WKF Friedman Enterprises, of Clayton, California, protests the terms of request for proposals (RFP) No. SPRDL1-14-R-0221, issued by the Defense Logistics Agency for track pads for the Abrams tank. WKF asserts that the solicitation the requirement for offers to be submitted on an "all or none" basis is unduly restrictive of competition. We deny the protest.

Key Facts

Decision date
Feb 23, 2015.
Publicly released
Feb 26, 2015.
Agency
Defense Logistics Agency
Department
Department of War

Formerly the Department of Defense

Decided by
Susan A. Poling, General Counsel

Counsel

Protester
Matthew Lyon
Agency
Defense Logistics Agency
Darin Morency
GAO
Office of the General Counsel, GAO
Mary G. Curcio, David A. Ashen

Procurement

Solicitation
SPRDL1-14-R-0221 (RFP)
Issued by
Defense Logistics Agency
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision4,377 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Cases cited

2 cases this decision cites, in the order it first names them. 1 of them opens in this app; the rest are shown without a link because no published copy of them was confirmed.

Nova Constructors, LLCB-410761Applied Cos.B-299675

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

WKF Friedman Enterprises, of Clayton, California, protests the terms of request for proposals (RFP) No. SPRDL1-14-R-0221, issued by the Defense Logistics Agency for track pads for the Abrams tank. WKF asserts that the solicitation the requirement for offers to be submitted on an "all or none" basis is unduly restrictive of competition.

We deny the protest.

Decision

Matter of: WKF Friedman Enterprises

File: B-410827

Date: February 23, 2015

Matthew Lyon for the protester.

Darin Morency, Esq., Defense Logistics Agency, for the agency.

Mary G. Curcio, Esq., and David A. Ashen, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Protest that requirement to submit offer on an “all or none” basis is unduly restrictive of competition is denied where approach is necessary due to the uncertainty of the agency’s requirements and protester does not demonstrate that the solicitation requirement is clearly unreasonable.

DECISION

WKF Friedman Enterprises, of Clayton, California, protests the terms of request for proposals (RFP) No. SPRDL1-14-R-0221, issued by the Defense Logistics Agency for track pads for the Abrams tank. WKF asserts that the solicitation the requirement for offers to be submitted on an “all or none” basis is unduly restrictive of competition.

We deny the protest.

The solicitation requested offers for 74,274 track pads with an option to purchase 74,274 additional units. RFP at 5, 8. The solicitation required offerors to submit proposals on an “all or none” basis. Id. at 3. WKF, which submitted an offer for 28,040 track pads, protests that the requirement to propose on an “all or none” basis is unduly restrictive of competition.

In preparing a solicitation, a contracting agency is generally required to specify its needs and solicit offers in a manner designed to achieve full and open competition, so that all responsible sources are permitted to compete. 10 U.S.C. §§ 2304(a)(1), 2305(a)(1)(A). A solicitation may include restrictive provisions or conditions only to the extent necessary to satisfy the agency's needs or as authorized by law. 10 U.S.C. § 2305(a)(1)(B)(ii). To the extent that a protester challenges a specification as unduly restrictive, that is, it challenges both the restrictive nature of the requirement as well as the agency's need for the restriction, the procuring agency has the responsibility of establishing that the specification is reasonably necessary to meet its needs. Nova Constructors, LLC, B-410761, Jan. 21, 2015, 2015 CPD ¶ 51 at 3. Once the agency establishes support for the provision, the burden shifts to the protester to show that the requirement is clearly unreasonable. J. Squared Inc., d/b/a Univ. Loft Co., B‑408388, Aug. 27, 2013, 2013 CPD ¶ 201 at 5; Outdoor Venture Corp; Applied Cos., B-299675, B‑299676, July 19, 2007, 2007 CPD ¶ 138 at 5.

Here, DLA explains that its requirement for track pads for the Abrams tank is uncertain. The agency notes in this regard that the track pads that are being purchased support multiple programs, including requirements for the Anniston Army Depot, various Marine Corps programs, and foreign military sales. There is also inherent uncertainty in the mission requirements for the Abrams tank. The agency maintains that, given the uncertainty and volatility in demand for the track pads, it needs a single source of supply with a 100% option quantity to ensure that any mission requirements are satisfied. Supplemental Agency Report at 1.

While WKF disagrees with the agency’s position, the protester has not demonstrated that it is unreasonable for the agency to choose to procure the entire quantity from one source in order to deal with the uncertainty in its requirements. WKF would like the agency to make multiple awards, instead of procuring the track pads on an all or none basis. Specifically, of the 74,272 track pads currently required, WKF would like to provide 28,040 because this is the number it has available. In our view, however, the statutory mandate to conduct procurements on the basis of full and open competition does not require agencies to modify their mission-related needs to accommodate the limited capabilities of a particular offeror.

The protest is denied.

Susan A. Poling

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Protest Ground

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.