No. 15-1070

MWH Global, Inc. v. United States

Aug 31, 2017U.S. Court of Federal Claims
Contract disputeProcedure, discovery and evidenceProcedural ruling

Key Facts

Plaintiff
MWH Global, Inc.
Case number
No. 15-1070The listing writes it as 15-1070 C, which names every case in a consolidated group.
Decided
Aug 31, 2017
As the opinion prints it
No. 15-1070C

Official Record (govinfo)

Judge of record
Judge Thomas C. Wheeler
Nature of suit
Contract - Service (CDA) (114)
Cause
civil

From U.S. court records published by the Government Publishing Office, matched to this decision only where the official record's issue date equals the decision date above. Open the official record.

Matter

Contract dispute

Matter is contract dispute, bid protest, or both. For a decision read from the curated listing it is the listing's own arrangement; for a decision read from the court's own feed it is the court's Nature of Suit where the official record holds one, and otherwise what the opinion's own opening states. Where the official record is available, the court's own Nature of Suit appears beside it.

Topics

Procedure, discovery and evidence
  • Listed under: Procedure; Discovery; Privilege; Evidence; Sanctions; Consolidation; Transfer; Stays; Motions for Reconsideration

Topics are an editorial grouping of the decisions read from the curated listing, not a classification by the court. A decision listed under several topics carries all of them. Bid protests carry no topic at all, and neither does a decision read from the court's own feed: no grouping was published for them.

Appearances

For plaintiff
Stephen W. Pickert
For the United States
Joseph A. Pixley
United States Department of Justice
Opinion PDF (uscourts.gov) U.S. Court of Federal Claims opinions and ordersThe opinion document is hosted by the U.S. Court of Federal Claims itself, so it is an official copy, and the court's own opinions page is the source of record. The outcome, topics and appearances above are derived deterministically from the court's record and the opinion's own text.

Research This Decision

Create a free account to open this decision in the COFC workspace: the Decision Brief workflow, the filtered browser and the outcome insights over the whole corpus.

COFC Decision Brief

A Workflows Hub brief drafted from this opinion's own text and the authorities it cites, with every citation traced back to the page it came from.

Browse and Insights

The court's opinions filtered by matter, topic, judge, outcome and year, with the outcome dashboard whose every rate divides by merits rulings.

Full Opinion

Full text of the opinion3 pages, 6,752 characters, read from the court's own documentFiled Aug 31, 2017 Decision documentOfficial source: U.S. Court of Federal Claims opinions and ordersThe document states: No. 15-1070C

Authorities cited

1 authority read from this opinion's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Contract Disputes Act1

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

2 cases this opinion cites, grouped by the forum that decided each, in the order it first names them. 2 of them open at a publisher.

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

In the United States Court of Federal Claims

No. 15-1070C

(Filed: August 31, 2017)

Motion for Leave to Take

Additional Depositions;

RCFC 30(a); RCFC 26(b);

Prejudice to Non-Movant.

MWH GLOBAL, INC.,

Plaintiff,

v.

THE UNITED STATES,

Defendant.

The case caption as the opinion prints it. The box the court draws around it is a rule rather than text, so it is not repeated here; every word is.

For the plaintiff
Stephen W. Pickert
As the opinion writes it

Stephen W. Pickert, with whom was Anthony R. Kovalcik, Moye, O’Brien, Pickert & Dillon, LLP, Maitland, Florida, for Plaintiff.

For the government
Joseph A. Pixley
United States Department of Justice
As the opinion writes it

Joseph A. Pixley, with whom were Chad A. Readler, Acting Assistant Attorney General, Robert E. Kirschman, Jr., Director, and Franklin E. White, Jr., Assistant Director, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington, D.C., and Kim J. Sabo, Of Counsel, U.S. Army Corps of Engineers, Chicago, Illinois for Defendant.

Stephen W. Pickert, with whom was Anthony R. Kovalcik, Moye, O’Brien, Pickert & Dillon, LLP, Maitland, Florida, for Plaintiff.

Joseph A. Pixley, with whom were Chad A. Readler, Acting Assistant Attorney General, Robert E. Kirschman, Jr., Director, and Franklin E. White, Jr., Assistant Director, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington, D.C., and Kim J. Sabo, Of Counsel, U.S. Army Corps of Engineers, Chicago, Illinois for Defendant.

Order on Motion for Leave to Take Additional Depositions

WHEELER, Judge.

On September 25, 2015, MWH Global, Inc. (“MWH”) brought this action under the Contract Disputes Act challenging the U.S. Army Corps of Engineers’ (“USACE”) final decision that MWH owes the USACE $11,317,141.76 in damages resulting from an alleged negligent design defect in a water management project in Chicago. Dkt. No. 1. The parties are currently engaged in discovery, which began in May 2016.

