B-403341

Eagle Aviation Services and Technology, Inc.

Oct 14, 2010.Air ForceSmall Business Administration
DeniedSmall Business

GAO Digest

Eagle Aviation Services and Technology, Inc., of Reston, Virginia, protests the rejection of its proposal under request for proposals (RFP) No. FA4664-10-R-0005, issued by the Department of the Air Force for base operating services at March Air Reserve Base (ARB), California. The protester contends that the contracting officer abused his discretion in failing to give it the opportunity to address an informational deficiency in its proposal pertaining to its experience. We deny the protest.

Key Facts

Decision date
Oct 14, 2010.
Publicly released
Oct 14, 2010.
Agency
Air Force
Department
Small Business Administration
Decided by
Lynn H. Gibson, Acting General Counsel

Counsel

Protester
Wayne A. Keup
Agency
Department of the Air Force
Sharon A. Jenks
GAO
Office of the General Counsel, GAO
Jennifer D. Westfall-McGrail, Christine S. Melody

Procurement

Solicitation
FA4664-10-R-0005 (RFP)
Instrument
Contract
Issued by
Department of the Air Force
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision12,114 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Cases cited

5 cases this decision cites, in the order it first names them. No published copy of any of them was confirmed, so each is shown without a link.

Gemmo-CCCB-297447.2Menendez-Donnell & Assocs.B-286599Inc.B-193261American Tech. Servs., Inc.B-214466.2B-214466.2B-214466.3

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

Eagle Aviation Services and Technology, Inc., of Reston, Virginia, protests the rejection of its proposal under request for proposals (RFP) No. FA4664-10-R-0005, issued by the Department of the Air Force for base operating services at March Air Reserve Base (ARB), California. The protester contends that the contracting officer abused his discretion in failing to give it the opportunity to address an informational deficiency in its proposal pertaining to its experience.

B-403341, Eagle Aviation Services and Technology, Inc., October 14, 2010

DOCUMENT FOR PUBLIC RELEASE

The decision issued on the date below was subject to a GAO Protective Order. This redacted version has been approved for public release.

Decision

Matter of: Eagle Aviation Services and Technology, Inc.

File: B-403341

Date: October 14, 2010

Wayne A. Keup, Esq., for the protester.

Sharon A. Jenks, Esq., Department of the Air Force, for the agency.

Jennifer D. Westfall-McGrail, Esq., and Christine S. Melody, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Protest alleging that agency should have given protester the opportunity to show that material information required to be included in one volume of the proposal was included in a different volume is denied where solicitation provided that only information included in designated volume would be considered in evaluating proposals.

DECISION

Eagle Aviation Services and Technology, Inc., of Reston, Virginia, protests the rejection of its proposal under request for proposals (RFP) No. FA4664-10-R-0005, issued by the Department of the Air Force for base operating services at March Air Reserve Base (ARB), California. The protester contends that the contracting officer abused his discretion in failing to give it the opportunity to address an informational deficiency in its proposal pertaining to its experience.

We deny the protest.

The RFP, which is set aside for small business competition, contemplates the award of a single contract for the management and operation of multiple base operating services at March ARB. Among the services to be furnished are transient aircraft maintenance and airfield management. The solicitation provides for a multiple-step evaluation process; under the first step, offeror compliance with two "minimum qualification requirements" pertaining to experience is to be evaluated on a go/no-go basis. To establish compliance with the minimum qualification requirements, the RFP instructed offerors to identify and furnish detailed information regarding previously-performed contracts for similar services, including annual and total dollar values of the pertinent functions managed and/or performed, performance period, and number of employees.

Other services are base supply, motor vehicle management, traffic management, real property maintenance, and fuels management.

The minimum qualification requirements are that (1) the prime have at least 1 year of experience within the last 5 years managing and performing a single, or simultaneously performing multiple, base operating services (or equivalent commercial) contract(s) encompassing at least two services similar in size and scope to the services to be provided here, and (2) the offeror's team, as a whole, have experience within the last 5 years in providing services similar in size and scope to each of the services to be provided here. RFP sect. M-1(1). The RFP stated that "[a]n offeror that does not meet the minimum qualification requirements will be eliminated from the competition." RFP sect. M-1(2).

The RFP instructed offerors that their proposals were to be submitted in four volumes: administrative/contract documentation, technical capabilities, present/past performance, and cost/price. Information establishing compliance with the minimum qualification requirements was to be included in volume I (administrative/contract documentation). RFP sect. L-1, Table 1. The RFP advised that "[e]ach volume shall be written on a 'stand-alone' basis so that its contents may be evaluated without cross-referencing to other volumes of the proposal." RFP sect. L-1(e)(1). Along the same lines, the RFP admonished offerors that information required for proposal evaluation not found in the designated volume would be regarded as omitted. RFP sect. L-1(e)(3).

The protester submitted a timely proposal in response to the RFP; the proposal comprised four volumes. Volume I included a tab marked "Minimum Qualifications," which consisted of a single page. The page described a contract that the protester had performed at Willow Grove Air Reserve Station, under which Eagle had provided real property maintenance and services, supply, traffic management, vehicle operations and maintenance, and fuels management. No information was provided regarding the performance of transient aircraft maintenance or airfield management services.

