B-404614.5

Boston Harbor Development Partners, LLC

Feb 17, 2012.Federal Bureau of InvestigationGeneral Services Administration
DeniedCostsCorrective Action

A request that GAO recommend the protester recover its protest costs.

GAO Digest

Boston Harbor Development Partners, LLC (BHDP), of Boston, Massachusetts, requests that our Office recommend that the General Services Administration (GSA) pay the firm the reasonable costs of filing and pursuing its protest with respect to the award of a contract to Emerald Corporate Center, LLC (ECC), of Chelsea, Massachusetts, under solicitation for offers (SFO) No. 2818A for the design, construction, and leasing of a dedicated campus facility for the Federal Bureau of Investigation. We dismissed the protest as academic on November 22, 2011, based on GSA’s statement that it was taking corrective action in the procurement. Boston Harbor Dev. Partners, LLC, B-404614.3, B-404614.4, Nov. 22, 2011. We deny the request.

Key Facts

Decision date
Feb 17, 2012.
Publicly released
Feb 21, 2012.
Agency
Federal Bureau of Investigation
Department
General Services Administration
Decided by
Lynn H. Gibson, General Counsel

Counsel

Requester
Holland & Knight LLP
David S. Black, Robert C. MacKichan Jr., Alexander B. Ginsberg
Agency
General Services Administration
GAO
Office of the General Counsel, GAO
Paul N. Wengert, Sharon L. Larkin

Procurement

Awardee
Emerald Corporate Center, LLC
Solicitation
2818A
Instrument
Contract
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision6,026 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

GAO Bid Protest Regulations1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

7 cases this decision cites, in the order it first names them. 2 of them open in this app; the rest are shown without a link because no published copy of them was confirmed.

Boston Harbor Dev. Partners, LLCB-404614.3B-404614.3B-404614.4IRS Partners-Birmingham--Entitlement to CostsB-251931.4B-251931.4B-251931.5Inc.--CostsB-287728.2LLC--Protest & CostsB-405907.2Inc.--CostsB-403566.2

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

Boston Harbor Development Partners, LLC (BHDP), of Boston, Massachusetts, requests that our Office recommend that the General Services Administration (GSA) pay the firm the reasonable costs of filing and pursuing its protest with respect to the award of a contract to Emerald Corporate Center, LLC (ECC), of Chelsea, Massachusetts, under solicitation for offers (SFO) No. 2818A for the design, construction, and leasing of a dedicated campus facility for the Federal Bureau of Investigation. We dismissed the protest as academic on November 22, 2011, based on GSA’s statement that it was taking corrective action in the procurement. Boston Harbor Dev. Partners, LLC, B-404614.3, B-404614.4, Nov. 22, 2011.

We deny the request.

Decision

Matter of: Boston Harbor Development Partners, LLC--Costs

File: B-404614.5

Date: February 17, 2012

David S. Black, Esq., Robert C. MacKichan Jr., Esq., and Alexander B. Ginsberg, Esq., Holland & Knight LLP, for the requester.

Nancy E. O’Connell, Esq., General Services Administration, for the agency.

Paul N. Wengert, Esq., and Sharon L. Larkin, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Protester is not entitled to reimbursement of protest costs after agency took corrective action where protest was not clearly meritorious.

DECISION

Boston Harbor Development Partners, LLC (BHDP), of Boston, Massachusetts, requests that our Office recommend that the General Services Administration (GSA) pay the firm the reasonable costs of filing and pursuing its protest with respect to the award of a contract to Emerald Corporate Center, LLC (ECC), of Chelsea, Massachusetts, under solicitation for offers (SFO) No. 2818A for the design, construction, and leasing of a dedicated campus facility for the Federal Bureau of Investigation. We dismissed the protest as academic on November 22, 2011, based on GSA’s statement that it was taking corrective action in the procurement. Boston Harbor Dev. Partners, LLC, B-404614.3, B-404614.4, Nov. 22, 2011.

We deny the request.

Our Bid Protest Regulations, 4 C.F.R. § 21.8(e) (2011), provide that we may recommend that an agency pay protest costs where the agency decides to take corrective action in response to a protest. We will make such a recommendation, however, only where the agency unduly delayed taking corrective action in the face of a clearly meritorious protest. CSL Birmingham Assocs.; IRS Partners-Birmingham--Entitlement to Costs, B-251931.4, B-251931.5, Aug. 29, 1994, 94-2 CPD ¶ 82 at 3. Our rule is intended to prevent inordinate delay in investigating the merits of a protest and taking corrective action once an error is evident, so that a protester will not incur unnecessary effort and expense in pursuing its remedies before our Office. Professional Landscape Mgmt. Servs., Inc.--Costs, B-287728.2, Nov. 2, 2001, 2001 CPD ¶ 180 at 5.

BHDP filed an initial protest on October 6, 2011. Protest at 1. The protest argued that ECC’s site did not meet a set of mandatory minimum requirements that were to be evaluated as “Phase I” of the procurement, that ECC’s offer constituted a prohibited capital lease, that ECC had been allowed to make a late revision to its offer, that the GSA should have held discussions with BHDP, and that the GSA had misevaluated BHDP’s offer. Protest at 13-17.

On November 10, the GSA submitted an agency report (subsequently revised, at our Office’s request, to provide citations to the record), in response to the protest allegations. On November 21, BHDP filed comments which raised new protest issues. Our Office requested a supplemental agency report, and we expressed our view that a hearing would likely be necessary following the receipt of the supplemental agency report and supplemental comments. Fax from GAO to parties, Nov. 14, 2011, at 1.

On November 18, the GSA announced that it would take corrective action by reevaluating offers and “scrutiniz[ing] its price evaluations pursuant to OMB [Office of Management and Budget] Circular A-11.” Letter from Counsel for GSA to GAO, Nov. 18, 2011, at 1.

In its request for costs, BHDP argues that its protest was clearly meritorious as demonstrated by the GSA’s including a reevaluation of the Phase I proposals, and additional scrutiny of both offerors’ compliance with OMB Circular No. A-10, as part of the corrective action. Request for Costs at 2. BHDP argues that these aspects of the corrective action tacitly acknowledged the merit of its protest and show that the GSA had no defensible position. Id.

We disagree. The mere fact than an agency decides to take corrective action does not necessarily establish that a statute or regulation has been violated. Sourcelinq, LLC--Protest & Costs, B-405907.2 et al., Jan. 27, 2012, 2012 CPD ¶ ___ at 6. Here, the record produced by the GSA provided some support for the agency’s assertions that it had analyzed ECC’s offer and had concluded that the offer complied with OMB Circular No. A-10. E.g., AR, Tab 1, Affidavit of GSA Director of Real Estate Acquisition, Nov. 4, 2011, at 1. Additionally, while we had questions and concerns regarding the adequacy of the agency’s evaluation record, we had not concluded that BHDP’s complaints of misevaluation were clearly meritorious. Rather, as noted above, our Office had expressed the view that a hearing would likely be necessary to more fully develop the protest record. Our consideration of a hearing reflected our view that additional development of the record was necessary to reach a decision regarding the merits of the protest. In short, at the time of the agency’s corrective action, we viewed the protest as presenting a close question and, therefore, it was not clearly meritorious. See Distributed Solutions, Inc.--Costs, B-403566.2, Feb. 14, 2011, 2011 CPD ¶ 41 at 4 (protest was not clearly meritorious where agency took corrective action while GAO was considering holding a hearing).

The request is denied.

Lynn H. Gibson

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Protest Ground

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.