No. 21-1102

Apt Research, Inc. v. United States

Jul 14, 2021U.S. Court of Federal Claims
Bid protestNo topicFor government

Key Facts

Plaintiff
Apt Research, Inc.
Case number
No. 21-1102The listing writes it as 21-1102 C, which names every case in a consolidated group.
Decided
Jul 14, 2021
As the opinion prints it
No. 21-1102C
Filed (per the opinion)
Jun 22, 2021 (the opinion's own filing line, kept beside the listing's date)

Official Record (govinfo)

Judge of record
Judge Lydia Kay Griggsby
Nature of suit
Contract - (Post Award) Injunction (140)
Cause
civil

From U.S. court records published by the Government Publishing Office, matched to this decision only where the official record's issue date equals the decision date above. Open the official record.

Matter

Bid protest

Matter is contract dispute, bid protest, or both. For a decision read from the curated listing it is the listing's own arrangement; for a decision read from the court's own feed it is the court's Nature of Suit where the official record holds one, and otherwise what the opinion's own opening states. Where the official record is available, the court's own Nature of Suit appears beside it.

Topics

No topic

Topics are an editorial grouping of the decisions read from the curated listing, not a classification by the court. A decision listed under several topics carries all of them. Bid protests carry no topic at all, and neither does a decision read from the court's own feed: no grouping was published for them.

Appearances

For plaintiff
Emily J. Chancey
Maynard, Cooper & Gale, P.C.
Huntsville, AL
For the United States
Michael D. Austin
United States Department of Justice
DC, Cpt
For the United States
Carlos Pedraza
United States Army
For the United States
Daniel R. Forman
Crowell & Moring, LLP
Washington, DC
Opinion PDF (uscourts.gov) U.S. Court of Federal Claims opinions and ordersThe opinion document is hosted by the U.S. Court of Federal Claims itself, so it is an official copy, and the court's own opinions page is the source of record. The outcome, topics and appearances above are derived deterministically from the court's record and the opinion's own text.

Research This Decision

Create a free account to open this decision in the COFC workspace: the Decision Brief workflow, the filtered browser and the outcome insights over the whole corpus.

COFC Decision Brief

A Workflows Hub brief drafted from this opinion's own text and the authorities it cites, with every citation traced back to the page it came from.

Browse and Insights

The court's opinions filtered by matter, topic, judge, outcome and year, with the outcome dashboard whose every rate divides by merits rulings.

Full Opinion

Full text of the opinion17 pages, 29,273 characters, read from the court's own documentFiled Jun 22, 2021 Decision documentOfficial source: U.S. Court of Federal Claims opinions and ordersThe document states: No. 21-1102C

Authorities cited

8 authorities read from this opinion's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Tucker Act and the Judicial Code2
Administrative Procedure Act1

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

29 cases this opinion cites, grouped by the forum that decided each, in the order it first names them. 28 of them open at a publisher; the rest are shown without a link because no published copy of them was confirmed.

19 more.

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

In the United States Court of Federal Claims

BID PROTEST

No. 21-1102C

Filed Under Seal: June 22, 2021

Reissued: July 14, 2021*

APT RESEARCH, INC.,

Plaintiff,

v.

THE UNITED STATES,

Defendant,

v.

ARES TECHNICAL SERVICES

CORPORATION,

Defendant-Intervenor.

Post-Award Bid Protest; Judgment Upon

the Administrative Record, RCFC 52.1;

Best Value.

The case caption as the opinion prints it. The box the court draws around it is a rule rather than text, so it is not repeated here; every word is.

For the plaintiff
Emily J. Chancey
Huntsville, AL
As the opinion writes it

Emily J. Chancey, Of Counsel, J. Dale Gipson, Of Counsel, Maynard, Cooper & Gale, P.C., Huntsville, AL, for plaintiff.

For the government
Michael D. Austin
United States Department of Justice
DC, Cpt
As the opinion writes it

Michael D. Austin, Trial Attorney, Deborah A. Bynum, Assistant Director, Martin F. Hockey, Jr., Acting Director, Brian M. Boynton, Acting Assistant Attorney General, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, Cpt.

