B-409442

Latvian Connection General Trading and Construction, LLC

Apr 25, 2014.ArmyDepartment of War
DeniedCommerciality

GAO Digest

Latvian Connection General Trading and Construction, LLC, of Kuwait City, Kuwait, protests the Department of the Army's issuance of request for quotations (RFQ) No. W912D2-14-T-0016, for 15-passenger vans, model year 2008 or later. We deny the protest.

Key Facts

Decision date
Apr 25, 2014.
Publicly released
Apr 25, 2014.
Agency
Army
Department
Department of War

Formerly the Department of Defense

Decided by
Susan A. Poling, General Counsel

Counsel

Protester
Latvian Connection General Trading and Construction, LLC
Agency
Department of the Army
GAO
Office of the General Counsel, GAO
Mary G. Curcio, David A. Ashen

Procurement

Solicitation
W912D2-14-T-0016 (RFQ)
Instrument
Contract
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision5,243 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Authorities cited

4 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Competition in Contracting Act1
Federal Acquisition Regulation3

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

2 cases this decision cites, in the order it first names them. 1 of them opens in this app; the rest are shown without a link because no published copy of them was confirmed.

Military Agency Services Pty., Ltd.B-290414Active Aero Group, Inc.B-404666

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

Latvian Connection General Trading and Construction, LLC, of Kuwait City, Kuwait, protests the Department of the Army's issuance of request for quotations (RFQ) No. W912D2-14-T-0016, for 15-passenger vans, model year 2008 or later.

We deny the protest.

Decision

Matter of: Latvian Connection General Trading and Construction, LLC

File: B-409442

Date: April 25, 2014

Keven L. Barnes, Latvian Connection General Trading and Construction, LLC, for the protester.

Capt. Evan Williams, Department of the Army, for the agency.

Mary G. Curcio, Esq., and David A. Ashen, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

1. Protest that agency improperly failed to publish notice of solicitation on Federal Business Opportunity website is denied where solicitation was for a contract action by a defense agency to be performed outside the United States and only local vendors were being solicited, as anticipated by Federal Acquisition Regulation

§ 5.202(a)(12).

2. Procuring agency conducting procurement using simplified acquisition procedures is not required to obtain full and open competition, but instead, must obtain competition to the maximum extent practicable.

DECISION

Latvian Connection General Trading and Construction, LLC, of Kuwait City, Kuwait, protests the Department of the Army’s issuance of request for quotations (RFQ) No. W912D2-14-T-0016, for 15-passenger vans, model year 2008 or later.

We deny the protest.

The RFQ, for the lease of four 15-passenger vans to move troops and equipment in the United Arab Emirates, was issued using the simplified acquisition procedures of Federal Acquisition Regulation (FAR) Part 13. The RFQ was provided to three local vendors on January 23, 2014. Under the RFQ as amended, quotations were due on January 26. On January 24, the Army provided the protester a copy of the RFQ in response to Latvian’s expression of interest earlier that day. Also on January 24, the protester filed its protest with our Office. A total of four vendors, including Latvian, responded by the January 26 due date; the protester submitted its quotation on January 26.

Latvian asserts that the agency acted improperly when it did not publicize notice of the procurement on the Federal Business Opportunity (FedBizOpps) website. We disagree. One of the specified exceptions to the general requirement to publicize procurements in FAR subpart 5.2 is for a contract action by a defense agency “to be made and performed outside the United States and its outlying areas, and only local sources will be solicited.” FAR § 5.202(a)(12); see Military Agency Services Pty., Ltd., B-290414 et al., Aug. 1, 2002, 2002 CPD ¶ 130 at 6. Given that the procurement meets the requirements of the regulatory exemption from publication, we have no basis to conclude that the agency acted improperly.

Latvian next asserts that the agency failed to conduct the procurement using full and open competition as required by the Competition in Contracting Act of 1984. However, since the agency was using simplified acquisition procedures, it was not required to use full and open competition to conduct the procurement. See 10 U.S.C. § 2304(g)(1) (2012). Instead, the agency was required to promote competition to the maximum extent practicable. 10 U.S.C. § 2304(g)(3); FAR § 13.104. Further, since the agency was using simplified acquisition procedures, and pursuant to FAR § 5.202(a)(12) was not required to publish notice on the FedBizOpps website, soliciting three sources meets the FAR’s requirements for conducting a simplified acquisition. FAR § 13.104(b).

Finally, Latvian protests that the agency did not provide sufficient time to respond to the solicitation. As noted above, the solicitation was issued on January 23, and called for vendors to submit their quotations by January 26. FAR § 13.003(h)(2) requires that for acquisitions conducted under simplified acquisition procedures the agency establish submission deadlines that afford vendors a reasonable opportunity to respond. Here, the record indicates that the agency issued a solicitation that was not complex to meet a requirement for commercial items that were, in the contracting officer’s experience, commonly available. Contracting Officer’s Statement at 2. Given these circumstances, and the fact that four vendors, including the protester, were able to respond by the due date, we have no basis to find that the agency did not allow a reasonable amount of time for vendors to respond. See Military Agency Services Pty., Ltd., supra, at 7.

Latvian also complains that the solicitation permitted vendors to submit quotations for vehicles that are 4 to 5 years old, and does not either exclude the Toyota HIACE van or require it to have a speed limiter. GAO does not consider protests that a solicitation should provide more restrictive specifications. See e.g., USA Jet Airlines, Inc.; Active Aero Group, Inc., B-404666, Apr. 1, 2011, 2011 CPD ¶ 91 at 5. In addition, Latvian’s disagreement with the agency’s assessment of its needs does not establish that the agency violated any procurement law or regulation.

The protest is denied.

Susan A. Poling

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.