No. 15-1197

U.S. Security Associates, Inc. v. United States

Nov 13, 2015U.S. Court of Federal Claims
Bid protestNo topicFor government

Key Facts

Plaintiff
U.S. Security Associates, Inc.
Case number
No. 15-1197
Decided
Nov 13, 2015
As the opinion prints it
No. 15-1197C
Filed (per the opinion)
Nov 2, 2015 (the opinion's own filing line, kept beside the listing's date)

Official Record (govinfo)

Judge of record
Senior Judge Eric G. Bruggink
Nature of suit
Contract - (Post Award) Injunction (140)
Cause
civil

From U.S. court records published by the Government Publishing Office, matched to this decision only where the official record's issue date equals the decision date above. Open the official record.

Matter

Bid protest

Matter is contract dispute, bid protest, or both. For a decision read from the curated listing it is the listing's own arrangement; for a decision read from the court's own feed it is the court's Nature of Suit where the official record holds one, and otherwise what the opinion's own opening states. Where the official record is available, the court's own Nature of Suit appears beside it.

Topics

No topic

Topics are an editorial grouping of the decisions read from the curated listing, not a classification by the court. A decision listed under several topics carries all of them. Bid protests carry no topic at all, and neither does a decision read from the court's own feed: no grouping was published for them.

Appearances

For plaintiff
Jerry A. Miles
Rockville, MD
For the United States
Amanda L. Tantum
United States Department of Justice
Washington, DC
Other appearance
Washington
Opinion PDF (uscourts.gov) U.S. Court of Federal Claims opinions and ordersThe opinion document is hosted by the U.S. Court of Federal Claims itself, so it is an official copy, and the court's own opinions page is the source of record. The outcome, topics and appearances above are derived deterministically from the court's record and the opinion's own text.

Research This Decision

Create a free account to open this decision in the COFC workspace: the Decision Brief workflow, the filtered browser and the outcome insights over the whole corpus.

COFC Decision Brief

A Workflows Hub brief drafted from this opinion's own text and the authorities it cites, with every citation traced back to the page it came from.

Browse and Insights

The court's opinions filtered by matter, topic, judge, outcome and year, with the outcome dashboard whose every rate divides by merits rulings.

Full Opinion

Full text of the opinion8 pages, 15,989 characters, read from the court's own documentFiled Nov 2, 2015 Decision documentOfficial source: U.S. Court of Federal Claims opinions and ordersThe document states: No. 15-1197C

Authorities cited

1 authority read from this opinion's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Federal Acquisition Regulation1

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

In the United States Court of Federal Claims

No. 15-1197C

(Originally filed: November 2, 2015)

(Reissued: November 13, 2015)1

U.S. SECURITY ASSOCIATES, INC.,

Plaintiff,

v.

THE UNITED STATES,

Defendant,

and

SECURIGUARD, INC.

Intervenor.

P ost-aw ard bid p ro test;

p r e l i m i n a r y i n j u n c t i o n ;

likelihood of success on the

merits; fixed price; lowest

priced technically acceptable

offer.

The case caption as the opinion prints it. The box the court draws around it is a rule rather than text, so it is not repeated here; every word is.

For the plaintiff
Jerry A. Miles
Rockville, MD
As the opinion writes it

Jerry A. Miles, Rockville, MD, for plaintiff, with whom was Ann M. Golski.

For the government
Amanda L. Tantum
United States Department of Justice
Washington, DC
As the opinion writes it

Amanda L. Tantum, Trial Attorney, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, with whom were Benjamin C. Mizer, Principal Deputy Assistant Attorney General, Robert E. Kirschman, Jr., Director, and Steven J. Gillingham, Assistant Director, for defendant. William S. Meyers and Sigmund Adams, Office of the General Counsel, Administrative Office of the United States Courts, of counsel. Keir X. Bancroft, Washington, DC, with whom was J. Scott Hommer, This opinion was first issued under seal to afford the parties an opportunity1 to propose redaction of protected information. Those redactions are indicated by brackets.

Other appearances
Washington
As the opinion writes it

Washington, DC, for intervenor.

Jerry A. Miles, Rockville, MD, for plaintiff, with whom was Ann M.

Golski.