Carlos Pedraza
United States Army
As the opinion writes it

Carlos Pedraza, Of Counsel, United States Army, for defendant.

Daniel R. Forman
Washington, DC
As the opinion writes it

Daniel R. Forman, Counsel of Record, James G. Peyster, Of Counsel, Crowell & Moring, LLP, Washington, DC, for defendant-intervenor. * This Memorandum Opinion and Order was originally filed under seal on June 22, 2021. ECF No. 47. The parties were given an opportunity to advise the Court of their views with respect to what information, if any, should be redacted from the Memorandum Opinion and Order. On July 14, 2021, plaintiff filed a joint status report on behalf of the parties indicating that no redactions are necessary. ECF No. 49. And so, the Court is reissuing its Memorandum Opinion and Order, dated July 14, 2021, as the public opinion.

W. Brad English, Counsel of Record, Jon D. Levin, Of Counsel. Emily J. Chancey, Of Counsel, J. Dale Gipson, Of Counsel, Maynard, Cooper & Gale, P.C., Huntsville, AL, for plaintiff.

Michael D. Austin, Trial Attorney, Deborah A. Bynum, Assistant Director, Martin F.

Hockey, Jr., Acting Director, Brian M. Boynton, Acting Assistant Attorney General, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, Cpt.

Carlos Pedraza, Of Counsel, United States Army, for defendant.

Daniel R. Forman, Counsel of Record, James G. Peyster, Of Counsel, Crowell & Moring, LLP, Washington, DC, for defendant-intervenor.

* This Memorandum Opinion and Order was originally filed under seal on June 22, 2021. ECF No. 47. The parties were given an opportunity to advise the Court of their views with respect to what information, if any, should be redacted from the Memorandum Opinion and Order. On July 14, 2021, plaintiff filed a joint status report on behalf of the parties indicating that no redactions are necessary. ECF No. 49. And so, the Court is reissuing its Memorandum Opinion and Order, dated July 14, 2021, as the public opinion.

Memorandum Opinion and Order

GRIGGSBY, Judge

I. Introduction

Plaintiff, APT Research, Inc. (“APT”), brings this post-award bid protest action challenging the United States Missile Defense Agency’s (“MDA”) evaluation process and decision to award a contract to support the Missile Defense System (the “MDS Contract”) to ARES Technical Services Corporation (“ARES”). The parties have filed cross-motions for judgment upon the administrative record on the issue of whether the MDA’s evaluation process for the MDS Contract and award decision were reasonable. See generally Pl. Mot.; Def. Mot.; Def.-Int. Mot. For the reasons set forth below, the Court: (1) DENIES APT’s motion for judgment upon the administrative record; (2) GRANTS the government’s and ARES’s respective cross-motions for judgment upon the administrative record; and (3) DISMISSES the complaint.

II. Factual and Procedural Background1

A. Factual Background

This bid protest involves a challenge to the MDA’s evaluation process and decision to award the MDS Contract to ARES. APT is an unsuccessful offeror in connection with that procurement. See AR2567.

As background, the MDA’s mission is to develop and deploy a layered Missile Defense System (“MDS”) to defend the United States, its deployed forces, its allies and friends from missile attacks in all phases of flight. See https://www.mda.mil. As part of this mission, the MDA requires, among other things, agency-wide safety engineering services to support the MDS, which include simulated flight and ground tests as well as the development, implementation and execution of safety and occupational health programs. AR302; AR2454.

The facts recited in this Memorandum Opinion and Order are taken from the administrative record (“AR”); APT’s motion for judgment upon the administrative record (“Pl. Mot.”); and the government’s and ARES’s cross-motions for judgment upon the administrative record (“Def. Mot.”; “Def.-Int. Mot.”). Except where otherwise noted, the facts cited herein are undisputed.

APT is the incumbent provider of safety engineering services to the MDA. See Am. Compl. at ¶ 34.

