B-405813

Argus & Black, Inc.

Jan 3, 2012.ArmyDepartment of War
DeniedCommerciality

GAO Digest

Argus & Black, Inc., of Cary, North Carolina, protests the award of a contract to Yorktown Systems Group, Inc., of Huntsville, Alabama, under request for quotations (RFQ) No. W9124E-11-T-0061, issued by the Department of the Army for instructor support services. We deny the protest.

Key Facts

Decision date
Jan 3, 2012.
Publicly released
Aug 13, 2012.
Agency
Army
Department
Department of War

Formerly the Department of Defense

Decided by
Lynn H. Gibson, General Counsel

Counsel

Protester
A. Jeff Ifrah
Intervenor (Yorktown Systems Group, Inc)
Lanier Ford Shaver & Payne P.C
J. Dale Gipson, Michael P. Johnson
Agency
Department of the Army
Robert B. Neill
GAO
Office of the General Counsel, GAO
Pedro E. Briones, Guy R. Pietrovito

Procurement

Awardee
Yorktown Systems Group, Inc.
Solicitation
W9124E-11-T-0061 (RFQ)
Instrument
Contract
Issued by
Department of the Army
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision10,747 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Federal Acquisition Regulation1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

12 cases this decision cites, in the order it first names them. 1 of them opens in this app; the rest are shown without a link because no published copy of them was confirmed.

Muddy Creek Oil and Gas, Inc.B-296836Solers, Inc.B-404032.3 B-404032.4Marine Pollution Control Corp.B-270172SunEdison, LLCB-298583B-298583B-298583.2Sawtooth Enters., Inc.B-281218Computers Universal, Inc.B-297552DOER MarineB-295087Citywide Managing Servs. of Port Washington, Inc.B-281287.12B-281287.12B-281287.13Washington-Harris GroupB-401794B-401794B-401794.2

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

Argus & Black, Inc., of Cary, North Carolina, protests the award of a contract to Yorktown Systems Group, Inc., of Huntsville, Alabama, under request for quotations (RFQ) No. W9124E-11-T-0061, issued by the Department of the Army for instructor support services.

We deny the protest.

DOCUMENT FOR PUBLIC RELEASE

The decision issued on the date below was subject to a GAO Protective Order. This redacted version has been approved for public release.

Decision

Matter of: Argus & Black, Inc.

File: B-405813

Date: January 3, 2012

A. Jeff Ifrah, Esq., for the protester.

J. Dale Gipson, Esq., and Michael P. Johnson, Esq., Lanier Ford Shaver & Payne P.C., for Yorktown Systems Group, Inc., the intervenor.

Robert B. Neill, Esq., Department of the Army, for the agency.

Pedro E. Briones, Esq., and Guy R. Pietrovito, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

1. Protest that awardee’s quotation failed to provide a fixed price for a particular contract line item (CLIN) is denied where the CLIN provided for the reimbursement of a vendor’s travel costs up to a not-to-exceed amount, to which the awardee did not take exception.

2. Protest that an awardee’s quotation was technically unacceptable is denied where the agency reasonably found the awardee’s quotation to be acceptable, consistent with the solicitation’s stated evaluation criteria.

DECISION

Argus & Black, Inc., of Cary, North Carolina, protests the award of a contract to Yorktown Systems Group, Inc., of Huntsville, Alabama, under request for quotations (RFQ) No. W9124E-11-T-0061, issued by the Department of the Army for instructor support services.

Although the protest here concerns the placement of an order under an RFQ, the RFQ and the parties refer to the award of a contract as does this decision for the sake of consistency.

We deny the protest.

