B-402292

American Warehouse Systems

Jan 28, 2010.General Services AdministrationGeneral Services Administration
Denied

GAO Digest

American Warehouse Systems (AWS), of Minneapolis, Minnesota, protests the issuance of an order to FedSource, Inc., of Union, Missouri, under the firm's General Services Administration (GSA) schedule contract by the GSA under request for quotations (RFQ) No. RFQ421147 for mezzanine installation. AWS contends that the order includes labor services that are not on FedSource's GSA schedule contract. We deny the protest.

Key Facts

Decision date
Jan 28, 2010.
Publicly released
Jan 28, 2010.
Agency
General Services Administration
Department
General Services Administration
Decided by
Lynn H. Gibson, Acting General Counsel

Counsel

Protester
Mark Juelich
Agency
General Services Administration
Melissa McWilliams
GAO
Office of the General Counsel, GAO
Sharon L. Larkin, James A. Spangenberg

Procurement

Awardee
FedSource, Inc.
Solicitation
RFQ421147 (RFQ)
Instrument
Contract
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision10,202 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Federal Acquisition Regulation1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

2 cases this decision cites, in the order it first names them. No published copy of any of them was confirmed, so each is shown without a link.

Firearms Training Sys., Inc.B-292819.2Symplicity Corp.B-291902

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

American Warehouse Systems (AWS), of Minneapolis, Minnesota, protests the issuance of an order to FedSource, Inc., of Union, Missouri, under the firm's General Services Administration (GSA) schedule contract by the GSA under request for quotations (RFQ) No. RFQ421147 for mezzanine installation. AWS contends that the order includes labor services that are not on FedSource's GSA schedule contract.

Decision

Matter of: American Warehouse Systems

File: B-402292

Date: January 28, 2010

Mark Juelich for the protester.

Melissa McWilliams, Esq., General Services Administration, for the agency.

Sharon L. Larkin, Esq., and James A. Spangenberg, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Protest that agency placed order for –construction— services that were not on vendor's General Services Administration (GSA) Schedule 56 contract is denied, where GSA reasonably determined that the solicitation did not require construction services and all of the services purchased were on the vendor's or its subcontractors' schedule contracts.

DECISION

American Warehouse Systems (AWS), of Minneapolis, Minnesota, protests the issuance of an order to FedSource, Inc., of Union, Missouri, under the firm's General Services Administration (GSA) schedule contract by the GSA under request for quotations (RFQ) No. RFQ421147 for mezzanine installation. AWS contends that the order includes labor services that are not on FedSource's GSA schedule contract.

We deny the protest.

The RFQ required the selected vendor to –furnish and install a storage system consisting of a free-standing mezzanine with bollards, fluorescent lighting, fire sprinkler system, storage racks, bin shelving, wire mesh partitions, modular wall units, work tables, personnel lockers, and storage cabinets— at Langley Air Force Base, Virginia. RFQ at 1. The mezzanine structure was to be a –free-standing— structure, measured at 96 feet by 42 feet, with shelving systems that –shall not be connected to any existing building structure except the floor.— RFQ, Statement of Work, at 2, 10.

The RFQ –recommended— that lighting and sprinklers be installed by identified vendors. RFQ, Statement of Work, at 4-5.

The acquisition was to be conducted in accordance with Federal Acquisition Regulation (FAR) subpart 8.4 governing the Federal Supply Schedule (FSS) program. The RFQ required that vendors hold GSA –Schedule 56— contracts for –Building Materials/Industrial Services and Supplies.— The RFQ also identified that the supplies and services could be supplied under the following –applicable— Special Item Numbers (SIN): 361-10B (–Pre-Engineered and Prefabricated Buildings and Structures for In-Plant Solutions—) and 361-30 (–Ancillary Services Relating to Pre'Engineered/Prefabricated Buildings and Structures—). RFQ at 1. After AWS informed the agency that additional SINS might apply, the RFQ was modified to state that –products may also fall within any other applicable [SIN] under this schedule.— RFQ, mod. 2, at 1.

Specifically, AWS asserted the SIN 357-11C, –Warehouse Equipment and Supplies,— could be used to procure the mezzanine components. Agency Report, Tab 12, E-Mail from AWS to GSA, Oct. 27, 2009, at 1.

The RFQ stated that award would be made on a best value basis, considering technical, past performance, and price factors. The solicitation provided that the technical and past performance factors were –approximately equal— in importance and, combined, were –significantly more important— than the price factor. RFQ at 2.

AWS and FedSource hold GSA Schedule 56 contracts and competed for the work. The agency placed the order for mezzanine installation with FedSource in the amount of $234,230.77 and AWS protested. Agency Report, Tab 16, Best Value Determination, at 5. AWS contends that FedSource's GSA contract does not contain the applicable SIN to install the mezzanine, and therefore the agency cannot purchase these services from FedSource. Specifically, AWS contends that installation of the mezzanine structure must be considered to be –construction— and that the procurement of the services from FedSource through SIN 361'30, which does not include construction, is inappropriate. Instead, AWS argues, labor must be provided under SIN361-32, –Installation and Site Preparation for Pre-Engineered/Prefabricated Buildings and Structures,— which does include construction and which is not included in FedSource's GSA contract. Protester's Comments at 2.