1. The RFP

The contract at issue was awarded pursuant to the MDA’s Request for Proposals No. HQ0858-20-R-0003 (“RFP”). Id. at ¶¶ 4-5. On June 1, 2020, the MDA issued the RFP to procure continued safety engineering services to support the MDS. AR33; AR302; AR2454.

The RFP provides that the MDA would use the following four factors to evaluate proposals: (1) Mission Capability; (2) Information Management and Control Plan Services; (3) Organizational Conflict of Interest Management Plan; and (4) Cost and Price. AR410.

The RFP states that the MDA would award the MDS Contract to the offeror whose proposal constitutes the best value to the government, using a trade-off analysis of two of the evaluation factors: (1) Mission Capability and (2) Cost and Price. Id. In this regard, the RFP states that the Mission Capability factor is “significantly more important than Cost and Price.” Id. The RFP also states that “[a]ward may be made to a higher rated, higher priced [o]fferor where the Source Selection Authority . . . reasonably determines that the technical superiority of the higher priced [o]fferor outweighs the price differential.” AR411.

The RFP requires offerors to submit proposals in six volumes. See AR358. Specifically relevant to this dispute, the RFP provides that offerors are required to address the following six subfactors of the Mission Capability factor in Volume III of their proposals: (1) Safety Risk Acceptance Package Development and Coordination; (2) Safety Requirements Tailoring Process Support; (3) Program Safety Documentation Review; (4) Test Event Safety Oversight; (5) Occupational Safety & Health Program; and (6) Human Capital Management. AR364. The RFP also provides that the Human Capital Management subfactor is comprised of the following four elements: (1) recruit qualified personnel; (2) retain qualified personnel; (3) problem resolution strategy; and (4) key staff position defined as Contract Program Manager (“CPM”). AR365-AR366. With regards to the fourth element concerning the CPM, Section L of the RFP states that every offeror “shall provide a bilaterally-signed employment agreement (employment contingent on contract award) for the key staff position.” AR396. Section M of the RFP similarly requires offerors to provide “a bilaterally-signed employment agreement that stipulates employment beginning on or before the first day of contract period of performance for this

On December 6, 2020, APT filed a bid protest before the Government Accountability Office (“GAO”) challenging the award of the MDS Contract to ARES. See AR3160-3180.

After the GAO denied APT’s protest on March 12, 2021, APT filed this bid protest action. See AR3955-AR3968.

B. Procedural Background

On March 23, 2021, APT filed the complaint in this matter, which it subsequently amended on May 5, 2021. See generally Compl; Am. Compl. On March 24, 2021, ARES filed an unopposed motion to intervene, which the Court granted on March 29, 2021. See generally Def.-Int. Mot. to Intervene; Order, dated March 29, 2021. On the same day, the Court entered a Protective Order in this matter. See generally Protective Order.

On April 12, 2021, the government filed the administrative record, which it subsequently corrected on April 29, 2021. See generally AR. On May 5, 2021, APT filed a motion for judgment upon the administrative record. See generally Pl. Mot. On May 19, 2021, the government and ARES filed their respective responses and oppositions to APT’s motion for judgment upon the administrative record and cross-motions for judgment upon the administrative record. See generally Def. Mot.; Def.-Int. Mot.

On May 24, 2021, APT filed a response and opposition to the government’s and ARES’s respective cross-motions for judgment upon the administrative record and a reply in support of its motion for judgment upon the administrative record. See generally Pl. Resp. On May 28, 2021, the government and ARES filed their respective reply briefs in support of their cross-motions. See generally Def. Reply; Def.-Int. Reply.

On June 11, 2021, the Court held oral arguments on the parties’ cross-motions for judgment upon the administrative record. See generally Oral Arg. Tr. The Court issued an oral opinion during the June 11, 2021, oral arguments. The Court issues this written opinion consistent with its prior oral ruling in this matter.

