No. 10-535

DCS Corp. v. United States

Oct 5, 2010Judge MerowU.S. Court of Federal Claims
Bid protestNo topicFor government

Key Facts

Plaintiff
DCS Corp.
Case number
No. 10-535The listing writes it as 10-535C, which names every case in a consolidated group.
Decided
Oct 5, 2010
Judge
Merow (from the court's own opinion filename)
As the opinion prints it
No. 10-535 C
Filed (per the opinion)
Sep 27, 2010 (the opinion's own filing line, kept beside the listing's date)

Matter

Bid protest

Matter is contract dispute, bid protest, or both. For a decision read from the curated listing it is the listing's own arrangement; for a decision read from the court's own feed it is the court's Nature of Suit where the official record holds one, and otherwise what the opinion's own opening states. Where the official record is available, the court's own Nature of Suit appears beside it.

Topics

No topic

Topics are an editorial grouping of the decisions read from the curated listing, not a classification by the court. A decision listed under several topics carries all of them. Bid protests carry no topic at all, and neither does a decision read from the court's own feed: no grouping was published for them.

Appearances

For plaintiff
John R. Tolle
McLean, Virginia
For the United States
Michael N. O’Connell
United States Department of Justice
Washington, D.C
Other appearance
Donald J. Walsh
Owings Mills, Maryland
Opinion PDF (uscourts.gov) U.S. Court of Federal Claims opinions and ordersThe opinion document is hosted by the U.S. Court of Federal Claims itself, so it is an official copy, and the court's own opinions page is the source of record. The outcome, topics and appearances above are derived deterministically from the court's record and the opinion's own text.

Research This Decision

Create a free account to open this decision in the COFC workspace: the Decision Brief workflow, the filtered browser and the outcome insights over the whole corpus.

COFC Decision Brief

A Workflows Hub brief drafted from this opinion's own text and the authorities it cites, with every citation traced back to the page it came from.

Browse and Insights

The court's opinions filtered by matter, topic, judge, outcome and year, with the outcome dashboard whose every rate divides by merits rulings.

Full Opinion

Full text of the opinion11 pages, 20,053 characters, read from the court's own documentFiled Sep 27, 2010 Decision documentOfficial source: U.S. Court of Federal Claims opinions and ordersThe document states: No. 10-535 C

Authorities cited

2 authorities read from this opinion's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Tucker Act and the Judicial Code1
Federal Acquisition Regulation1

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

10 cases this opinion cites, grouped by the forum that decided each, in the order it first names them. 9 of them open at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

In the United States Court of Federal Claims

No. 10-535 C

(Filed Under Seal September 27, 2010)

(Reissued: October 5, 2010)

DCS CORPORATION,

Plaintiff,

v.

THE UNITED STATES,

Defendant,

and

SURVICE ENGINEERING CORP.

Defendant-Intervenor.

Post-award procurement protest;

Past performance ratings; Best

value award.

The case caption as the opinion prints it. The box the court draws around it is a rule rather than text, so it is not repeated here; every word is.

For the plaintiff
John R. Tolle
McLean, Virginia
As the opinion writes it

John R. Tolle, McLean, Virginia, for plaintiff. Bryan King, McLean Virginia, of counsel.

For the government
Michael N. O’Connell
United States Department of Justice
Washington, D.C
As the opinion writes it

Michael N. O’Connell, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, D.C., for defendant, with whom were Tony West, Assistant Attorney General, Jeanne E. Davidson, Director and Reginald T. Blades, Jr., Assistant Director. Michael G. McCormack, Trial Attorney, Commercial Litigation Division, Air Force Legal Operations Agency, Arlington, Virginia and Jeffrey W. Watson, AAC/JA, Eglin Air Force Base, Florida, of counsel.

Other appearances
Donald J. Walsh
Owings Mills, Maryland
As the opinion writes it

Donald J. Walsh, Owings Mills, Maryland, for intervenor. Timothy Monahan, Owings Mills, Maryland, of counsel. OPINION 1/ Plaintiff, DCS Corporation (“DCS”) commenced this post-award procurement protest action pursuant to 28 U.S.C. § 1491(b)(1), contesting the award of a United States Air Force contract for the SEEK EAGLE Modeling, Analysis, and Tools Support (“SEMATS”) contract. The successful awardee, SURVICE Engineering 1/ This Opinion was originally filed under seal on September 27, 2010, pursuant to the Protective Order filed August 11, 2010. On October 5, 2010, parties to the above-captioned action filed a Joint Stipulation of Redactions. That stipulation is hereby APPROVED and the Redacted Opinion is released for publication. Corporation (“SURVICE”), intervened. Defendant and the intervenor have filed motions to dismiss and all parties have filed motions for judgment on the administrative record of the procurement pursuant to RCFC 52.1. See Bannum, Inc. v. United States, 404 F.3d 1346, 1356 (Fed. Cir. 2005). Oral argument on these motions was held on September 16, 2010.

