B-406228.2

Kingdomware Technologies

May 10, 2012.Department of Veterans AffairsDepartment of Veterans Affairs
DeniedCostsSet-Aside / Small BusinessSmall Business

A request that GAO recommend the protester recover its protest costs.

GAO Digest

Kingdomware Technologies, Inc., of Waldorf, Maryland, a service-disabled veteran-owned small business (SDVOSB) concern, requests that we recommend that it be reimbursed the costs of filing and pursuing its protest challenging the Department of Veterans Affairs’ (VA) issuance of a purchase order (No. 679-C25041) to LiveProcess Corporation, of Verona, New Jersey, under LiveProcess’ General Services Administration Federal Supply Schedule contract. We deny the request.

Key Facts

Decision date
May 10, 2012.
Publicly released
May 11, 2012.
Agency
Department of Veterans Affairs
Department
Department of Veterans Affairs
Decided by
Lynn H. Gibson, General Counsel

Counsel

Protester
Kingdomware Technologies
Agency
Department of Veterans Affairs
Natica C. Neely, Dennis Foley
GAO
Office of the General Counsel, GAO
Jacqueline Maeder, David A. Ashen

Procurement

Instrument
Purchase order
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision6,101 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

GAO Bid Protest Regulations1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

5 cases this decision cites, in the order it first names them. 1 of them opens in this app; the rest are shown without a link because no published copy of them was confirmed.

B-406228AAR Aircraft Servs.--CostsB-291670.6Apptis Inc.--CostsB-402146.3First Fed. Corp.--CostsB-293373.2Inc.--CostsB-298575.4

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

Kingdomware Technologies, Inc., of Waldorf, Maryland, a service-disabled veteran-owned small business (SDVOSB) concern, requests that we recommend that it be reimbursed the costs of filing and pursuing its protest challenging the Department of Veterans Affairs’ (VA) issuance of a purchase order (No. 679-C25041) to LiveProcess Corporation, of Verona, New Jersey, under LiveProcess’ General Services Administration Federal Supply Schedule contract.

We deny the request.

Decision

Matter of: Kingdomware Technologies--Costs

File: B-406228.2

Date: May 10, 2012

LaTonya Barton, Kingdomware Technologies, for the protester.

Natica C. Neely, Esq., and Dennis Foley, Esq., Department of Veterans Affairs, for the agency.

Jacqueline Maeder, Esq., and David A. Ashen, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Protester is not entitled to reimbursement of protest costs after agency took corrective action where protest was not clearly meritorious.

DECISION

Kingdomware Technologies, Inc., of Waldorf, Maryland, a service-disabled veteran-owned small business (SDVOSB) concern, requests that we recommend that it be reimbursed the costs of filing and pursuing its protest challenging the Department of Veterans Affairs’ (VA) issuance of a purchase order (No. 679-C25041) to LiveProcess Corporation, of Verona, New Jersey, under LiveProcess’ General Services Administration Federal Supply Schedule contract.

We deny the request.

Kingdomware challenged the issuance (on November 28, 2011) of the purchase order, arguing that the VA failed to comply with the requirements of the Veterans Benefits, Health Care, and Information Technology Act of 2006, 38 U.S.C. §§ 8127-8128 (2006) (the VA Act), and its implementing regulations to determine whether the procurement should be set aside for SDVOSB (or veteran-owned small business (VOSB)) concerns. In response, the VA filed its agency report, explaining that the VA Act did not apply to the protested purchase order because this was not a new contracting opportunity, but rather an exercise of an option under an existing 2010 purchase order issued to LiveProcess. AR at 2.

In its comments on the agency report, however, the protester asserted that information concerning the 2010 purchase order posted in the Federal Procurement Data System (FDPS) by the VA did not support VA’s position that the order included a 1-year option. Protester Comments at 2. Because the record remained unclear after receipt of the agency report and comments, GAO requested that the agency submit a copy of the 2010 solicitation and purchase order, as well as documentation demonstrating that the asserted option had been evaluated at the time of issuance of the 2010 order.

The agency informed us that while the contract specialist acted properly in exercising an option, nevertheless, because of personnel retirements, the agency was unable to locate the procurement file and it could not provide a copy of the solicitation for the 2010 order. In response, we advised the agency that because it could not provide supporting documentation, we were unable to determine whether the prior solicitation included an option for which the agency had requested and evaluated prices at the time of issuance of the 2010 order. The VA then advised us that it would take corrective action. Specifically, the agency stated that it would conduct a new procurement in accordance with the Federal Acquisition Regulation and terminate the current 2011 order for the convenience of the government. Because the actions by the VA rendered the protest academic, we dismissed the protest. (B-406228, February 28, 2012).

Kingdomware now requests that our Office recommend that the agency reimburse the protester’s costs of filing and pursuing its protest.

When a procuring agency takes corrective action in response to a protest, our Office may recommend reimbursement of protest costs, including reasonable attorneys’ fees, where, based on the circumstances of the case, we determine that the agency unduly delayed taking corrective action in the face of a clearly meritorious protest, thereby causing the protester to expend unnecessary time and resources to make further use of the protest process in order to obtain relief. Bid Protest Regulations, 4 C.F.R. § 21.8(e) (2011); AAR Aircraft Servs.--Costs, B-291670.6, May 12, 2003, 2003 CPD ¶ 100 at 6. Thus, as a prerequisite to our recommending that costs be reimbursed where a protest has been settled by corrective action, not only must the protest have been meritorious, but it also must have been clearly meritorious, i.e., not a close question. Apptis Inc.--Costs, B-402146.3, Mar. 31, 2010, 2010 CPD ¶ 123 at 4. A protest is clearly meritorious where a reasonable agency inquiry into the protester’s allegations would reveal facts showing the absence of a defensible legal position. First Fed. Corp.--Costs, B-293373.2, Apr. 21, 2004, 2004 CPD ¶ 94 at 2.

Here, we conclude that it is not appropriate to recommend that Kingdomware recover its protest costs because, even if we determined that the agency’s corrective action was not prompt, the protest was not clearly meritorious. Whether the protest was meritorious was not apparent from the record, which is why GAO requested additional information and documentation from the VA. In this regard, the record included both documents consistent with the agency’s position that the order as awarded in 2010 included an option which was exercised in 2011, and documents indicating that the original order either never included such an option or that the option had been deleted at some point. Since the ultimate resolution of this matter required substantial further development as indicated, in part, by our Office’s request for additional information, the protest, in our view, presented a close question, and therefore was not clearly meritorious. See Alaska Structures, Inc.--Costs, B-298575.4, Jan. 22, 2007, 2007 CPD ¶ 15 at 6.

Accordingly, the request is denied.

Lynn H. Gibson

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Protest Ground

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.