B-402284.2

Cedar Electric, Inc.

Mar 19, 2010.Department of Veterans AffairsDepartment of Veterans Affairs
Denied

GAO Digest

Cedar Electric, Inc., of Lititz, Pennsylvania, protests the award of a contract to Seawolf Construction Corp., of Parsippany, New Jersey, by the Department of Veterans Affairs (VA) under invitation for bids (IFB) No. VA-244-09-IB-0315, for renovation and new construction at the Lebanon VA Medical Center, in Lebanon, Pennsylvania. Cedar Electric contends that the VA improperly waived Seawolf's failure to acknowledge amendments to the IFB. We deny the protest.

Key Facts

Decision date
Mar 19, 2010.
Publicly released
Mar 19, 2010.
Agency
Department of Veterans Affairs
Department
Department of Veterans Affairs
Decided by
Lynn H. Gibson, Acting General Counsel

Counsel

Protester
Woolford Law, PC
Timothy J. Woolford
Intervenor
PilieroMazza PLLC
Kelly DiGrado, Antonio R. Franco
Agency
Department of Veterans Affairs
Kate Gorney
GAO
Office of the General Counsel, GAO
Paula J. Haurilesko, Jonathan L. Kang, Guy R. Pietrovito

Procurement

Awardee
Seawolf Construction Corp.
Solicitation
VA-244-09-IB-0315 (IFB)
Instrument
Contract
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision11,344 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Cases cited

10 cases this decision cites, grouped by the forum that decided each, in the order it first names them. 1 of them opens at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Government Accountability Office9
Federal Constr., Inc.B-279638B-279638B-279638.2Kalex Constr. & Dev., Inc.B-278076.2Overstreet Elec. Co., Inc.B-283830B-283830B-283830.2K ServicesB-238744L-3 Sys. Co. Wescam Sonoma, Inc.B-297323Johnson Moving & Storage Co.B-221826M. C. Hodom Constr. Co., Inc.B-209241

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

Cedar Electric, Inc., of Lititz, Pennsylvania, protests the award of a contract to Seawolf Construction Corp., of Parsippany, New Jersey, by the Department of Veterans Affairs (VA) under invitation for bids (IFB) No. VA-244-09-IB-0315, for renovation and new construction at the Lebanon VA Medical Center, in Lebanon, Pennsylvania. Cedar Electric contends that the VA improperly waived Seawolf's failure to acknowledge amendments to the IFB.

B-402284.2, Cedar Electric, Inc., March 19, 2010

Decision

Matter of: Cedar Electric, Inc.

File: B-402284.2

Date: March 19, 2010

Timothy J. Woolford, Esq., Woolford Law, PC, for the protester.

Kelly DiGrado, Esq., Antonio R. Franco, Esq., PilieroMazza PLLC, for the intervenor.

Kate Gorney, Esq., Department of Veterans Affairs, for the agency.

Paula J. Haurilesko, Esq., Jonathan L. Kang, Esq., and Guy R. Pietrovito, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Protest of agency's waiver of the awardee's failure to acknowledge an amendment is denied where the amendment was not material because it did not impose new legal obligations on the bidders.

DECISION

Cedar Electric, Inc., of Lititz, Pennsylvania, protests the award of a contract to Seawolf Construction Corp., of Parsippany, New Jersey, by the Department of Veterans Affairs (VA) under invitation for bids (IFB) No. VA-244-09-IB-0315, for renovation and new construction at the Lebanon VA Medical Center, in Lebanon, Pennsylvania. Cedar Electric contends that the VA improperly waived Seawolf's failure to acknowledge amendments to the IFB.

We deny the protest.

The IFB, issued on August 31, 2009, provided for the award of a construction contract. Drawings, specifications, and project design information for performance of the construction services were provided. The IFB was amended eight times. Bidders were required to acknowledge each amendment when submitting a bid, and were advised that, –[f]ailure to acknowledge an amendment may result in your proposal being considered non-responsive.— IFB at 7.