John R. Tolle, McLean, Virginia, for plaintiff. Bryan King, McLean Virginia, of counsel.

Michael N. O’Connell, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, D.C., for defendant, with whom were Tony West, Assistant Attorney General, Jeanne E. Davidson, Director and Reginald T. Blades, Jr., Assistant Director. Michael G. McCormack, Trial Attorney, Commercial Litigation Division, Air Force Legal Operations Agency, Arlington, Virginia and Jeffrey W. Watson, AAC/JA, Eglin Air Force Base, Florida, of counsel.

Donald J. Walsh, Owings Mills, Maryland, for intervenor. Timothy Monahan, Owings Mills, Maryland, of counsel.

OPINION 1/

Plaintiff, DCS Corporation (“DCS”) commenced this post-award procurement protest action pursuant to 28 U.S.C. § 1491(b)(1), contesting the award of a United States Air Force contract for the SEEK EAGLE Modeling, Analysis, and Tools Support (“SEMATS”) contract. The successful awardee, SURVICE Engineering 1/ This Opinion was originally filed under seal on September 27, 2010, pursuant to the Protective Order filed August 11, 2010. On October 5, 2010, parties to the above-captioned action filed a Joint Stipulation of Redactions. That stipulation is hereby APPROVED and the Redacted Opinion is released for publication.

Corporation (“SURVICE”), intervened. Defendant and the intervenor have filed motions to dismiss and all parties have filed motions for judgment on the administrative record of the procurement pursuant to RCFC 52.1. See Bannum, Inc. v. United States, 404 F.3d 1346, 1356 (Fed. Cir. 2005). Oral argument on these motions was held on September 16, 2010.

Facts

This procurement protest litigation was initiated by the Complaint for Declaratory Judgment, and Preliminary and Permanent Injunctive Relief filed by DCS on August 10, 2010. The relevant portion of the procurement commenced on September 22, 2009, with the issuance by the United States Air Force of its request for proposals (“RFP”), Solicitation No. FA9201-R-0063 (the “Solicitation”), for the SEEK EAGLE Modeling, Analysis, and Tools Support (“SEMATS”) contract.

(Administrative Record, Tab 4 at 115 (“AR 4/115”).) The Air Force created the SEEK EAGLE program as its standard process for “aircraft stores certification,” and designated the SEEK EAGLE Office (the “AFSEO”) as the manager of all certification activities. (AR 2/7; AR 4/240 at 1.2.) The term “aircraft stores” refers to any device intended for internal or external carriage and mounted on aircraft suspension and release equipment. “The mission of the AFSEO is to‘Ensure new war-fighter capabilities through the application and transfer of aircraft-store compatibility expertise.’” (AR 4/240 at 1.2.) “Compatibility expertise includes providing manpower and engineering tools, models, data, rationale, and mission planning software applications necessary to safely load, carry, and employ legacy and developmental stores (e.g. weapons, tanks, pods).” (Id.)

According to the Performance Work Statement (“PWS”) of the RFP, AFSEO sought to “augment its organic (civil service and military), highly technical workforce with contracted skills and expertise to primarily provide modeling and simulation (M&S), analysis and product development support.” (AR 4/240 at 1.0.) “The primary scope of the work is to provide software and data based modeling, analysis and tool/product development support.” (AR 4/240 at 1.1.) The contractor provides the AFSEO with software developers/programmers, engineers, mathematicians, project managers and technicians to augment military and civilian personnel. (Id. at 1.0, 1.1.) The Solicitation is a small business set-aside, subject to FAR 52.219-14 “Limitations on Subcontracting,” with an anticipated five year contract award. “The

proposed subcontractors, the Performance Information Sheet was to be submitted “proportional to the amount of work the subcontractor will be performing.” (Id.) In addition, by using questionnaires “the contracting officer shall seek relevant performance information on all offerors based on (1) the past and present efforts provided by the offeror and (2) data independently obtained from other Government and commercial sources.” (AR 4/227.) The purpose of the past performance evaluation was “to allow the Government to assess the offeror’s ability to perform the effort described in this RFP, based on the offeror’s demonstrated present and past performance.” (Id.) In making this assessment it was provided that “sub-contractors that will perform major or critical aspects of the requirement will be rated as highly as past performance information for the principal offeror.” (AR 4/227 (as changed by AR 5/277 at 6a).)