By letter dated July 14, 2010, the contracting officer notified Eagle that its proposal had been rejected for failing to demonstrate experience in the areas of transient aircraft maintenance and airfield management. The protester immediately contacted the contracting officer and asked him to reconsider his decision. Eagle explained that it had inadvertently omitted four pages addressing its minimum qualifications from volume I of its proposal, but that it had furnished a complete description of its experience in volume III. Eagle also noted that its proposal cover letter, which was included in volume I, described experience on the part of the protester and its subcontractor in performing all of the required services. The protester asserted that the contracting officer was required to "obtain clarification of the perceived omissions," Protest, Exh. 2; according to Eagle, such an exchange would have disclosed that the omissions were a clerical error, which could have been corrected through reference to volume III. By letter dated July 16, the contracting officer rejected the protester's argument and refused to reinstate Eagle's proposal in the competition. On July 19, Eagle protested to our Office.

The contracting officer also noted that Eagle had failed to demonstrate relevant experience in fuels management. The contracting officer subsequently conceded that this was an error and that the protester had addressed fuels management in its minimum qualifications submission.

Eagle argues that the contracting officer abused his discretion in failing to give it the opportunity to show that information establishing its compliance with the minimum qualifications requirement was present in the cover letter and volume III of its proposal. In the alternative, Eagle argues that the contracting officer's rejection of its proposal as noncompliant was essentially a determination of nonresponsibility, which, because the protester is a small business, should have been referred to the Small Business Administration (SBA) for consideration under Certificate of Competency (COC) procedures.

Eagle did note in the cover letter of its proposal that its proposed subcontractor was furnishing airfield management services at both a specified air reserve station and a specified Air Force base, and that it had experience in furnishing "transient alert" services at another specified Air Force base. Eagle did not, however, furnish in the cover letter the detailed information required by the RFP to establish experience in performing services similar in scope and magnitude to those to be provided here. For example, the cover letter did not provide information regarding the dollar value of the services that the protester's subcontractor was performing at the other bases and stations or the number of employees working on them. The cover letter also failed to provide information regarding the time period during which the subcontractor had performed the transient alert services (and thus did not establish performance within the last 5 years). In sum, the general information furnished by the protester in its cover letter was clearly insufficient to demonstrate compliance with the RFP's minimum qualification requirements.

The protester also argues that the agency should have given it the opportunity to show that volume III of its proposal contained information establishing its compliance with the minimum qualification requirements. We disagree. The RFP here explicitly advised offerors that only information included in the designated volume would be considered in evaluating proposals. Moreover, there was nothing in volume I of the protester's proposal--which, under the RFP, was the only volume that was to be considered in determining the protester's compliance with the minimum qualification requirements--that would have placed the agency on notice that the protester had inadvertently omitted pages addressing its experience from the volume. As a result, there was no reasonable basis for the contracting officer to regard the protester's failure to furnish the required information as other than a material omission not subject to correction except through discussions, which the agency had no obligation to conduct with Eagle. See RFP sect. M-2(b)(7) (agency reserves right to make award without holding discussions); Gemmo-CCC, B-297447.2, July 13, 2006, 2006 CPD para. 182 at 5.

The protester's suggestion that the contracting officer in fact knew that the missing information was contained elsewhere in the proposal, Comments, Aug. 30, 2010, at 3, is clearly without merit. The protester asserts that its cover letter showed that it met the minimum qualification requirements and the contracting officer thus knew that additional relevant information "would necessarily be included in a properly prepared Volume III." Id. As explained above, the cover letter did not demonstrate that the protester met the qualification requirements. Faced with a Volume I that lacked the information specifically required by the RFP, there was no reason for the contracting officer to "know"--actually or constructively--that the missing information was contained elsewhere in the proposal.

The protester cites two cases in support of its assertion that we will sustain a protest where the agency does not make efforts to bring step one proposals to an acceptable status. Comments, supra at 4-5. Both cases--Angstrom, Inc., B-193261, July 9, 1980, 80-2 CPD para. 20 and Control Central Corp.; American Tech. Servs., Inc., B-214466.2, B-214466.3, July 9, 1984, 84-2 CPD para. 28--involved two-step sealed bidding under FAR subpart 14.5, which differs materially from the procedure established under the RFP here. As explained in Angstrom, two-step sealed bidding contemplates qualification of as many proposals as possible through discussions and does not require compliance with "all details of the specifications." Angstrom, Inc., supra at 6; see FAR sect. 14.503-1(e)(2) (conformance required with the "essential requirements or specifications" in the solicitation). In contrast, the RFP here clearly described how information was to be presented in the proposals and required demonstration of compliance with the minimum qualifications in order for proposals to be considered acceptable, and the protester indisputably omitted the required information from Volume I of its proposal.

We also find no merit in the protester's argument that the contracting officer's rejection of its proposal for failure to demonstrate experience in performing airfield management and transient aircraft maintenance was essentially a determination of nonresponsibility, requiring referral to the SBA under COC procedures. Where an agency finds a proposal to be unacceptable based on the offeror's failure to submit required information establishing its experience, the finding does not constitute a determination that the offeror is not a responsible prospective contractor. Menendez-Donnell & Assocs., B-286599, Jan. 16, 2001, 2001 CPD para. 15 at 3 n.1.

The protest is denied.

Lynn H. Gibson

Acting General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.