Amendment 1 replaced the IFB in its entirety and included associated drawings and two volumes of specifications. As relevant here, this amendment included a section on Wall and Door Protection, which specifically discussed –corner guards.— IFB amend. 1, Project Manual, Vol. 2, sect. 10 26 00.

Amendment 5 included a list of the specifications and also amended some of the specifications and drawings. The amendment listed as an attachment the –Schedule for Finishes,— which specifies interior and exterior materials, sizes, colors, patterns, textures, and finishes for the project. IFB amend. 5, at 2. The Schedule for Finishes was referred to throughout the specifications provided by Amendment 5. For example, the section on Shop Drawings, Product Data, and Samples requires the contractor to submit all samples required by the Schedule for Finishes in quadruplicate for approval. Id., Project Manual, Vol. 1, sect. 01 33 23, at 2. The specification for Resilient Sheet Flooring identifies the Schedule for Finishes as the source for color, pattern, and texture. Id., sect. 09 65 16, at 1. However, the agency did not attach the Schedule for Finishes to Amendment 5. Contracting Officer's (CO) Statement para. 5.

The specifications provided in Amendment 1 also contained references to the Schedule for Finishes.

Amendment 8 provided a copy of the Schedule for Finishes and responded to contractor questions. In response to a question about wall and door protection, the agency stated that corner guards should be 42— high, made of stainless steel, and should be assumed for all outside corners of corridors. IFB amend. 8.

VA received six bids, including that of Cedar Electric and Seawolf. Seawolf submitted the apparent low bid of $3,695,000 and acknowledged amendments 1 through 6, but failed to acknowledge amendments 7 and 8 prior to bid opening. Cedar Electric submitted the next apparent low bid of $3,760,000 and acknowledged all eight amendments. CO Statement para. 2. The CO waived Seawolf's failure to acknowledge amendments 7 and 8, citing Federal Acquisition Regulation (FAR) sect. 14.405, and awarded the contract to Seawolf. CO Statement paras. 3-4.

Seawolf acknowledged Amendments 7 and 8 after bid opening; however, a bidder's intent to be bound must be evident from the bidding documents themselves, so that post-bid-opening submissions or explanations cannot be used to make a non'responsive bid responsive. Johnson Moving & Storage Co., B-221826, Mar. 19, 1986, 86-1 CPD para. 273 at 3.

FAR sect. 14.405 permits the waiver of minor informalities and irregularities in bids.

Cedar Electric protested to the agency, and following the VA's denial of the protest, protested to our Office. Cedar Electric primarily argues that Amendment 8 is a material amendment that cannot be waived, and that Seawolf's bid should have been rejected. In particular, Cedar Electric contends that the Schedule for Finishes constitutes a significant design change that imposes new legal obligations and increases the cost of performance. The agency responds that Amendment 8 is not material because the Schedule for Finishes was referenced in Amendment 5, which Seawolf acknowledged. In the alternative, the agency argues that the price impact of Amendment 8 is not significant in relation to the value of the total project and therefore is not material.

Cedar Electric also argued in its protest that Seawolf's failure to acknowledge amendment 7 was not waivable. However, Cedar Electric did not address the agency's response to this argument in its comments on the agency report. We therefore deem this basis for protest to have been abandoned. Citrus College; KEI Pearson, Inc., B'293543 et al., Apr. 9, 2004, 2004 CPD para. 104 at 8 n.4.

A bidder's failure to acknowledge a material amendment to an IFB renders the bid nonresponsive, since absent such an acknowledgment the government's acceptance of the bid would not legally obligate the bidder to meet the government's needs as identified in the amendment. Federal Constr., Inc., B-279638, B-279638.2, July 2, 1998, 98-2 CPD para. 65 at 2. An amendment is material if it would have more than a negligible impact on price, quantity, quality, or delivery. FAR sect. 14.405(d)(2). Moreover, our Office has held that an amendment is not material where it does not impose any legal obligations on the bidder different from those imposed by the original solicitation--for example, where it merely clarifies an existing requirement or is a matter of form--or has a negligible impact on the relative standing of the bidders. Kalex Constr. & Dev., Inc., B-278076.2, Jan. 20, 1998, 98'1 CPD para. 25 at 2. A bidder's failure to acknowledge an amendment that is not material is waivable as a minor informality. FAR sect. 14.405; Overstreet Elec. Co., Inc., B-283830, B-283830.2, Dec. 30, 1999, 2000 CPD para. 8 at 7. No precise rule exists to determine whether a change required by an amendment is more than negligible; that determination is based on the facts of each case. K Services, B-238744, June 13, 1990, 90-1 CPD para. 556 at 2, citing DeRalco, Inc., B'233996, Mar. 29, 1989, 89-1 CPD para. 327.