A Performance Confidence Assessment Group (“PCAG”) of five persons was established to rate each offeror’s ability to perform the efforts described in the SEMATS RFP, based on the offeror’s demonstrated present and past performance.

(AR 2/21, 23/3661.) The quality and extent of the offeror’s performance deemed relevant in accordance with Table 1 of Section M was evaluated by the Government. (AR 4/170.) The relevancy factors in Table 1 of Section M were (AR 4/228):

M agnitudeTechnical Complexity
Very Relevant>=$5M per year and >=40 MYEs per yearANDW ork required management of personnel performing work in Engineering plus 2 of the following areas: Mathematical/Statistical Analysis, Computer Science or Information Technology Support
Relevant>=$3M per year and >=25 MYEs per yearANDW ork required management of personnel performing work in Engineering plus 1 of the following areas: Mathematical/Statistical Analysis, Computer Science or Information Technology Support
Somewhat Relevant>=$1M per year and >=10MYEs per yearANDW ork required management of personnel performing work in 1 of the following areas: Engineering , Mathematical/Statistical Analysis, Computer Science or Information Technology Support.
Not Relevant<$1M per year or <10 MYEs per yearORW ork required management of personnel performing work in none of the following: Engineering, Mathematical/Statistical Analysis, Computer Science or Information Technology Support
Table as printed on page 4 of the court's own document, set from where the page puts its cells rather than from the text layer, which prints one cell per line. The words are the document's and nothing is totalled or interpreted. The page sets no heading apart on this one, so none is shown; a table that runs on from the previous page begins mid-data.

Note: If the number of Man Year Equivalents (MYEs) is not available, the magnitude will be determined on dollar value.

The rating scale for each past performance effort identified by the offerors together with the additional efforts collected from questionnaires sent by the PCAG was (AR 4/181):

Exceptional (E): Performance met and exceeded many of the contractual requirements that benefitted the customer. The contractor accomplished the assessed factors and sub factors with few minor problems. Corrective actions taken by the contractor were highly effective.

Very Good (VG): Performance met and exceeded some of the contractual requirements that benefitted the customer. The contractor accomplished the assessed factors and sub factors with some minor problems. Corrective actions taken by the contractor were effective.

Satisfactory (S): Performance met the contractual requirements. The contractor accomplished the assessed factors and sub factors with some minor problems. Corrective actions taken by the contractor were satisfactory.

M arginal (M ): Performance does not meet some contractual requirements. The contractual performance of factors and sub factors reflected a serious problem. Contractor has not yet fully implemented corrective actions. The proposed actions were only marginally effective or not identified.

Unsatisfactory (U): Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the factors and sub factors contains serious problem(s) for which the contractor’s corrective actions were ineffective.

Note: Your comments on unsatisfactory ratings and other ratings where problems have not been satisfactorily resolved are critical to our past performance evaluation. Please take the time to provide comments.

Not Applicable (N/A): The contractor was not required to perform in the assessed area. A “N/A” response does not affect the evaluation, either favorably or unfavorably.

The assessment process was designed to “result in an overall performance confidence assessment of Substantial Confidence, Satisfactory Confidence, Limited Confidence, No Confidence, or Unknown Confidence, as defined in Table 2.” (AR 4/227.)

Table 2 in Section M provided descriptions as follows (AR 4/228): Rating Description

SUBSTANTIAL CONFIDENCE Based on the offeror’s performance record, the government has a high expectation that the offeror will successfully perform the required effort.

SATISFACTORY

CONFIDENCE

Based on the offeror’s performance record, the government has an expectation that the offeror will successfully perform the required effort.

LIMITED CONFIDENCE Based on the offeror’s performance record, the govern has a low expectation that the offeror will successfully perform the required effort.

NO

CONFIDENCE

Based on the offeror’s performance record, the government has no expectation that the offeror will be able to successfully perform the required effort.

UNKNOW N CONFIDENCE No performance record is identifiable or the offeror’s performance record is so sparse that no confidence assessment rating can be reasonably assigned.