Amanda L. Tantum, Trial Attorney, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, with whom were Benjamin C. Mizer, Principal Deputy Assistant Attorney General, Robert E. Kirschman, Jr., Director, and Steven J. Gillingham, Assistant Director, for defendant. William S. Meyers and Sigmund Adams, Office of the General Counsel, Administrative Office of the United States Courts, of counsel.

Keir X. Bancroft, Washington, DC, with whom was J. Scott Hommer, This opinion was first issued under seal to afford the parties an opportunity1 to propose redaction of protected information. Those redactions are indicated by brackets.

Washington, DC, for intervenor.

Order and Opinion

BRUGGINK, Judge.

Pending in this bid protest is plaintiff’s motion for preliminary injunctive relief. The matter is fully briefed. Subsequently, plaintiff filed a2 notice of voluntary dismissal under RCFC 41(a)(1) along with a motion for relief from the protective order in place in this case, in order for plaintiff to file a new protest at the Government Accountability Office (“GAO”). The motion3 indicates that, because access to the administrative record in this case suggests what plaintiff’s counsel considers to be additional grounds beyond those of which plaintiff was aware at the time of the GAO protest, it wishes dispensation from the protective order here in order to return to GAO to advance those new arguments there. Oral argument on both motions was scheduled for October 29, 2015. At the beginning of oral argument, plaintiff notified the court that it intended to withdraw its notice of dismissal and proceed with the present suit. After oral argument, plaintiff affirmed that intent by filing a notice of withdrawal of its notice of dismissal and withdrawal of its motion for relief from the protective order. As announced at oral argument, and for the reasons set out below, we deny the request for a preliminary injunction.

PROCEDURAL AND FACTUAL BACKGROUND4

Plaintiff, U.S. Security Associates, Inc., was one of several holders of a Schedule 84 contract for security services with the General Services Administration (“GSA”). On June 19, 2015, the Administrative Office of the United States Courts (“AO”), acting under that contract, issued a Request for Quotations (Solicitation No. 061915) for security services at the Thurgood Marshall Building in Washington, DC. Those services are currently, and were in the recent past, subject of a different contract issued by the Architect of the Plaintiff also applied simultaneously for a temporary restraining order. By2 order dated October 16, 2015, that application was denied without prejudice to consideration of the motion for a preliminary injunction.

Plaintiff proceeded initially at GAO and was unsuccessful.3 The facts are drawn from the Administrative Record4 United States Capital, which has authority to act with respect to the Marshall Building. The incumbent on that contract is CMI Management, Inc. (“CMI”). Plaintiff is the primary subcontractor for CMI under the incumbent contract. After an extension triggered by plaintiff’s protest at GAO, the incumbent contract is currently scheduled to expire on October 31, 2015.

The RFQ proceeds under Federal Acquisition Regulation (“FAR”) Subpart 8.4, which permits GSA to set up blanket purchase agreements (“BPA”) and for authorized entities, such as the AO, to place task orders under the BPA. The task orders can be competed among the holders of the BPA, as the AO did here. The RFQ contemplated award of a fixed price task order to a single awardee for one year with options potentially extending another four and a half years. The award would be made to the “lowest price technically acceptable” (“LPTA”) offeror. Offerors were asked to submit their quotations in two volumes, one setting out their price proposal and the second in a technical proposal. The procurement would then proceed in three steps. All offerors who had self-certified that they had “at least 5 years security service experience in a Level IV facility,” AR 43, were permitted to proceed to step two. In step two, the overall lowest price offer was identified. Then in step three, only that lowest price offer was evaluated to determine if the offeror’s technical proposal was acceptable as measured against three evaluation factors by the Technical Evaluation Team (“TET”): Key Personnel, Staffing Plan, and Past Performance. If the lowest price proposal was acceptable, the search was over and a contract awarded. If not, then the TET advanced to consideration of the next lowest price offer.

With respect to key personnel, offerors were required to submit at least one resume for two senior positions: On-Site Security Manager and Captain. The staffing plan needed to reflect how the staff would be recruited, selected, and allocated over the required posts. In order to satisfy the past performance requirement, offerors were to submit information concerning five contracts of similar size, scope and complexity in a comparable facility that had been performed within the past three years or were being currently performed. The AO received quotations from [ ] entities, including plaintiff and the intervenor, Securiguard, Inc. All [ ] met the requirement of certifying five years of security experience. The contracting officer then determined that Securiguard offered the lowest proposed price. The TET therefore evaluated Securiguard’s proposal and concluded that it was technically acceptable in all areas and had no deficiencies. Securiguard was awarded the task order on September 8, 2015.