III. Legal Standards

A. Bid Protest Jurisdiction

The Tucker Act grants the United States Court of Federal Claims jurisdiction over bid protests brought by “an interested party objecting to a solicitation by a Federal agency for bids or proposals for a proposed contract or to a proposed award or the award of a contract or any alleged violation of statute or regulation in connection with a procurement or a proposed procurement.” 28 U.S.C. § 1491(b)(1). This Court reviews agency actions that are at issue in a bid protest matter under the Administrative Procedure Act’s (“APA”) “arbitrary and capricious” standard. See 28 U.S.C. § 1491(b)(4) (adopting the standard of review set forth in the APA). Under this standard, an “‘award may be set aside if either (1) the procurement official’s decision lacked a rational basis; or (2) the procurement procedure involved a violation of regulation or procedure.’” Banknote Corp. of Am., Inc. v. United States, 365 F.3d 1345, 1351 (Fed. Cir. 2004) (quoting Impresa Construzioni Geom. Domenico Garufi v. United States, 238 F.3d 1324, 1332 (Fed. Cir. 2001)).

In this regard, the United States Court of Appeals for the Federal Circuit has explained that, “[w]hen a challenge is brought on the first ground, the test is ‘whether the contracting agency provided a coherent and reasonable explanation of its exercise of discretion, and the disappointed bidder bears a “heavy burden” of showing that the award decision had no rational basis.’” Id. (quoting Impresa, 238 F.3d at 1332-33). “‘When a challenge is brought on the second ground, the disappointed bidder must show a clear and prejudicial violation of applicable statutes or regulations.’” Id. (quoting Impresa, 238 F.3d at 1333). In addition, when reviewing an agency’s procurement decision, the Court should recognize that the agency’s decision is entitled to a “presumption of regularity.” Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 415 (1971), abrogated by Califano v. Sanders, 430 U.S. 99 (1977). “The [C]ourt should not substitute its judgment for that of a procuring agency . . . .” Cincom Sys., Inc. v. United States, 37 Fed. Cl. 663, 672 (1997). And so, “[t]he protestor must show, by a preponderance of the evidence, that the agency’s actions were either without a reasonable basis or in violation of applicable procurement law.” Info. Tech. & Applications. Corp. v. United States, 51 Fed. Cl. 340, 346 (2001), aff’d, 316 F.3d 1312 (Fed. Cir. 2003) (citation omitted). The Court’s standard of review “is highly deferential.” Advanced Data Concepts, Inc. v. United States, 216 F.3d 1054, 1058 (Fed. Cir. 2000). As long as there is “‘a reasonable basis for the agency’s action, the [C]ourt should stay its hand even though it might, as an original proposition, have reached a different conclusion . . . .’” Honeywell, Inc. v. United States, 870 F.2d 644, 648 (Fed. Cir. 1989) (quoting M. Steinthal & Co. v. Seamans, 455 F.2d 1289, 1301 (D.C. Cir. 1971)). But, if “the agency ‘entirely fail[s] to consider an important aspect of the problem, [or] offer[s] an explanation for its decision that runs counter to the evidence before the agency,’” then the resulting action lacks a rational basis and, therefore, is defined as “arbitrary and capricious.” Ala. Aircraft Indus., Inc.-Birmingham v. United States, 586 F.3d 1372, 1375 (Fed. Cir. 2009) (quoting Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983)).

In addition, this Court affords contracting officers a great deal of discretion in making contract award decisions when the contract is to be awarded to the offeror that will provide the best value to the government. See Banknote Corp. of Am., 365 F.3d at 1355-56; TRW, Inc. v. Unisys Corp., 98 F.3d 1325, 1327-28 (Fed. Cir. 1996); E.W. Bliss Co. v. United States, 77 F.3d 445, 449 (Fed. Cir. 1996); Lockheed Missiles & Space Co. v. Bentsen, 4 F.3d 955, 958-59 (Fed. Cir. 1993). In this regard, the Court has held that the government’s best value determination should not be disturbed, if the government documents its analysis and includes a rationale for any business judgments and trade-offs made in reaching that decision. See Blackwater Lodge & Training Ctr., Inc. v. United States, 86 Fed. Cl. 488, 514 (2009). And so, a decision to award a contract is least vulnerable to challenge when that decision is based upon a best value determination. PlanetSpace, Inc. v. United Sates, 96 Fed. Cl. 119, 125 (2010).

