No. 08-608

Sitco General & Trading Co. v. United States

Jun 22, 2009Judge HodgesU.S. Court of Federal Claims
Contract disputeJurisdiction and the CDADismissed

Key Facts

Plaintiff
Sitco General & Trading Co.
Case number
No. 08-608The listing writes it as 08-608C, which names every case in a consolidated group.
Decided
Jun 22, 2009
Judge
Hodges (from the court's own opinion filename)
As the opinion prints it
No.08-603C

Matter

Contract dispute

Matter is contract dispute, bid protest, or both. For a decision read from the curated listing it is the listing's own arrangement; for a decision read from the court's own feed it is the court's Nature of Suit where the official record holds one, and otherwise what the opinion's own opening states. Where the official record is available, the court's own Nature of Suit appears beside it.

Topics

Jurisdiction and the CDA
  • Listed under: Contract Disputes Act; Tucker Act; Jurisdiction; Timeliness; Standing

Topics are an editorial grouping of the decisions read from the curated listing, not a classification by the court. A decision listed under several topics carries all of them. Bid protests carry no topic at all, and neither does a decision read from the court's own feed: no grouping was published for them.

Appearances

For plaintiff
James J. Harrington
New York, New York
For the United States
Maame A.F. Ewusi-Mensah
United States Department of Justice
Washington, D.C
Opinion PDF (uscourts.gov) U.S. Court of Federal Claims opinions and ordersThe opinion document is hosted by the U.S. Court of Federal Claims itself, so it is an official copy, and the court's own opinions page is the source of record. The outcome, topics and appearances above are derived deterministically from the court's record and the opinion's own text.

Research This Decision

Create a free account to open this decision in the COFC workspace: the Decision Brief workflow, the filtered browser and the outcome insights over the whole corpus.

COFC Decision Brief

A Workflows Hub brief drafted from this opinion's own text and the authorities it cites, with every citation traced back to the page it came from.

Browse and Insights

The court's opinions filtered by matter, topic, judge, outcome and year, with the outcome dashboard whose every rate divides by merits rulings.

Full Opinion

Full text of the opinion3 pages, 7,859 characters, read from the court's own documentFiled Jun 22, 2009 Decision documentOfficial source: U.S. Court of Federal Claims opinions and ordersThe document states: No.08-603C

Authorities cited

5 authorities read from this opinion's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Tucker Act and the Judicial Code1
Federal Acquisition Regulation1

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

9 cases this opinion cites, grouped by the forum that decided each, in the order it first names them. 9 of them open at a publisher.

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

In the United States Court of Federal Claims

No.08-603C

Filed: June 22, 2009

SITCO GENERAL TRADING AND

CONTRACTING CO., W.W.L., a Kuwait

Corporation, * Motion to Dismiss; RCFC 12(b)(1);

Contract Disputes Act’s

Plaintiff, * Requirement of Written and

Certified Claim to the Contracting

v. * Officer; 41 U.S.C. § 605(a

UNITED STATES OF AMERICA,

Defendant.

The case caption as the opinion prints it. The box the court draws around it is a rule rather than text, so it is not repeated here; every word is.

For the plaintiff
James J. Harrington
New York, New York
As the opinion writes it

James J. Harrington, New York, New York, for plaintiff.

For the government
Maame A.F. Ewusi-Mensah
United States Department of Justice
Washington, D.C
As the opinion writes it

Maame A.F. Ewusi-Mensah, United States Department of Justice, Civil Division, Commercial Litigation Branch, Washington, D.C., for defendant.

James J. Harrington, New York, New York, for plaintiff.

Maame A.F. Ewusi-Mensah, United States Department of Justice, Civil Division, Commercial Litigation Branch, Washington, D.C., for defendant.

Opinion and Order

HODGES, Judge.

The United States Army contracted with plaintiff for construction of concrete barriers on-site at Camp Taji, Iraq. At the conclusion of the contract, the Army ordered the deconstruction of SITCO’s temporary concrete factory. Plaintiff alleges that the Army denied SITCO’s representative access to the base during the deconstruction, causing plaintiff $31 million in damages. The Government moved to dismiss SITCO’s complaint for lack of jurisdiction.

Because plaintiff did not exhaust its administrative remedies before coming to court, we rule for defendant.

Background

The Army contracted with SITCO for the production of concrete barriers in Iraq in June 2004. The contract price was approximately $3.5 million. Plaintiff transported its “ready mix factory” to Camp Taji, Iraq, to fulfill its obligations under the contract. Compl. ¶ 6. The Army arranged for removal of the temporary SITCO factory at contract completion.

Section 605(a) of the Contract Disputes Act states in part: “All claims by a contractor1 against the government relating to a contract shall be in writing and shall be submitted to the contracting officer for a decision.” 41 U.S.C. § 605(a) (2000).

Plaintiff alleges that SITCO representatives were denied access to Camp Taji during the deconstruction process. Without supervision, the factory was left in an “unusable condition,” according to SITCO. Compl. ¶ 11. Plaintiff claims that this denial of access cost SITCO $31 million in damages. The Government moved to dismiss for lack of jurisdiction because plaintiff did not file a claim with the contracting officer as required by the Contracts Dispute Act. See 41 U.S.C. § 602(a) (2000).