Currently before the Court is the Government’s motion for leave to take additional depositions beyond the ten allowed under RCFC 30(a)(2)(A)(1). Specifically, the Government wishes to depose “three additional fact witnesses, one of whom is a current or former MWH employee, who has relevant information as it pertains to damages” and two fact witnesses associated with the construction contractor for the project. Gov.’s Mot. at 3. The Government believes it can take these additional depositions by the September 29, 2017 deadline for the completion of fact discovery. Id. at 4.

“Questions of the scope and conduct of discovery are, of course, committed to the discretion of the trial court.” Florsheim Shoe Co. v. United States, 744 F.2d 787, 797 (Fed. Cir. 1984). However, pursuant to RCFC 26(b)(2) a court should consider whether:

(i) the discovery sought is unreasonably cumulative or duplicative, or is obtainable from some other source that is more convenient, less burdensome, or less expensive; (ii) the party seeking discovery has had an ample opportunity . . . to obtain the information sought; or (iii) the burden or expense of the proposed discovery outweighs its likely benefit . . . .

System Fuels, Inc. v. United States, 73 Fed. Cl. 206, 218 (2006) (quoting RCFC 26(b)(2)). The party seeking discovery must specify “what information it seeks” and explain why “the information sought would not be obtainable from some other source that is more convenient, less burdensome, or less expensive.” Id. In System Fuels, the Government “[did] not directly address the criteria on which this court must base its decision, leaving this court to glean scattered kernels of pertinent information . . . .” Id.

As in System Fuels, the Government offers no information in its motion that would allow the Court to evaluate the Rule 26(b)(2) factors. The Government here merely asks for more depositions and asserts that “there can be no question of any prejudice to MWH by our reasonable request to take additional depositions” without any explanation. Gov.’s Mot. at 4. As MWH points out, the Government’s motion provides no information from which the Court can reasonably assess the necessity of additional depositions. Pl.’s Resp. at 1-3. In its reply, the Government names the individuals it would like to depose and what relevant information it believes the witnesses possess, however the Government still does not address the RCFC 26(b)(2) factors. Gov.’s Reply at 1-3. The mere fact that individuals have relevant information tells the Court nothing about whether the discovery sought is “unreasonably cumulative”, burdensome, or whether the Government had “ample opportunity” to obtain the sought information in another way. RCFC 26(b)(2). The Government has not even provided “scattered kernels of pertinent information” for the Court to evaluate. System Fuels, 73 Fed. Cl. at 218.

Further, as of the filing of its motion, the Government has only taken six depositions, five of which were MWH witnesses and one of which was a former employee for the construction contractor, and are currently scheduling depositions for “four MWH witnesses”. Gov.’s Mot. at 3. Therefore, in total, the Government seeks to depose ten MWH witnesses and three witnesses affiliated with the construction contractor. This is unnecessary and overly cumulative, especially given that five of the ten proposed MWH witnesses have not yet been deposed. Instead of seeking to expand its allowable discovery, the Government should carefully and efficiently conduct its ten depositions as provided by the Rules of this Court.

Finally, MWH has convinced the Court that it would suffer prejudice if the Court granted the Government’s motion. Initially, the Government stated that it intended to take no more than ten depositions in accordance with RCFC 30. Dkt. No. 13, at 10. The Government then waited until July 19, 2017 to begin taking depositions and did not request to depose any MWH witnesses until July 2017. Pl.’s Resp. at 1-2. Meanwhile, MWH was taking depositions in accordance with RCFC 30 by “wait[ing] to see what a witness testified to before turning to the next witness.” Id. at 1. According to MWH, “[h]ad the Government not waited until July 2017 to try to take more depositions than the Rule allowed, MWH would have approached discovery in a much different fashion.” Id. It is clear that MWH assumed that each party would take only ten depositions and conducted its discovery with that limitation in mind. Id., Ex. A (email from MWH’s counsel to the Government’s counsel dated August 17, 2017) (“You have already taken [six] out of the [ten] depositions you get. Which four of those listed do you wish to take?”); see also Id. (“We do oppose [a motion for leave to take additional depositions] especially since you waited so long to make it known that this would be your intention.”). Therefore, MWH’s ability to properly develop its claim would be affected by allowing the Government to take additional depositions this late in discovery.

For these reasons, the Government’s motion is DENIED. Fact discovery shall end on September 29, 2017 and each party is limited to ten depositions. As is proper procedure in any deposition, the Government will have the opportunity to cross-examine any witness MWH deposes but any cross-examination of a witness not included in the Government’s ten allowable depositions is limited to the scope of MWH’s direct examination.

IT IS SO ORDERED.

s/ Thomas C. Wheeler

THOMAS C. WHEELER

Judge

This is a verbatim capture of the text layer of the court's own document in MWH Global, Inc. v. United States. Nothing is summarized or reworded, and the sections run in the order the court wrote them. Two things the page shows are not repeated in the text: the rule the court draws around its caption, and the pagination furniture (the page numbers and the electronic filing stamp printed across the top of each page).

Related Decisions

Same Topic: Procedure, discovery and evidence

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.