Plaintiff filed a protest with GAO on September 14, and the statutory stay attached. In order to maintain security services under the incumbent contract, the Architect of the Capitol extended the contract with CMI through the end of October. When the GAO denied the protest on October 8, the AO instructed Securiguard to begin transition preparation with the goal of commencing performance on November 1, 2015. Plaintiff filed its complaint in this court on October 13, 2015, along with a motion for a temporary restraining order and permanent injunction.

Discussion

To obtain preliminary injunctive relief pursuant to Rule 65 of the Rules of the United States Court of Federal Claims (“RCFC”), plaintiff must persuade the court that it is likely to succeed on the merits of the protest, that it will be irreparably harmed if an injunction is not awarded, that the harm to it exceeds the harm to the United States and interested third parties if an injunction is not granted, and that the public interest militates in favor of an injunction. Because the matter is before us on a request for a preliminary injunction, even if we deny the request, plaintiff may still proceed to seek a permanent injunction. Similarly, if we grant the injunction now, the government and intervenor may still argue that a permanent injunction is unwarranted. There is no prejudicial effect to a grant or denial. Nevertheless,5 while the harm and public interest considerations obviously will differ in considering preliminary or permanent relief, there is no blinking the fact that, with respect to the merits, consideration of the likelihood of success now requires the court to look at the same arguments it likely will consider when the request for permanent relief is addressed.

Defendant’s opposition to the request for a preliminary injunction raises a subject matter jurisdiction defense and a defense of lack of standing, which, in this context, also implicates jurisdiction. Normally we would have to satisfy ourselves of subject matter jurisdiction and plaintiff’s standing in order to proceed. Three factors persuade us that it is unnecessary to resolve those questions now, however. First, we are confronted with an issue of whether interim relief is appropriate, not a permanent resolution of the merits of the case. Second, the question of subject matter jurisdiction, as even defendant concedes, is not entirely straight forward. And the matter of standing is factually muddled because there is at least a theoretical possibility that, if See discussion below at page 7.5

plaintiff is successful in knocking Securiguard out of the competition, the agency would have to advance to the next lowest price offeror, which in turn could be rejected, and so on, [ ]. Third, we believe that consideration of one of the elements of plaintiff’s burden of proof–likelihood of success on the merits–is so weighted against plaintiff that it is unnecessary to address, much less resolve, these otherwise preliminary issues at this point. We therefore forego, for now, consideration of the government’s jurisdictional defenses (as well as two of the three other factors which plaintiff must establish) and move to the likelihood of plaintiff’s success on the merits. Plaintiff must show that the AO’s decision was either arbitrary or capricious or not in accordance with law. There is no hint of the latter in plaintiff’s briefing, so the question is whether plaintiff is likely to persuade us that the AO’s actions were arbitrary or capricious. Under any circumstances, of course, a protestor faces a tough hurdle in overcoming the deference accorded the actions of the procuring agency. Here, however, we conclude that there is nothing close to a telling argument.

Plaintiff contends that the agency improperly treated Securiguard’s proposal as technically acceptable because [ ].

AR 43. The contracting officer was [ ], however, because Securiguard [

], AR 343, The contracting officer [ ]. As counsel for defendant pointed out at oral argument, the RFQ merely called for a description of the offeror’s code of conduct, and it was only in the RFQ’s explanation of what the evaluation team would look at that there was a reference [ ]. We can understand why the CO was disinclined to reject the lowest price offer on this ground. [ ]. Rejecting the proposal for failure to submit it with the proposal would arguably have been arbitrary in light of the failure to spell out the requirement in the RFQ.

Plaintiff’s real argument is that Securiguard’s price is too low. Thus the agency should have concluded that Securiguard’s price proposal was not responsive to the RFQ and that its price was neither fair nor reasonable. FAR 9.103(a) dictates that awards can only be made to responsible offerors, which, as plaintiff points out, means that the prospective contractor is “able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments.” 48 C.F.R. 9.104-1(b) (2015). In a nutshell, plaintiff argues that Securiguard’s price is so low that it could not possibly attract or keep enough qualified staff to perform the contract and that it will run afoul of the collective bargaining agreement (“CBA”) applicable to the employees it would hire. Plaintiff argues that the solicitation requires compliance with the prevailing wage rates as set by the CBA. Plaintiff argues that the awardee’s6 prices are too low, at least in the contract’s out years, for the intervenor to pay the hourly wages it proposes and still satisfy the CBA.