We find that Amendment 8 is not a material amendment because the inclusion of the Schedule for Finishes in Amendment 8 does not constitute a change in the legal obligations of the bidders to meet the government's requirements. The references to the Schedule for Finishes in Amendment 5 put bidders on notice that the Schedule for Finishes existed as a contract requirement which they were obligated to fulfill. The Schedule for Finishes was included in the list of attachments to Amendment 5, even through the agency neglected to provide the actual schedule at that time. Amendment 5 required the contractor to submit for approval all samples required by the Schedule for Finishes in quadruplicate. Moreover, several of the specifications attached to Amendment 5 specifically stated that –color, pattern, and texture— performance requirements were specified in the Schedule for Finishes. All of these references, combined, clearly indicate that Amendment 5 created a legal obligation for contractors to perform in accordance with the Schedule for Finishes, even though the schedule was not attached to the amendment. See B'173563, Nov. 12, 1971, 51 Comp. Gen. 293 (1971). Because Amendment 8 was not a material amendment, VA acted appropriately in waiving Seawolf's failure to acknowledge the amendment.

In this regard, boards of contract appeals have found that contractors are bound to perform, at no additional cost to the government, provisions of which the contractor had knowledge, or should have requested clarification. Murson Constructors, Inc., 88-3 BCA para. 20992, June 29, 1988, aff'd, 878 F.2d 1446 (Fed. Cir. 1989); George E. Newsom, 80-2 BCA para. 14490, June 30, 1980, aff'd, George E. Newsom v. United States, 230 Ct.Cl. 301, 676 F.2d 647 (1982).

Cedar Electric also objects that the amendment's requirement to provide 42— stainless steel corner guards constitutes a new material requirement. This allegation is untimely, however.

Our Bid Protest Regulations contain strict rules for the timely submission of protests. Under these rules, a protest based on other than alleged improprieties in a solicitation must be filed no later than 10 calendar days after the protester knew, or should have known, of the basis for protest, whichever is earlier. 4 C.F.R. sect. 21.2(a)(2)(2009). Moreover, where a protester initially files a timely protest, and later supplements it with independent grounds of protest, the later-raised allegations must independently satisfy the timeliness requirements, since our Regulations do not contemplate the unwarranted piecemeal presentation or development of protest issues. L-3 Sys. Co. Wescam Sonoma, Inc., B-297323, Dec. 3, 2005, 2005 CPD para. 219 at 4.

Here, Cedar Electric first raised the issue of the corner guards in its response to the agency report. However, Cedar Electric was aware of the requirement for corner guards at the time of its original protest, and therefore should have raised the issue at that time. Hence, the argument with regard to corner guards is untimely.

In any event, it appears that the requirement for corner guards is negligible. The agency estimates the cost of the corner guards as $6,550, which is less than 0.2 percent of both Cedar Electric's and Seawolf's bids and is 10 percent of the difference between the two bids. CO Statement para. 3. Our Office has found that a change that represented 0.1 percent of the lowest bid price and 6.6 percent of the difference between the low bid and the second lowest bid to be negligible. See K Services, supra; cf. M. C. Hodom Constr. Co., Inc., B-209241, Apr. 22, 1983, 83-1 CPD para. 440 (an 11.25 percent difference in bid prices is not negligible).

In sum, we think that Amendment 8 was not a material amendment. It did not impose legal obligations upon the bidders that were not already incorporated through prior amendments. Therefore, the agency reasonably waived Seawolf's failure to acknowledge Amendment 8 as a minor informality.

The protest is denied.

Lynn H. Gibson

Acting General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.