B. Judgment Upon The Administrative Record

Unlike a summary judgment motion brought pursuant to RCFC 56, “the existence of genuine issues of material fact does not preclude judgment on the administrative record” under RCFC 52.1. Tech Sys., Inc. v. United States, 98 Fed. Cl. 228, 242-43 (2011); see RCFC 56. Rather, the Court’s inquiry is whether, “given all the disputed and undisputed facts, a party has met its burden of proof based on the evidence in the record.” A&D Fire Prot., Inc. v. United States, 72 Fed. Cl. 126, 131 (2006) (citing Bannum, Inc. v. United States, 404 F.3d 1346, 1356 (Fed. Cir. 2005)).

C. Injunctive Relief

Lastly, the Tucker Act authorizes this Court to “award any relief that the court considers proper, including . . . injunctive relief” in bid protest matters. 28 U.S.C. § 1491(b)(2); see RCFC 65. In deciding whether to issue a permanent injunction, the Court “considers: (1) whether . . . the plaintiff has succeeded on the merits of the case; (2) whether the plaintiff will suffer irreparable harm if the court withholds injunctive relief; (3) whether the balance of hardships to the respective parties favors the grant of injunctive relief; and (4) whether it is in the public interest to grant injunctive relief.” PGBA, LLC v. United States, 389 F.3d 1219, 1228-29 (Fed. Cir. 2004) (citing Amoco Prod. Co. v. Vill. of Gambell, Alaska, 480 U.S. 531, 546 n.12 (1987) (“The standard for a preliminary injunction is essentially the same as for a permanent injunction with the exception that the plaintiff must show a likelihood of success on the merits rather than actual success.”)); see also Centech Grp., Inc. v. United States, 554 F.3d 1029, 1037 (Fed. Cir. 2009). In this regard, the Federal Circuit has held that:

No one factor, taken individually, is necessarily dispositive. If [an injunction] is granted by the trial court, the weakness of the showing regarding one factor may be overborne by the strength of the others. If the injunction is denied, the absence of an adequate showing with regard to any one factor may be sufficient, given the weight or lack of it assigned the other factors, to justify the denial.
FMC Corp. v. United States, 3 F.3d 424, 427 (Fed. Cir. 1993) (citation omitted). This Court has also found success upon the merits to be “the most important factor for a

court to consider when deciding whether to issue injunctive relief.” Dellew Corp. v. United States, 108 Fed. Cl. 357, 369 (2012) (citing Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308, 1312 (Fed. Cir. 2007)). But, while success upon the merits is necessary, it is not sufficient alone for a plaintiff to establish an entitlement to injunctive relief. See Contracting, Consulting, Eng’g LLC v. United States, 104 Fed. Cl. 334, 353 (2012) (“Although plaintiff’s entitlement to injunctive relief depends on its succeeding on the merits, it is not determinative because the three equitable factors must be considered, as well.”) (citations omitted)).

IV. Legal Analysis

APT asserts five challenges to the MDA’s evaluation process and award decision for the MDS Contract, namely that: (1) the MDA acted arbitrarily, irrationally and contrary to applicable law by assigning APT’s proposal an unacceptable rating; (2) the MDA’s cost realism analysis was arbitrary, irrational and violated FAR § 15.404-1(d); (3) the MDA failed to evaluate professional compensation, as required by FAR § 52.222-46; (4) the MDA arbitrarily and irrationally evaluated the offerors’ experience under the Mission Capability factor; and (5) the MDA’s source selection analysis was arbitrary and capricious, an abuse of discretion and contrary to law. Pl. Mot. at 12-37. And so, APT requests, among other things, that the Court enjoin the MDA from proceeding with performance under the MDS Contract. Id. at 39.