Plaintiff compares the CBA-mandated pay rates with intervenor’s proposed labor rates for the options years, [ ]. Plaintiff avers that its own historical negotiations with the union have involved [ ]. It concludes that the purported inconsistency between intervenor’s proposed price and the CBA (or plaintiff’s experience with it) demonstrate that the proposal was not responsive.

As the government points out, however, and as GAO concluded, there are problems with this argument. First, plaintiff cannot, and indeed has not attempted to draw into question the AO’s determination that Securiguard’s technical proposal was acceptable. We must therefore assume that Securiguard will perform as advertised. Second, plaintiff cannot demonstrate that Securiguard will not pay its employees legally required wages. Indeed, Securiguard’s proposal plainly states that it will comply with the CBA and that it will pay prevailing wages. AR 363. Nor can plaintiff demonstrate that the7 There was discussion during oral argument about whether the CBA had been6 specifically incorporated by the solicitation. Plaintiff is correct that a Questions and Answers sheet attached to solicitation amendment two implies that the first amendment had incorporated the CBA. AR 166. What is not stated there, however, or anywhere else in the solicitation, is a requirement that the offeror promised to charge the government the full CBA rate for every year.

Also in contrast to plaintiff’s allegations regarding Securiguard’s intent not7 (continued...)

resumes of the key personnel are inadequate for the work required. What plaintiff wants the court to do is step into the shoes of the agency and substitute its judgment that the technical plan is inadequate in light of Securigaurd’s proposed rates for future option years. If the TET was satisfied, the court is in no better position to judge the adequacy of proposals. In any event, if Securiguard promises to do the work required, its ultimate satisfaction of that requirement is a matter of contract performance. Plaintiff’s doubts in that regard are not a basis for enjoining performance. In the context of a fixed price procurement, price risk is borne by the offeror not the agency.8 In short, there is no basis for disagreeing with the agency’s conclusion that the technical proposal was acceptable. While plaintiff suggested the problem could be cast in terms of price realism, or reasonableness, we disagree. The prices were in a relatively close range, and clearly plaintiff does not contend that the intervenor’s price was too high.

Even if the likelihood of success were not great, we would entertain an argument that there is such a high likelihood of permanent and irreparable harm to the movant that the likelihood of success is not determinative. Such a risk has plainly not been established here, however. The court is committed to determine promptly whether plaintiff is ultimately successful on the merits, and, given plaintiff’s promptness in requesting injunctive relief, it will not be prejudiced in obtaining permanent injunctive relief, if it is warranted. The only injury we can see, therefore, is that plaintiff might miss out on as much as one month’s net profit. That relatively minor financial harm certainly does (...continued)

to follow the CBA are several statements earlier in Securiguard’s Technical Proposal, [

]. In both instances, Securiguard confirmed its intent to follow the applicable CBA. See AR 338, 339.

In fact, inervenor affirmed in paragraph 8 of its pricing narrative that it bears8 the price risk, stating that it [

]. AR 365. The very next paragraph offers [ ]. Id.

not outweigh the fact that the government has shown that it is paying more on a monthly basis to keep the incumbent in place.

Conclusion

Because plaintiff has not established a likelihood of success on the merits nor shown irreparable harm, its motion for a preliminary injunction is denied. The parties are directed to confer and propose by November 9, 2015, jointly if possible, a schedule for resolution of the merits through cross-motions for judgment on the administrative record. Oral argument can be held on December 1, 2, or 3, 2015.

s/Eric G. Bruggink

ERIC G. BRUGGINK

Judge

This is a verbatim capture of the text layer of the court's own document in U.S. Security Associates, Inc. v. United States. Nothing is summarized or reworded, and the sections run in the order the court wrote them. Two things the page shows are not repeated in the text: the rule the court draws around its caption, and the pagination furniture (the page numbers and the electronic filing stamp printed across the top of each page).

Related Decisions

Same Matter: Bid protest

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.