BACKGROUND

The RFQ, issued under the commercial item and simplified acquisition procedures of Federal Acquisition Regulation (FAR) Parts 12 and 13, provided for the award of a fixed-price contract to train personnel in security force assistance, Iraqi and Afghan cultural awareness, and personnel recovery. RFQ at 27; RFQ amend. 1, at 3; Performance Work Statement (PWS) at 2. The PWS requires the vendor to provide qualified instructors, including a mobile training team, in several subject areas. See PWS at 2-18. Training was to be provided in accordance with relevant field manuals, guidance documents, and other requirements specified in the PWS. See id. For example, personnel recovery training was required to be based on the Army’s Field Manual No. 3-50.1, “Army Personnel Recovery,” and taught in accordance with the U.S. Armed Forces Command’s (FORSCOM) pre-deployment training guidance, as well as additional program instructions to be provided by the agency. See id. at 18.

Offerors were informed that award would be made on a lowest-priced, technically acceptable basis considering the following evaluation factors: price, technical, and past performance. RFQ at 9. With regard to the technical factor, the RFQ required vendors to provide a detailed training methodology and document their ability to train students in accordance with the PWS and military policies and procedures. See id. With regard to price, vendors were instructed to quote fixed prices for four contract line items (CLINS 0001, 0002, 0004, and 0005). CLIN 0003 provided for the reimbursement of a vendor’s actual costs for travel up to a not-to-exceed amount of $200,000 in accordance with Joint Travel Regulations and the PWS. Id. at 3-5: PWS at 20. In response to questions from vendors, the agency advised them to use $200,000 as a “plug number” for the CLIN 0003 travel costs. RFQ amend. 1, Questions/Answers, at 2.

The agency received five quotations, including those of Yorktown and Argus. Yorktown’s and Argus’s quotations were both found to be technically acceptable, and their price quotations were evaluated by the CO and the contract specialist. See Contracting Officer’s (CO) Statement at 2-3; Agency Report (AR), Tab 8, Evaluation Memorandum, at 1-3. Yorktown’s quotation was evaluated as the lowest priced at $1,754,980, and Argus’s quotation was evaluated as the second lowest at $1,760,075. Id. With respect to the price evaluation, the Army used the $200,000 plug number in evaluating vendors’ travel costs under CLIN 0003. CO’s Supp. Statement at 1; Supp. AR at 5. As pertinent here, Yorktown stated in its price quotation that “[i]n performance of the contract, travel will be invoiced on a cost reimbursable basis; [in accordance with] the [Joint Travel Regulations], [DELETED] by Yorktown Systems Group.” See Yorktown’s Quotation at 16.

Award was made to Yorktown as the vendor with the lowest-priced, technically acceptable quotation, and this protest followed.

DISCUSSION

Argus complains that Yorktown’s quotation should have been rejected because the awardee did not offer a fixed price for CLIN 0003. Specifically, the protester argues that Yorktown’s quotation, which stated that the vendor’s travel costs would have a [DELETED], was contrary to the RFQ’s requirement for fixed prices. See Protester’s Comments and Supp. Protest at 3-4. The protester also contends that in evaluating Yorktown’s price quotation the Army should have added [DELETED] to the $200,000 plug number for travel costs under CLIN 0003 to reflect Yorktown’s [DELETED]. Id. Argus states that adding [DELETED] to Yorktown’s evaluated price would result in the protester’s evaluated price being lower than Yorktown’s. See id. at 3; Protester’s Supp. Comments at 3.

A quotation that fails to conform to material terms and conditions of a solicitation should be considered unacceptable and may not form the basis for the issuance of a task order. Muddy Creek Oil and Gas, Inc., B-296836, Aug. 9, 2005, 2005 CPD ¶ 143 at 2. The requirement to propose fixed prices is a material term or condition of a solicitation requiring such pricing. Solers, Inc., B-404032.3, B-404032.4, Apr. 6, 2011, 2011 CPD ¶83 at 4; Marine Pollution Control Corp., B-270172, Feb. 13, 1996, 96-1 CPD ¶ 73 at 2-3. Where a solicitation requests proposals on a fixed-price basis, a price offer that is conditional and not firm cannot be considered for award. Id.; SunEdison, LLC, B-298583, B-298583.2, Oct. 30, 2006, 2006 CPD ¶ 168 at 5.