As set forth in the AR at 18/1640-42, the PCAG considered 20 contracts providing past performance information for DCS and its subcontractors, of which 18 met some degree of relevancy. Six past contracts were performed by DCS, of which three were deemed “Very Relevant,” one was deemed “Relevant,” and two were deemed “Somewhat Relevant.” Subcontractor “Kratos,” listed to perform 20% of the SEMATS contract, had one very relevant past contract. Subcontractor “ManTech,” listed to perform 15% of the SEMATS contract, had five very relevant, two relevant and four somewhat relevant past contracts. Two of DCS’ very relevant past contracts were rated “E” and one was rated “VG.” The relevant past DCS contract was rated “E.” One somewhat relevant past DCS contract was rated “VG” and the other was rated “S.” Two of ManTech’s five very relevant past contracts were rated “E” and three were rated “VG.” One of ManTech’s somewhat relevant contracts was rated “E” with the remaining contracts rated “VG.” Kratos’ very relevant past contract was rated “E.”

Based on this past performance record of DCS and its subcontractors the five members of the PCAG determined that “[t]he government has a high expectation that the offeror will successfully perform the required effort.” (AR 18/1641.) A “Substantial Confidence” assessment for the DCS proposal was provided. (Id.)

As set forth in the AR at 19/2433-35, the PCAG considered 36 contracts providing past performance information for SURVICE and its subcontractors of which 27 met some degree of relevancy. Three past contracts were performed by SURVICE of which two were deemed relevant and one was deemed somewhat relevant. Subcontractor “ARA,” listed to perform 10% of the SEMATS contract, had two very relevant, one relevant, and four somewhat relevant past contracts.

Subcontractor “Wyle,” listed to perform 30% of the SEMATS contract, had 10 very relevant, two relevant and five somewhat relevant past contracts. The three SURVICE past contracts were rated “E.” The two ARA very relevant past contracts were rated “E.” ARA’s relevant past contract was rated “S ” and two of its four

The Source Selection Authority awarded the SEMATS contract to SURVICE on his determination that its proposal “provides the United States Air Force (USAF) the best overall value.” (AR 24/3690.)

Discussion

As an initial jurisdictional matter, plaintiff must show that it has standing to bring this post-award procurement protest. Info. Tech. & Applications Corp. v. United States, 316 F.3d 1312, 1319 (Fed. Cir. 2003); Myers Investigative & Sec. Servs., Inc. v. United States, 275 F.3d 1366, 1369 (Fed. Cir. 2002). As an offeror for the procurement at issue, with direct economic interest affected by the award, and having a substantial chance of obtaining the award were its protest asserting a prejudicial failure to evaluate past performance information, to be sustained, plaintiff has shown the requisite standing. Am. Fed’n of Gov’t Employees v. United States, 258 F.3d 1294, 1302 (Fed. Cir. 2001); Rex Serv. Corp. v. United States, 448 F.3d 1305, 1307-08 (Fed. Cir. 2006); Weeks Marine, Inc. v. United States, 575 F.3d 1352, 1359 (Fed. Cir. 2009).

Plaintiff contests the validity of the Air Force’s “Substantial Confidence” assessment for SURVICE, asserting that a correct evaluation would have resulted in only a “Satisfactory Confidence” assessment with a resulting favorable impact on DCS’ chances of obtaining the award. Upon examination, it is concluded that plaintiff has not established a viable basis for its assertions as to evaluation error. The RFP concerning past-performance material for the SEMATS contract provided, “[o]nly references for the same or similar type contract desired.” (AR 4/170.) The RFP also provided that for the quality and satisfaction rating for contracts completed in the past five years, “[p]rovide any information currently available (letters, metrics, customer surveys, independent surveys, etc.) which demonstrates customer satisfaction with overall job performance and quality of completed product for same or similar type contract.” (Id.) Plaintiff asserts that “same or similar type-contract” equates to dollar value and as the award amount for the SEMATS contract was approximately $65 million over five years, a “same or similar” contract would have to be approximately $13 million for each year. (Pl.’s Opp’n Br. 21, ECF No. 25.) Plaintiff notes that DCS submitted more past performance submissions with yearly dollar values of at least $13 million than SURVICE submitted. (Id.)

However, the RFP for the SEMATS contract stated, “[t]he Government will evaluate the quality and extent of offeror’s performance deemed relevant in accordance with Section M, Table 1.” (AR 4/170.) The standard provided in Table 1 provided that the highest relevance, “Very Relevant,” is assigned to past performance efforts having a yearly dollar value of at least $5 million. (AR 4/228.) If plaintiff wished to contest the RFP provision commencing “Very Relevant” past performance at efforts having at least $5 million in annual receipts, it was required to do so before final proposals were received from the offerors. Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308, 1313 (Fed. Cir. 2007). The cases plaintiff cites do not support the application of a relevance standard contrary to a specific provision in the applicable specifications and concern situations where there was a significant absence of similarity. That is not the circumstance involved in the SEMATS procurement. Plaintiff does not challenge any of the past performance ratings reached by the Air Force under the relevance standards set forth in Table 1 of Section M.

