B-417506.2B-417506.3B-417506.4B-417506.5B-417506.6B-417506.7B-417506.8B-417506.9B-417506.11

AECOM Management Services, Inc.; Fluor Intercontinental, Inc.; PAE-Parsons Global Logistics Services, LLC

Aug 7, 2019.ArmyDepartment of War
DismissedTechnical EvaluationBest-Value TradeoffSmall Business

GAO Digest

AECOM Management Services, Inc., of Germantown, Maryland, protests the award of contracts (and the issuance of task orders) in connection with the logistics civil augmentation program (LOGCAP) to Kellogg, Brown & Root Services, Inc. (KBR), of Houston, Texas; Vectrus Systems Corporation, of Colorado Springs, Colorado; Fluor Intercontinental, Inc., of Greenville, South Carolina, and PAE-Parsons Global Logistics Services (P2GLS), of Arlington, Virginia, under request for proposals (RFP) No. W52P1J-16-R-0001, which was issued by the Department of the Army, for support services for U.S. Military installations worldwide. Additionally, Fluor and P2GLS, both of which received LOGCAP contracts, protest the Army's decision to issue task orders to KBR and Vectrus in support of U.S. military installations in the African Command (AFRICOM), European Command (EUCOM), Central Command (CENTCOM), Pacific Command (PACOM), and Afghanistan. All three protesters primarily challenge the agency's evaluation of proposals, and resulting selection decisions. We dismiss the protests because the subject matter of the protests is currently pending before a court of competent jurisdiction.

Key Facts

Decision date
Aug 7, 2019.
Publicly released
Aug 8, 2019.
Agency
Army
Department
Department of War

Formerly the Department of Defense

Decided by
Thomas H. Armstrong, General Counsel

Counsel

Protester (AECOM Management Services, Inc)
Rogers Joseph O’Donnell, PC
Jeffery M. Chiow, Neil H. O’Donnell, Lucas T. Hanback, Emily A. Wieser, Cassidy Kim
Protester (Fluor Intercontinental, Inc)
Wilmer Cutler Pickering Hale and Dorr LLP
Andrew E. Shipley, Stephen W. Preston, Philip E. Beshara, Souvik Saha, Matthew F. Ferraro, Elizabeth J. D’Aunno, Chanda L. Brown
Protester (Fluor Intercontinental, Inc)
Hughes Law PLC
James A. Hughes
Protester (PAE-Parsons Global Logistics Services, LLC)
Crowell & Moring LLP
Anuj Vohra, Christian N. Curran, Olivia L. Lynch, Zachary H. Schroeder, Lauren H. Williams, James G. Peyster
Intervenor (Kellogg, Brown & Root Services, Inc)
Perkins Coie, LLP
Lee P. Curtis, Seth H. Locke, David E. Fletcher, Eric A. Aaserud, Alexander O. Canizares, Julia M. Fox, Brenna D. Duncan
Intervenor (Vectrus Systems Corporation)
Morrison & Foerster LLP
Kevin P. Mullen, J. Alex Ward, James A. Tucker, Sandeep N. Nandivada, R. Locke Bell, Lauren J. Horneffer, Caitlin A. Crujido
Intervenor (Fluor Intercontinental, Inc)
Wilmer Cutler Pickering Hale and Dorr, LLP
Andrew Shipley, Stephen W. Preston, Philip E. Beshara, Souvik Saha, Matthew F. Ferraro, Elizabeth J. D’Aunno, Chanda L. Brown
Intervenor (PAE-Parsons Global Logistics Services, LLC)
Crowell & Moring LLP
Anuj Vohra, Christian N. Curran, Olivia L. Lynch, Zachary H. Schroeder, Lauren H. Williams
Agency
Department of the Army
Wade L. Brown, Matthew R. Wilson, Jonathan A. Hardage, Debra J. Talley, Scott A. Johnson, Alex M. Cahill
GAO
Office of the General Counsel, GAO
Scott H. Riback, Evan D. Wesser, Tania Calhoun, Edward Goldstein
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: the grounded legal brief, semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Grounded AI Case Analysis

A verified legal brief: the holding, each protest ground with its determination, key amounts, cited authorities and practitioner takeaways, every quote checked against the decision text.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision14,752 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

GAO Bid Protest Regulations1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

3 cases this decision cites, in the order it first names them. 2 of them open in this app; the rest are shown without a link because no published copy of them was confirmed.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

