B-406025

Integrated Science Solutions, Inc.

Jan 17, 2012.National Aeronautics and Space AdministrationNational Aeronautics and Space Administration
Denied

GAO Digest

Integrated Science Solutions, Inc. (ISSi), of Walnut Creek, California, protests the National Aeronautics and Space Administration’s (NASA) decision to cancel the order awarded to ISSi, and reevaluate the quotations that were received in response to request for quotations (RFQ) No. NND10348201R, for environmental consulting services. We deny the protest.

Key Facts

Decision date
Jan 17, 2012.
Publicly released
Feb 6, 2012.
Agency
National Aeronautics and Space Administration
Department
National Aeronautics and Space Administration
Decided by
Lynn H. Gibson, General Counsel

Counsel

Protester
Rogers Joseph O'Donnell
Patricia A. Meagher, Suhani Kamdar, Lauren B. Kramer
Agency
National Aeronautics and Space Administration
Victoria H. Kauffman, J. Brett Swanson
GAO
Office of the General Counsel, GAO
Mary G. Curcio, David A. Ashen

Procurement

Solicitation
NND10348201R (RFQ)
Instrument
Contract
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision6,346 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Cases cited

4 cases this decision cites, in the order it first names them. No published copy of any of them was confirmed, so each is shown without a link.

Major Contracting Servs., Inc.B-400737.3Main Bldg. Maintenance, Inc.B-279191.2SWR, Inc.B-284075B-284075B-284075.2

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

Integrated Science Solutions, Inc. (ISSi), of Walnut Creek, California, protests the National Aeronautics and Space Administration’s (NASA) decision to cancel the order awarded to ISSi, and reevaluate the quotations that were received in response to request for quotations (RFQ) No. NND10348201R, for environmental consulting services.

We deny the protest.

B-406025, Integrated Science Solutions, Inc., January 17, 2012

DOCUMENT FOR PUBLIC RELEASE

The decision issued on the date below was subject to a GAO Protective Order. This redacted version has been approved for public release.

Date: January 17, 2012

Patricia A. Meagher, Esq., Suhani Kamdar, Esq., and Lauren B. Kramer, Esq., Rogers Joseph O'Donnell, for the protester.

Victoria H. Kauffman, Esq., and J. Brett Swanson, Esq., National Aeronautics and Space Administration, for the agency.

Mary G. Curcio, Esq., and David A. Ashen, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Agency decision to cancel award to protester and reevaluate proposals is unobjectionable where, in response to agency level protest, agency discovered unequal treatment in evaluation which appeared to benefit protester in the evaluation.

DECISION

Integrated Science Solutions, Inc. (ISSi), of Walnut Creek, California, protests the National Aeronautics and Space Administration's (NASA) decision to cancel the order awarded to ISSi, and reevaluate the quotations that were received in response to request for quotations (RFQ) No. NND10348201R, for environmental consulting services.

We deny the protest.

The RFQ was issued to five vendors that hold a General Services Administration (GSA), Federal Supply Service (FSS) schedule contract for Environmental Services, Consulting. The RFQ provided for the order to be issued on a best value basis, based on the following evaluation factors: technical capability (with subfactors for staffing plan, management plan, and safety and health plan); past performance; and price. As relevant to this protest, the solicitation further provided that the staffing plan would be evaluated against six elements: appropriateness and rationale for the proposed skill mix; identification of key personnel; ability and methodology to hire and retain qualified staff; corporate staffing standards; rationale for hiring or replacing incumbent personnel; and methods for addressing absences and surge requirements. RFQ, Att. A. Vendors were required to include their GSA FSS contracts with their offers.

Following the evaluation of offers, ISSi's quotation was selected as offering the best value to the government, and ISSi was awarded the order. Subsequently, another offeror protested to NASA that ISSi's GSA contract required all of its proposed personnel to have a college degree and a certain number of years experience. According to that protester, as a result of this requirement, ISSi would be unable to retain a substantial majority of the incumbent staff. The contracting officer reviewed the protest and agreed that the evaluation of ISSi's quotation should have considered the likelihood ISSi would be unable to hire incumbent staff. In this regard, the contracting officer further found that another offeror had been assigned two significant weaknesses related to the possibility that it would have trouble hiring incumbent staff. COS at 7. The contracting officer therefore decided to cancel the award to ISSi, reevaluate quotations, and make a new award determination. ISSi protests the agency's corrective action.

Contracting officials in negotiated procurements have broad discretion to take corrective action where the agency determines that such action is necessary to ensure fair and impartial competition. Major Contracting Servs., Inc., B-400737.3, Dec. 17, 2008, 2008 CPD ¶ 230 at 2. In this regard, it is not necessary for an agency to conclude that the protest is certain to be sustained before it may take corrective action; rather, where the agency has reasonable concern that there were errors in the procurement, we view it as within the agency's discretion to take corrective action even if the protest could be denied. Main Bldg. Maintenance, Inc., B-279191.2, Aug. 5, 1998, 98-2 CPD ¶ 47 at 3.

Here, the agency explains that it was necessary to cancel the award because it could not determine from ISSi's quotation whether the degree requirements in its GSA schedule contract would impede its ability to hire incumbent staff. The agency further reports that in reviewing the agency level protest it became aware that it had treated vendors unequally, because while the agency had not considered how the degree requirements would affect ISSi's ability to hire incumbent staff, another offeror, with similar degree requirements in its GSA schedule contract, was assessed two significant weaknesses related to the possibility that it would have trouble hiring incumbent staff. COS at 7.

ISSi argues that the failure to capture incumbent staff was not an evaluation factor and thus should not have been the basis for evaluation or for canceling the award. However, while it may be true that the ability to capture incumbent staff was not a stated evaluation factor, it is clear from the record that the agency in fact took into account this consideration when evaluating some of the quotes. Again, [DELETED], Source Selection Statement (SSS) at 4-5, while another offeror was assigned two significant weaknesses related to its apparent inability to retain incumbent staff. SSS at 8. Further, one of the significant weaknesses assigned to that other offeror was specifically based on the hiring limitations resulting from the degree requirements in the offeror's schedule contract, an issue that the agency did not even consider in evaluating ISSi's quotation. Under these circumstances, we find that the agency made a reasonable decision to cancel the award and reevaluate quotations. In this regard, it is a fundamental principle of federal procurement that competition be conducted on an equal basis and that offerors are treated equally in the evaluation process. SWR, Inc., B-284075, B-284075.2, Feb. 16, 2000, 2000 CPD ¶ 43 at 3.

The protest is denied.

Lynn H. Gibson

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.