Here, contrary to the protester’s premise, the RFQ did not request the quotation of a fixed price for CLIN 0003. Rather, as noted above, the RFQ provided that vendors would be reimbursed their costs up to a not-to-exceed amount of $200,000 under this CLIN 0003 in accordance with the Joint Travel Regulations and the PWS. See RFQ at 4; PWS at 20. Nothing in Yorktown’s quotation indicates that the awardee took exception to solicitation provision that the firm would be reimbursed its travel costs up the not-to-exceed amount. We find that the Army reasonably evaluated all vendors’ quotations using the $200,000 plug number that was provided for CLIN 0003. See AR, Tab 11, Quotation Abstract.

Argus does not contend that Yorktown’s quotation would violate either the Joint Travel Regulations or the specific provision of the PWS providing for the reimbursement of travel costs.

Argus also complains that Yorktown’s quotation did not satisfy certain PWS requirements. See Protester’s Comments and Supp. Protest at 4-5; Protester’s Supp. Comments at 3-4. In this respect, the protester states that the evaluators expressed concern over Yorktown’s personnel recovery training and failure to mention the relevant guidance, whereas the evaluators noted Argus’s proposed FORSCOM personnel recovery training. See Protester’s Comments and Supp. Protest at 5.

Argus initially protested that Yorktown did not have relevant past performance, that the agency failed to consider risks associated with Yorktown’s compensation for course instructions and with Yorktown’s proposed hours of instruction, and that Yorktown’s price was not reasonable. Protest at 1-2. The Army responded to these arguments in its report. Because the protester did not in its comments address the agency’s responses, we consider these issues to be abandoned. Washington-Harris Group, B-401794, B-401794.2, Nov. 16, 2009, 2009 CPD ¶ 230 at 5 n.3.

Simplified acquisition procedures are designed to, among other things, reduce administrative costs, promote efficiency and economy in contracting, and avoid unnecessary burdens for agencies and contractors. FAR § 13.002; Sawtooth Enters., Inc., B-281218, Dec. 7, 1998, 98-2 CPD ¶ 139 at 3. When using simplified acquisition procedures, an agency must conduct the procurement consistent with a concern for fair and equitable competition and must evaluate quotations in accordance with the terms of the solicitation. In reviewing protests of an allegedly improper simplified acquisition evaluation, we examine the record to determine whether the agency met this standard and executed its discretion reasonably. Computers Universal, Inc., B-297552, Feb. 14, 2006, 2006 CPD ¶ 42 at 4-5; DOER Marine, B-295087, Dec. 21, 2004, 2004 CPD ¶ 252 at 3.

Here, we find that the agency reasonably found that Yorktown’s quotation was technically acceptable. Although the agency’s evaluators noted qualitative differences between the vendors’ technical quotations, both firms’ quotations were found to satisfy the RFQ requirements and to be technically acceptable. With respect to the protester’s contention that Yorktown would not satisfy the requirement to provide training in accordance with FORSCOM guidance, the Army states that, although Yorktown did not specifically refer to the FORSCOM guidance in its quotation, the awardee fully explained its instruction methodology and how it would ensure that its training would be consistent with all applicable policy guidance. Supp. AR at 9. Based upon this, the Army found Yorktown’s quotation to be acceptable. Although Argus disagrees with the agency’s judgment in this regard, the protester’s disagreement does not establish that the agency acted unreasonably. See Citywide Managing Servs. of Port Washington, Inc., B-281287.12, B-281287.13, Nov. 15, 2000, 2001 CPD ¶ 6 at 10-11.

Yorktown’s technical quotation stated that its instructors would provide instruction in personnel recovery operations as required, and listed five policies and procedures that Yorktown would use in refining or developing training materials in that regard. Yorktown’s Quotation at 14.

The Army notes that there was no requirement in the RFQ that vendors repeat the title of specific training policies. Supp. AR at 8.

The protest is denied.

Lynn H. Gibson

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.