The government and ARES counter that the MDA’s evaluation process and award decision were rational and consistent with the terms of the RFP and applicable law. Def. Mot. at 20-32; Def.-Int. Mot. at 13-48. And so, they request that the Court sustain the MDA’s award decision. Def. Mot. at 33; Def-Int. Mot. at 49-50.

For the reasons that follow, a careful review of the administrative record shows that the MDA’s evaluation process and decision to award the MDS Contract to ARES were reasonable and consistent with the terms of the RFP. And so, the Court: (1) DENIES APT’s motion for judgment upon the administrative record; (2) GRANTS the government’s and ARES’s cross-motions for judgment upon the administrative record; and (3) DISMISSES the complaint.

A. The MDA Did Not Err In Determining That APT’s Proposal Was Unacceptable

As an initial matter, APT has not shown that the MDA acted arbitrarily, irrationally, or contrary to applicable law by assigning APT’s proposal an unacceptable rating under the RFP’s Mission Capability factor. It is undisputed that APT did not provide a bilaterally-signed employment agreement for its proposed Contract Program Manager, Mr. Clark Kilgore, with its revised proposal. Pl. Mot. at 12; Def. Mot. at 8; see also AR943-AR945. Because the record evidence shows that APT was required to do so under the terms of the RFP, the MDA reasonably found APT’s proposal to be “unawardable.” AR2472.

In this regard, a plain reading of the RFP makes clear that APT and all other offerors were required to provide a bilaterally-signed employment agreement for the individual proposed to serve as the CPM for the MDS Contract. Notably, Section L of the RFP provides that:

The Offeror shall provide a bilaterally-signed employment agreement (employment contingent on contract award) for [the proposed CPM]. The bilaterally-signed employment agreement must stipulate employment beginning on or before the first day of contract period of performance for this effort.
AR396. Section M of the RFP similarly requires that offerors provide “a bilaterally-signed employment agreement [for the proposed CPM] that stipulates employment beginning on or

before the first day of contract period of performance for this effort.” AR417. And so, the Court reads these provisions in the RFP to require that APT provide a bilaterally-signed employment agreement for its proposed CPM with its final revised proposal. AR396; see Gutierrez de Martinez v. Lamagno, 515 U.S. 417, 432 n.9 (1995) (recognizing that the use of the word “‘shall’ generally means ‘must’”).

The Court is also not persuaded by APT’s argument that it had no obligation to provide such an agreement for Mr. Kilgore, because the RFP does not require a bilaterally-signed employment agreement for existing employees. Def. Mot. at 12-15; Pl. Resp. at 2-3. To support this argument, APT points to the language in Section L of the RFP providing that “(employment contingent on contract award),” and APT argues that Mr. Kilgore did not need to sign an employment agreement for the MDS Contract because he is an existing employee of APT. Pl.

Mot. at 13-14. But, the Court reads the language cited by APT to mean that employment as the CPM for the MDS Contact would be contingent upon the award of that contract to the successful offeror. AR396. Such a reading is in harmony with the plain text of Section M of the RFP, which provides that the bilaterally-signed employment agreement would stipulate “employment beginning on or before the first day of contract period of performance for this effort.” AR417. Given this, the plain text of the RFP requires a bilaterally-signed employment agreement for any individual proposed to be the CPM.

Because it is undisputed that APT did not provide the bilaterally-signed employment agreement at issue, the record evidence in this case makes clear that the MDA reasonably assigned “unacceptable” rating to APT’s proposal. Def. Mot. at 8; Pl. Mot. at 12; AR2460.

APT’s argument that the MDA erred by failing to seek clarification from APT regarding the missing employment agreement for Mr. Kilgore is equally unavailing. Pl. Mot. at 15-17; Pl. Resp. at 4-5; Oral Arg. Tr. at 18:3-18:21. APT argues that the MDA should have engaged in discussions with, or sought clarification from, APT regarding the missing employment agreement. Pl. Mot. at 15-17; Pl. Resp. at 4-5. But, the RFP makes clear that an discussions with APT would have been inappropriate, because the RFP requires that the MDA “evaluate proposals and award a contract without discussions with [o]fferors, (except clarifications as described in FAR 15.306(a)).” AR383.