Discussion

We have “jurisdiction to render judgment upon any claim against the United States founded either upon the Constitution, or any Act of Congress or any regulation of an executive department, or upon any express or implied contract with the United States . . . not sounding in tort.” 28 U.S.C. § 1491(a)(1) (2006). The Contracts Dispute Act authorizes this court to adjudicate claims for monetary damages arising from disputes regarding any express or implied government contract for the procurement of goods or services. See 41 U.S.C. § 602(a).

Plaintiff must establish jurisdiction by a preponderance of the evidence. Sarang Corp. v. United States, 76 Fed. Cl. 560, 564 (2007). The court is “obligated to assume all factual allegations to be true and to draw all reasonable inferences in plaintiff’s favor” when considering a motion to dismiss for lack of subject matter jurisdiction. Henke v. United States, 60 F.3d 795, 797 (Fed. Cir. 1995). We may consider any materials the plaintiff attaches to its complaint in ruling on a motion to dismiss. Pennington Seed, Inc. v. Produce Exchange No. 299, 457 F.3d 1334, 1342 n.6 (Fed. Cir. 2006).

A plaintiff must exhaust the administrative remedies available under the CDA by1 submitting a claim to and seeking a final decision from the contracting officer before filing suit. Sarang, 76 Fed. Cl. at 564. The Federal Circuit has “enforced the strict limits of the CDA as jurisdictional prerequisites.” England v. The Swanson Group, Inc., 353 F.3d 1375, 1379 (Fed. Cir. 2004). This court’s jurisdiction over a CDA claim “is lacking unless the contractor’s claim is first presented to the contracting officer and that officer renders a final decision on the claim.” Id. Thus, we hear CDA claims only after final decisions by contracting officers.

A claim is “a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract.” 48 C.F.R. § 2.101 (2009). While a claim need not use particular language to satisfy CDA requirements, “the contractor [must] submit in writing to the contracting officer a clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim.” Contract Cleaning Maint. Inc. v. United States, 811 F.2d 586, 592 (Fed. Cir. 1987).

Plaintiff’s counsel did not file his contentions in a brief, but in the form of an affidavit2 signed by A. Luis Suarez, President of the International Division of SITCO General Trading and Contracting Co. We consider Mr. Suarez’s sworn statements to be those of plaintiff SITCO.

A contractor must also certify a claim that exceeds $100,000 in accordance with the CDA. See 41 U.S.C. § 605(c)(1) (2000). This certification must assert that the claim is “made in good faith, that the supporting data are accurate and complete to the best of [the contractor’s] knowledge and belief, that the amount requested accurately reflects the [amount] for which the contractor believes the government is liable, and that the certifier is duly authorized to certify the claim.” 41 U.S.C. § 605(c)(1). The certification requirement cannot be waived. See United Sales, Inc. v. United States, 34 Fed. Cl. 88, 94 (1995).

Plaintiff contends that the Army’s refusal to allow it admission to Camp Taji and the2 Army’s failure to “respond substantively” to SITCO’s complaint filed in this court constitute a “final decision from the contracting officer.” Suarez Aff. ¶ 13. The Government argues that the court does not have jurisdiction to adjudicate this claim because plaintiff did not submit it in writing to the appropriate contracting officer as required by the CDA. Moreover, plaintiff did not certify the claim as required for claims of more than $100,000. These are jurisdictional prerequisites. See 41 U.S.C. § 605(a); England, 353 F.3d at 1379.

SITCO’s contract with the Army states that it is governed by the Contract Disputes Act.

Plaintiff must show that the contracting officer has rendered a final decision on its claim for this court to have jurisdiction. See McNutt v. General Motors Acceptance Corp. of Indiana, 298 U.S. 178, 189 (1936); Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 748 (Fed. Cir. 1988). Plaintiff did not allege and has not provided evidence suggesting that it submitted a properly certified claim to the contracting officer.

Material attached to the Complaint includes correspondence between Mr. Suarez and Army officials demonstrating Mr. Suarez’s difficulties in obtaining permission to return to Camp Taji. Plaintiff contends that the Army’s refusal to allow Mr. Suarez to return to Camp Taji to supervise removal of SITCO’S temporary factory constituted a “constructive denial of the within claim.” Suarez Aff. ¶ 11. The Army’s decision to deny access to Mr. Suarez does not equate to denial of a certified claim to a contracting officer.

Plaintiff argues in the alternative that the Complaint itself was a claim to the contracting officer. A complaint filed in this court does not seek a decision from the contracting officer or meet the other CDA requirements of a “claim.”

Conclusion

This court lacks jurisdiction over SITCO’S complaint because plaintiff did not submit a certified written claim to the contracting officer as required by the Contracts Dispute Act. See Cox v. United States, 26 Cl. Ct. 199, 200-01 (1992). Defendant’s motion to dismiss is GRANTED. The Clerk of the Court will dismiss plaintiff’s complaint without prejudice. No costs.

This is a verbatim capture of the text layer of the court's own document in Sitco General & Trading Co. v. United States. Nothing is summarized or reworded, and the sections run in the order the court wrote them. Two things the page shows are not repeated in the text: the rule the court draws around its caption, and the pagination furniture (the page numbers and the electronic filing stamp printed across the top of each page).

Related Decisions

Same Judge

Same Topic: Jurisdiction and the CDA

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.