B-402404.2

Staker & Parsons Companies

Mar 1, 2010.Federal Highway AdministrationDepartment of Transportation
DeniedSet-Aside / Small BusinessSmall Business

GAO Digest

Staker & Parsons Companies of Elko, Nevada, protests the award of a contract to Eagle Peak Rock and Paving, Inc., a Historically Underutilized Business Zone (HUBZone) small business concern, under invitation for bids (IFB) No. DTFH68-09-B-00045, issued by the Department of Transportation, Federal Highway Administration (FHwA), for road repair and improvement. Staker & Parsons argues that it submitted the lowest-priced bid when options are considered. We deny the protest

Key Facts

Decision date
Mar 1, 2010.
Publicly released
Mar 1, 2010.
Agency
Federal Highway Administration
Department
Department of Transportation
Decided by
Lynn H. Gibson, Acting General Counsel

Counsel

Protester
Kesler & Rust
Joseph C. Rust
Agency
Federal Highway Administration
David Sett
GAO
Office of the General Counsel, GAO
Peter D. Verchinski, Guy R. Pietrovito

Procurement

Awardee
Eagle Peak Rock and Paving, Inc.
Solicitation
DTFH68-09-B-00045 (IFB)
Instrument
Contract
Issued by
Department of Transportation
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision6,416 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Cases cited

2 cases this decision cites, in the order it first names them. No published copy of any of them was confirmed, so each is shown without a link.

B-00045Cober Elecs., Inc.B-173643

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

Staker & Parsons Companies of Elko, Nevada, protests the award of a contract to Eagle Peak Rock and Paving, Inc., a Historically Underutilized Business Zone (HUBZone) small business concern, under invitation for bids (IFB) No. DTFH68-09-B-00045, issued by the Department of Transportation, Federal Highway Administration (FHwA), for road repair and improvement. Staker & Parsons argues that it submitted the lowest-priced bid when options are considered.

Decision

Matter of: Staker & Parsons Companies

File: B-402404.2

Date: March 1, 2010

Joseph C. Rust, Esq., Kesler & Rust, for the protester.

David Sett, Esq., Federal Highway Administration, for the agency.

Peter D. Verchinski, Esq., and Guy R. Pietrovito, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Where an invitation for bids for road repair and improvements incorporated the standard Federal Acquisition Regulation clause 52.217-3, "Evaluation Exclusive of Options," agency properly did not consider options prices in evaluating bid prices.

DECISION

Staker & Parsons Companies of Elko, Nevada, protests the award of a contract to Eagle Peak Rock and Paving, Inc., a Historically Underutilized Business Zone (HUBZone) small business concern, under invitation for bids (IFB) No. DTFH68-09-B-00045, issued by the Department of Transportation, Federal Highway Administration (FHwA), for road repair and improvement. Staker & Parsons argues that it submitted the lowest-priced bid when options are considered.

We deny the protest.

The IFB sought bids for road resurfacing, rehabilitation, and restoration in the Humboldt-Toiyabe National Forest, Nevada. Bidders were required to price contract line items (CLIN) for three lengths of road (Schedules A, B, and C) as well as price a number of option CLINs (Options V, W, X, Y, and Z). The IFB stated that award would be based on the lowest price for the work to be completed under Schedule C, unless sufficient funding was not available, in which case Schedule B would be evaluated, and if funds were not available for Schedule B, then Schedule A would be evaluated. IFB at A'4. The IFB also provided for a 10-percent price evaluation preference in favor of HUBZone small business concerns. See IFB at A-ii; Federal Acquisition Regulation (FAR) clause 52.219-4. In addition, the IFB incorporated by reference standard FAR clause 52.217-3, "Evaluation Exclusive of Options (APR 1984)," which states in its entirety:

As prescribed in 17.208(a), insert a provision substantially the same as in the following in solicitations when the solicitation includes an option clause and does not include one of the provisions prescribed in 17.208(b) or (c):

EVALUATION EXCLUSIVE OF OPTIONS

(APR 1984)

The Government will evaluate offers for award purposes by including only the price for the basic requirement; i.e., options will not be included in the evaluation for award purposes.

FHwA received seven bids, including Staker & Parsons's and Eagle Peak's. Staker & Parsons bid $3,596,741.40 for Schedule C and Eagle Peak bid $3,945,078 to perform the same work. Agency Report (AR), Tab 3, Bid Abstract. Applying the HUBZone preference, the agency added 10 percent ($359,674.14) to Staker & Parson's Schedule C bid, which resulted in an overall evaluated price of $3,956,415.40. The agency determined that it had sufficient funding to make award under Schedule C, as well as award options W, X, and Z. Award was made to Eagle Peak as the bidder with the lowest evaluated price for Schedule C, and this protest followed.

Staker & Parsons argues that the agency was required to consider the bidders' prices for the option CLINs that the agency awarded, and that, considering the option prices, the protester's overall bid price for Schedule C and for Options W, X and Z is lower than Eagle Peak's, even after application of the HUBZone preference. Staker & Parsons does not dispute that the IFB included the FAR clause that informed bidders that options would not be evaluated, but essentially argues that the agency's incorporation of the clause by reference was ineffective.

Specifically, Staker & Parsons contends that the FAR language requires that the agency "insert a provision in the solicitation" containing language "substantially the same" as the operative language of the clause. In the protester's view, the act of incorporating the clause by reference means the agency did not insert a provision containing substantially similar language. Thus, the protester contends that the failure to include the actual operative words of the clause in the IFB meant that the solicitation failed to inform bidders that award would be based on the schedule prices alone. In short, Staker & Parsons contends that it should have been awarded the contract for Schedule C and Options W, X and Z.

We find no merit to Staker & Parsons's contention that FHwA's incorporation of this standard FAR clause was ineffective, or failed to inform bidders that option prices would not be evaluated. It is a well accepted principle of contract law that when an item is incorporated by reference into a contract or other document, it is not necessary to bodily insert the text of the item itself into the contract or document. See Cober Elecs., Inc., B-173643, Nov. 23, 1971; see also Northrop Grumman Info. Tech., Inc., 535 F.3d 1339, 1343-46 (Fed. Cir. 2008) (providing a lengthy explanation of incorporation by reference in government contracts). In this regard, the FAR provides that provisions and clauses "should be incorporated by reference to the maximum practical extent, rather than being incorporated in full text . . . ." FAR sect. 52.102(a).

Here, as noted above, the IFB identified FAR clause 52.217-3, "Evaluation Exclusive of Options," as applying to this solicitation. Given this express incorporation, bidders were on notice that option prices would not be evaluated. To the extent that the protester believed that option prices should be evaluated or that the solicitation was in someway ambiguous with respect to the evaluation of option prices, such allegations concern alleged apparent solicitation improprieties that the protester was required to raise prior to bid opening. 4 C.F.R. sect. 21.2(a)(1) (2009).

The protest is denied.

Lynn H. Gibson

Acting General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Protest Ground

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.