APT’s claim that the MDA should have sought clarification from APT regarding the bilaterally-signed employment agreement for Mr. Kilgore is also dubious. FAR § 15.306(a)(2) makes clear that clarifications may only resolve minor or clerical errors with regards to APT’s proposal. See FAR § 15.306(a)(2) (providing that “[i]f award will be made without conducting discussions, offerors may be given the opportunity to clarify certain aspects of proposals . . . or to resolve minor or clerical errors.”). The missing bilaterally-signed employment agreement for Mr. Kilgore is not the type of minor or clerical error contemplated by FAR § 15.306(a)(2). While perhaps on somewhat stronger footing, APT’s argument that the MDA engaged in unequal treatment of the offerors does not provide a sufficient basis for the Court to set aside the MDA’s award decision. APT argues that the MDA engaged in unequal treatment of offerors, because the agency’s contracting officer sought clarification from ARES’s regarding a FAR § 52.204-24 certification that was not included in ARES’s final revised proposal. Pl. Mot. at 20; see also Oral Arg. Tr. at 18:22-19:8. But, even if it the MDA erred in seeking clarification from ARES, the record evidence makes clear that APT has not been prejudiced by this alleged conduct for two reasons.

First, APT has not shown that it was prejudiced by the clarification at issue because, its own proposal was “unacceptable,” and thus, “unawardable” under the terms of the RFP.

AR2472. And so, APT would not have been in a position to be awarded the MDS Contract, if the agency had not sought clarification from ARES.

APT also fails to establish prejudice, because the administrative record shows that the clarification at issue did not alter ARES’s final revised proposal. It is undisputed that ARES had no obligation to submit a FAR § 52.204-24 certification with its proposal because ARES had previously submitted a FAR § 52.204-26 certification to the MDA. Pl. Mot. at 18; Def. Mot. at 8; see also AR1263. The MDA’s contracting officer, April L. Paul, also makes clear in her declaration that “even if ARES did not respond to the MDA’s question regarding the FAR § 52.204-24 certification, ARES’[s] proposal would still have been acceptable and contained no deficiencies; thus it still would have been awardable.” Dec. of April L. Paul ¶ 8. Given this, the MDA’s decision to seek clarification from ARES regarding the missing FAR § 52.204-24 certification did not alter the fact that ARES’s proposal offered the best value to the government. AR2567.

APT also argues that the MDA had a duty to inquire into missing proposal information based upon the agency’s past contracting history with APT. Pl. Mot. at 16-17. But, this argument is unavailing, because it is expressly contradicted by the terms of the RFP. Section L of the RFP states that offerors “shall assume that the Government has no prior knowledge of the [o]fferor’s experience and will base its evaluation on the information presented in the [o]fferor’s proposal. Alternate proposals . . . that deviate in any way from the solicitation . . . will not be considered nor evaluated.” AR356.

B. APT Fails To Show Prejudice Regarding The MDA’s Other Alleged Errors

Because the record evidence shows that the MDA reasonably determined that APT’s proposal was “unacceptable” and thus, “unawardable” under the terms of the RFP, the Court need not address the other evaluation errors alleged in this case. APT simply has not established that it was prejudiced by any of these alleged evaluation errors, given the deficiency in its own proposal. AR2460. And so, the Court must also DENY these claims. See Labatt Food Serv., Inc. v. United States, 577 F.3d 1375, 1378 (Fed. Cir. 2009) (protestor must show that “but for the [alleged] error, it would have had a substantial chance of securing the contract”). A careful review of the administrative record also shows that the MDA’s evaluation process was rational and that the agency reasonably decided to award the MDS Contract to ARES, consistent with the requirements of the RFP. In this regard, the record evidence shows that the MDA’s cost evaluation team carefully analyzed all responsive proposals and determined that the proposed costs all of the offerors were reasonable and realistic, consistent with the terms of the RFP. AR2339; AR2343; AR2347-2348; see also AR419 (requiring that the MDA conduct an independent cost realism analysis to determine whether each offeror’s proposed costs are reasonable and realistic for the work to be performed). The record evidence also makes clear that the MDA’s SSEB carefully evaluated all responsive proposals and prepared a detailed proposal analysis report that: (1) outlined the technical evaluation criteria in the RFP and their respective importance; (2) provided the evaluation results for each proposal; (3) summarized and discussed the differences between each proposal; and (4) recommended that the SSA award the MDS Contract to ARES. AR2448-AR2564.