Plaintiff also asserts that SURVICE in its past performance submissions did not comply with the RFP provision stating that, “[i]f subcontractors are proposed, provide Performance Information Sheets for subcontractors proportional to the amount of work the subcontractor will be performing.” (AR 4/170.) It appears to be plaintiff’s contention that SURVICE’s past performance subcontractor submissions were not proportional because SURVICE was to perform 60% of the SEMATS contract and its subcontractors were to perform 40% of the contract, but SURVICE submitted 3 past performance efforts it had performed and 4 past performance efforts one of its subcontractors had performed. An examination of the Administrative Record reveals that a past performance effort submitted by SURVICE for its subcontractor Wyle was comprised of two contracts, one for a 4-year period and a sole source “bridge” contract thereafter for less than one year. (AR 13/1295.) In its consideration of SURVICE’s proposal, the Air Force noted that “[t]wo of the Wyle contracts were one effort; base contract with bridge.” (AR 22/3640.) Therefore SURVICE’s past performance submission was comprised of 3 of its own past performance efforts and 3 of its subcontractor’s past performance efforts.

In addition the PCAG located a number of additional past performance efforts performed by SURVICE’s subcontractors and relied on their performance ratings as well as SURVICE’s three past performance efforts with “Exceptional” performance ratings, in reaching the “Substantial Confidence” assessment for the SURVICE proposal. (AR 23/3675.) The RFP clearly provided that “sub-contractors that will perform major or critical aspects of the requirement will be rated as highly as past performance information for the principal offeror.” (AR 4/227 (as changed by AR 5/277 at 6a).) This was accomplished for the SURVICE proposal. (AR 23/3675.) It is recognized that the past performance information evaluated for DCS’s proposal contained more than three efforts performed by DCS, but this in no way detracts from the evaluation of SURVICE’s proposal. Each proposal was evaluated separately by the PCAG. The PCAG, complying fully with evaluation criteria, did not require any specific number of past performance efforts to reach a substantial confidence assessment. If such an assessment can be reached on the basis of three past performance efforts, additional submissions of equal quality could be considered surplusage.

Again, the cases relied upon by plaintiff provide little relevance to the facts of this case. For example, reliance is placed on DCMS-ISA, Inc. v. United States, 84 Fed. Cl. 501, 508 (2008), where a procurement was canceled upon a determination that the offerors had no similar past experience so that performance reliance would be placed in subcontractors. In the present case, the Air Force placed substantial confidence on the past performance by SURVICE of three efforts with excellent performance ratings plus a number of past efforts by its subcontractors with excellent or very good performance ratings. The PCAG’s assessment of “Substantial Confidence” for SURVICE’s proposal has a rational basis in the supporting past performance information evaluated. The court may not substitute its judgment for the Air Force’s expertise in regard to this evaluation. See Ala. Aircraft Indus., Inc.-Birmingham v. United States, 586 F.3d 1372, 1376 (Fed. Cir. 2009).

Given the determination that the Air Force’s substantial confidence assessment for SURVICE’s proposal will not be overturned, there is no basis on which the best value award to SURVICE could be rejected. Having the same substantial confidence assessment as DCS, the substantially lower price offered by SURVICE provides a rational basis for the Air Force’s award decision.

Conclusion

The decision to award the SEMATS contract to SURVICE may be set aside if it lacked a rational basis or if the decision involved a clear and prejudicial violation of statute, regulation or procedure. Emory Worldwide Airlines, Inc. v. United States, 264 F.3d 1071, 1085-86 (Fed. Cir. 2001). None of these events occurred in the Air Force procurement action for the SEMATS contract. The award decision was well within the discretion afforded the agency in a best value negotiated procurement. Galen Med. Assocs., Inc. v. United States, 369 F.3d 1324, 1330 (Fed. Cir. 2004). Accordingly, it is ORDERED:

(1) That Defendant’s and SURVICE’s Motions for Judgment on the Administrative Record are GRANTED; (2) Plaintiff’s Motions for Judgment on the Administrative Record and for Injunctive Relief are DENIED; and (3) Defendant’s and SURVICE’s Motions to Dismiss are DENIED.
s/ James F. Merow
James F. Merow
Senior Judge

This is a verbatim capture of the text layer of the court's own document in DCS Corp. v. United States. Nothing is summarized or reworded, and the sections run in the order the court wrote them. Two things the page shows are not repeated in the text: the rule the court draws around its caption, and the pagination furniture (the page numbers and the electronic filing stamp printed across the top of each page).

Related Decisions

Same Matter: Bid protest

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.