claim lacks subject matter jurisdiction and the non-moving party fails to establish such jurisdiction by a preponderance of the evidence. Leonardo v. United States, 55 Fed. Cl. 344, 346-47 (2003).

III. Jurisdiction

The CDA draws a distinction between a contractor’s: (1) direct appeal of a CO’s final decision; and (2) claim for damages that extend beyond that appeal. Pursuant to 41 U.S.C. § 609(a), this Court has jurisdiction over a contractor’s claim that “directly appeal[s] a final decision of the contracting officer.” Educators Assocs. v. United States, 41 Fed. Cl. 811, 814 (1998); see also K&S Const. v. United States, 35 Fed. Cl. 270, 271-74 (1996).

However, in order to file any other claim arising under the contract in this Court, the CDA requires that the contractor first submit the claim to the CO for a decision. 41 U.S.C. § 605(a); Kenney Orthopedic, LLC v. United States, 83 Fed. Cl. 35, 43 (2008).

IV. Discussion

Mr. Quillen raises two arguments before this Court in support of his timeliness. First, Mr. Quillen’s contends that the statement of protest written on the memo line of his check to the Forest Service was a timely claim to the CO. However, at oral argument, Mr. Quillen seemed to withhold this first argument. (See generally Tr. 12:23-37:17.) Instead he devoted his attention to his second argument, that the claim he filed in this Court is timely under RCFC 6(a)(1) when the rule is applied to the CDA’s twelve-month statutory window. Id.

A. Mr. Quillen’s Payment in Protest Failed to Constitute a Valid Claim

In order to file a valid claim with the CO, the contractor must submit in writing a “clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim.” Contract Cleaning Maint., Inc. v. United States, 811 F.2d 586, 592 (Fed. Cir. 1987). Mr. Quillen’s statement of protest written on the memo line of his check to the Forest Service failed to constitute a claim to the CO under the CDA. In remittance of payment to the Forest Service, it is clear that Mr. Quillen contested the accuracy of the CO’s findings. However, he did not indicate the basis or amount of any claim at that time. (See Pl.’s Resp. Ex. 6(A)(1) at 1-2.) As a result, the CO did not have adequate notice of the basis or amount of the claim. In fact, it is not clear whether the CO ever knew of any objections, since Mr. Quillen’s statement of protest was only written on the memo line of the check that was sent to a Forest Service receiving bank for deposit. (Compl. Ex. A6 at 6, 8.) The notice requirement is not a mere technicality. It serves to make the process of evaluating, settling, and litigating claims both fair and more efficient. Thus, this Court lacks jurisdiction over any of Mr. Quillen’s claims that are unrelated to the direct appeal of the CO’s final decision finding $24,838.87 in damages.

B. Mr. Quillen’s Appeal is Timely: CDA Twelve-Month Statutory Period Under RCFC 6(a)(1)

Although Mr. Quillen failed to submit a valid claim to the CO, he may appeal the CO’s final decision in the United States Court of Federal Claims. This appeal must be filed “within twelve months from the date of the receipt” of the CO’s determination. 41 U.S.C. § 609(a)(1).

In order to establish the date of receipt, the CO must present “[o]bjective indicia of receipt by the contractor.” Borough of Alpine v. United States, 923 F.2d 170, 172 (Fed. Cir. 1991). Based upon the certified mail receipt, the Court holds that Mr. Quillen clearly received the CO’s final decision on March 6, 2007, thus triggering the twelve-month statutory period of limitations on that date. (Def.’s Mot. to Dismiss Ex. 1; Pl.’s Resp. at 3.)

Federal courts generally calculate “one-year” statutory periods of limitations as 365 days. See, e.g., Minasyan v. Mukasey, 553 F.3d 1224, 1228 (9th Cir. 2009). However, the relevant statutory language under the CDA clearly provides for a “twelve month[]” window. 41 U.S.C. § 609(a)(1). The use of “twelve months” instead of “one year” or “365 days” is noteworthy given that other sections of the CDA explicitly calculate statutory periods in terms of days. See, e.g., 41 U.S.C. § 607(g)(1)(A) (“A contractor may appeal such a decision . . . within one hundred and twenty days.”).

Furthermore, some calendar months contain a different number of days. For example, three months does not always mean ninety days, since the number of days within each month differs. Similarly, twelve months does not necessarily suggest a certain number of days, like “one year” does. Therefore, this Court holds that the statutory period in question should be calculated as twelve calendar months instead of 365 days. For example, from March 7, 2007 to April 7, 2007 is one calendar month; March 7, 2007 to May 7, 2007 is two calendar months, and so forth.

With regard to RCFC 6(a)(1), when calculating any statutory period of limitations, the rule provides that the Court shall exclude “the day of the act, event, or default that begins the period.” See SAI Indus. v. United States, 421 F.3d 1344, 1346 (Fed. Cir. 2005). Furthermore, in Wood-Ivey Sys. Corp. v. United States, 4 F.3d 961 (Fed. Cir. 1993), the Federal Circuit extended the close of the CDA’s statutory window from Saturday December 8, 1990 to Monday December 11, 1990 in order to comply with a provision of the RCFC 6(a) that prohibits statutory windows from closing on weekends. See RCFC 6(a)(3). The court held that the extension did not violate the jurisdictional limits of the Court of Federal Claims because RCFC 6 was enacted in accordance with Congressional authorization. Wood-Ivey, 4 F.3d at 964.

Applying the procedural rules to this case, the Court will apply the plain meaning of RCFC 6(a)(1) and the language of 41 U.S.C. § 609(a)(1). Pursuant to RCFC 6(a)(1), the Court calculates the statutory window to exclude March 6, 2007, and counts March 7, 2007 as the first day of the statutory window. From March 7, 2007, the Court allots twelve months to find that the statutory period of limitations closed on March 7, 2008. Accordingly, the Court holds that Mr. Quillen’s appeal of the contracting officer’s decision was timely.

C. This Court Lacks Jurisdiction Over Plaintiff’s Negligence and Due Process Claims

The Defendant, however, correctly notes that this Court lacks jurisdiction over Mr. Quillen’s negligence and due process claims. The Tucker Act does not permit this Court to entertain claims based in tort. 28 U.S.C. § 1491(a)(1) (2006). Moreover, this Court finds no jurisdiction to entertain due process claims, as such claims do not “mandate payment of money by the government.” Le Blanc v. United States, 50 F.3d 1025, 1029 (Fed. Cir. 1995). Therefore, Mr. Quillen’s due process and negligence claims must be dismissed.

V. Conclusion

For the reasons set forth above, this Court GRANTS in part and DENIES in part Defendant’s Motion to Dismiss. The claims advanced by Mr. Quillen that extend beyond a direct appeal of the contracting officer’s final decision, as well as the negligence and due process claims, are DISMISSED for lack of jurisdiction. The parties are directed to file a joint preliminary status report within 45 days from the date of this opinion.

It is so ORDERED.

_________________________

LOREN A. SMITH

Senior Judge

This is a verbatim capture of the text layer of the court's own document in Martin Byrd Quillen, Sr. v. United States. Nothing is summarized or reworded, and the sections run in the order the court wrote them. Two things the page shows are not repeated in the text: the rule the court draws around its caption, and the pagination furniture (the page numbers and the electronic filing stamp printed across the top of each page).

Related Decisions

Same Judge

Same Topic: Jurisdiction and the CDA

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.