The administrative record also calls into doubt several of APT’s claims challenging the MDA’s evaluation process. For example, APT’s claim that the MDA erred by failing to compare ARES’s proposed costs to APT’s costs is contradicted by the terms of the RFP, which provides that the MDA would analyze each offeror’s proposed costs for reasonableness and realism by comparing these costs to benchmark estimates of adequate labor rates and fringe benefits that were developed using incumbent contractor rates and labor market data. AR370-AR371; AR2339-AR2444. APT’s claim that the MDA failed to appropriately credit its prior experience is similarly belied by the record evidence showing that the MDA assigned a strength to APT’s proposal for proposing to use staff that had “extensive experience providing Ground Safety at missile testing sites.” AR2470.

The source selection decision for the MDS Contract also reflects the independent best value determination of the SSA, based upon the RFP’s evaluation factors and the evaluation results for each proposal. AR2567 (showing that the SSA reviewed the evaluation results and independently determined that: (1) ARES submitted the only proposal that did not receive an “unacceptable” technical rating under one of the Mission Capability subfactors and (2) APT’s total evaluated price was more than $10 million higher than ARES’s total evaluated price). AR2567. And so, the Court is satisfied that the MDA reasonably determined that ARES’s proposal represented the best value to the government in this case.

Because APT has not shown that the MDA’s evaluation process and decision to award the MDS Contract to ARES were irrational, or contrary to the terms of the RFP or applicable law, the Court will not set aside the sound determinations of the MDA.

C. APT Is Not Entitled To Injunctive Relief

Because APT has not prevailed upon the merits of any of its bid protest claims in this case, the Court must also DENY APT’s request for injunctive relief. Argencord Mach. & Equip., Inc. v. United States, 68 Fed. Cl. 167, 176 (2005).

V. Conclusion

In sum, APT has not shown that the MDA erred in determining that its proposal was “unacceptable,” and thus “unawardable,” under the terms of the RFP for the MDS Contract. APT similarly fails to show that it has been prejudiced by any of the other alleged evaluation errors in this case. And so, the Court:

1. DENIES APT’s motion for judgment upon the administrative record; 2. GRANTS the government’s and ARES’s respective cross-motions for judgment upon the administrative record; and
3. DISMISSES the complaint.
The Clerk shall enter judgment accordingly.
Each party to bear its own costs.
Some of the information contained in this Memorandum Opinion and Order may be

considered protected information subject to the Protective Order entered in this matter on March 29, 2021. This Memorandum Opinion and Order shall therefore be filed UNDER SEAL. The parties shall review the Memorandum Opinion and Order to determine whether, in their view, any information should be redacted in accordance with the terms of the Protective Order prior to publication. The parties shall FILE a joint status report identifying the information, if any, that they contend should be redacted, together with an explanation of the basis for each proposed redaction on or before July 14, 2021.

IT IS SO ORDERED.

s/ Lydia Kay Griggsby

LYDIA KAY GRIGGSBY

Judge

This is a verbatim capture of the text layer of the court's own document in Apt Research, Inc. v. United States. Nothing is summarized or reworded, and the sections run in the order the court wrote them. Two things the page shows are not repeated in the text: the rule the court draws around its caption, and the pagination furniture (the page numbers and the electronic filing stamp printed across the top of each page).

Related Decisions

Same Matter: Bid protest

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.