It is true that an agency may not use FSS procedures to purchase items that are not listed on a vendor's GSA schedule without conducting a competition for those non'schedule items. Firearms Training Sys., Inc., B-292819.2 et al., Apr. 26, 2004, 2004 CPD para. 107 at 9; Symplicity Corp., B-291902, Apr. 29, 2003, 2003 CPD para. 89 at 4.

However, as discussed below, we find that GSA reasonably found that the required services were included in FedSource's or its subcontractors' schedule contracts and purchased under the appropriate SINs.

As AWS properly notes, FAR sect. 2.101 defines –construction— to mean –construction, alteration, or repair (including dredging, excavating, and painting) of buildings, structures, or other real property.— However, the agency reasonably determined here that the RFQ did not contemplate construction services. As the agency correctly notes, the RFQ seeks the installation of a free-standing mezzanine system that requires no construction, alteration, or repair of the building structure; it requires only that the mezzanine structure be bolted to the floor. According to the agency, the mezzanine structure is manufactured off site and assembled on site, and it can easily be disassembled and reassembled in another location. GSA Legal Memorandum at 4. The RFQ generally requires that installation occur –in accordance with [the] manufacturer's specified installation procedures,— RFQ, Statement of Work, at 3, and does not include any FAR provisions concerning construction or Davis Bacon wage rates. Although the RFQ generally references –[International Building Code] design— in describing the width and rise requirements for the mezzanine stairs, id. at 2, and generally requires that design, fabrication, and installation of the mezzanine systems occur –in accordance with the applicable industry codes and standards,— id. at 1, these general provisions, in our view, do not transform this order into construction services as AWS contends.

The only possible construction services--fire sprinkler and lighting installation--are going to be performed by the recommended vendors identified in the RFQ and not by FedSource. Contracting Officer's Statement at 8. This aspect of the award was not challenged here.

In addition, GSA's market research confirmed that the services are not construction.

In this regard, prior to issuing the solicitation, the contracting officer consulted with a project engineer from the Air Force, as well as representatives from AWS and FedSource. All three indicated that fabrication and installation of the mezzanine structure was not construction, but rather was assembly. Contracting Officer's Statement at 3, 7. Furthermore, we note that AWS's website shows that it –designs, manufactures, and installs— mezzanine systems, and makes no reference to performing construction services. See www.aw-systems.com/mezzanine-systems.htm.

Although AWS indicated that sometimes construction could be involved, AWS did not contend that this solicitation included construction, and AWS did not raise with the agency that SIN 361-32 should apply here until the agency selected another firm for the order.

The contracting officer also reviewed the SIN descriptions for SIN 361-30 (–Ancillary Services Relating to Pre-Engineered/Prefabricated Buildings and Structures—) and SIN 361-32 (–Installation and Site Preparation for Pre-Engineered/Prefabricated Buildings and Structures—) under Schedule 56 to determine the appropriate labor SIN to use. These descriptions are as follows:

SIN 361-30, Ancillary Services Relating to Pre-Engineered/ Prefabricated Buildings and Structures -- Including services relating to and ordered in conjunction with products purchased under the supply schedule contract, such as, field assembly, training, consultation and design assistance. EXCLUDES Construction as defined by FAR 2.101; Architectural Engineering Services (A&E) under the Brooks Architect-Engineers Act as stated in [FAR] Part 36; and services applicable to the Service Contract Act.

* * * * *

SIN 361-32, Installation and Site Preparation for Pre-Engineered/ Prefabricated Buildings and Structures -- Applicable to installation and site preparation services ordered in conjunction with buildings and structures purchased under the supply schedule contract. SPECIAL ORDERING PROCEDURES, WHICH INCLUDE DAVIS BACON WAGE RATES AND CONSTRUCTION CLAUSES FOR INSTALLATION AND SITE PREPARATION APPLY TO THIS SIN. EXCLUDES Architectural Engineering Services (A&E) under the Brooks Architect-Engineers Act as stated in [FAR] Part 36.

* * * * *

Agency Report, Tab 23, SIN Descriptions; Contracting Officer's Statement at 2.

As noted above, the agency has provided a reasonable basis for its determination that the installation services here are for assembly and not construction, and, therefore, are more appropriately procured under SIN 361-30. In this regard, the RFQ requirements were reasonably found to not involve construction, alteration, or repair of the building or building structures, and the RFQ does not contain any construction clauses or Davis Bacon Act wage rate requirements. Thus, we find that the agency reasonably determined that SIN 361-32 was not applicable. Since FedSource's GSA schedule and its subcontractors' GSA schedules contained SIN 361-30, and since of the services purchased were either on these schedules or purchased through competition as –open market— items, we find that the order placed with FedSource was unobjectionable.

The protest is denied.

Lynn H. Gibson

Acting General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.