AECOM Management Services, Inc., of Germantown, Maryland, protests the award of contracts (and the issuance of task orders) in connection with the logistics civil augmentation program (LOGCAP) to Kellogg, Brown & Root Services, Inc. (KBR), of Houston, Texas; Vectrus Systems Corporation, of Colorado Springs, Colorado; Fluor Intercontinental, Inc., of Greenville, South Carolina, and PAE-Parsons Global Logistics Services (P2GLS), of Arlington, Virginia, under request for proposals (RFP) No. W52P1J-16-R-0001, which was issued by the Department of the Army, for support services for U.S. Military installations worldwide. Additionally, Fluor and P2GLS, both of which received LOGCAP contracts, protest the Army's decision to issue task orders to KBR and Vectrus in support of U.S. military installations in the African Command (AFRICOM), European Command (EUCOM), Central Command (CENTCOM), Pacific Command (PACOM), and Afghanistan. All three protesters primarily challenge the agency's evaluation of proposals, and resulting selection decisions.

Decision

Matter of: AECOM Management Services, Inc.; Fluor Intercontinental, Inc.; PAE‑Parsons Global Logistics Services, LLC

File: B-417506.2; B-417506.3; B-417506.4; B-417506.5; B-417506.6; B‑417506.7; B-417506.8; B-417506.9; B-417506.11

Date: August 7, 2019

Jeffery M. Chiow, Esq., Neil H. O’Donnell, Esq., Lucas T. Hanback, Esq., Emily A. Wieser, Esq., and Cassidy Kim, Esq., Rogers Joseph O’Donnell, PC, for AECOM Management Services, Inc.; Andrew E. Shipley, Esq., Stephen W. Preston, Esq., Philip E. Beshara, Esq., Souvik Saha, Esq., Matthew F. Ferraro, Esq., Elizabeth J. D’Aunno, Esq., and Chanda L. Brown, Esq., Wilmer Cutler Pickering Hale and Dorr LLP, and James A. Hughes, Esq., Hughes Law PLC, for Fluor Intercontinental, Inc.; Anuj Vohra, Esq., Christian N. Curran, Esq., Olivia L. Lynch, Esq., Zachary H. Schroeder, Esq., Lauren H. Williams, Esq., and James G. Peyster, Esq., Crowell & Moring LLP, for PAE-Parsons Global Logistics Services, LLC, the protesters.

Lee P. Curtis, Esq., Seth H. Locke, Esq., David E. Fletcher, Esq., Eric A. Aaserud, Esq., Alexander O. Canizares, Esq., Julia M. Fox, Esq., and Brenna D. Duncan, Esq., Perkins Coie, LLP, for Kellogg, Brown & Root Services, Inc.; Kevin P. Mullen, Esq., J. Alex Ward, Esq., James A. Tucker, Esq., Sandeep N. Nandivada, Esq., R. Locke Bell, Esq., Lauren J. Horneffer, Esq., and Caitlin A. Crujido, Esq., Morrison & Foerster LLP, for Vectrus Systems Corporation; Andrew Shipley, Esq., Stephen W. Preston, Esq., Philip E. Beshara, Esq., Souvik Saha, Esq., Matthew F. Ferraro, Esq., Elizabeth J. D’Aunno, Esq., and Chanda L. Brown, Esq., Wilmer Cutler Pickering Hale and Dorr, LLP, for Fluor Intercontinental, Inc.; and Anuj Vohra, Esq., Christian N. Curran, Esq., Olivia L. Lynch, Esq., Zachary H. Schroeder, Esq., and Lauren H. Williams, Esq., Crowell & Moring LLP, for PAE-Parsons Global Logistics Services, LLC, the intervenors.

Wade L. Brown, Esq., Matthew R. Wilson, Esq., Jonathan A. Hardage, Esq., Debra J. Talley, Esq., Scott A. Johnson, Esq., and Alex M. Cahill, Esq., Department of the Army, for the agency.

Scott H. Riback, Esq., Evan D. Wesser, Esq., and Tania Calhoun, Esq., and Edward Goldstein, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Protests are dismissed where the matter involved is the subject of litigation before a court of competent jurisdiction.

DECISION

AECOM Management Services, Inc., of Germantown, Maryland, protests the award of contracts (and the issuance of task orders) in connection with the logistics civil augmentation program (LOGCAP) to Kellogg, Brown & Root Services, Inc. (KBR), of Houston, Texas; Vectrus Systems Corporation, of Colorado Springs, Colorado; Fluor Intercontinental, Inc., of Greenville, South Carolina, and PAE-Parsons Global Logistics Services (P2GLS), of Arlington, Virginia, under request for proposals (RFP) No. W52P1J-16-R-0001, which was issued by the Department of the Army, for support services for U.S. Military installations worldwide. Additionally, Fluor and P2GLS, both of which received LOGCAP contracts, protest the Army’s decision to issue task orders to KBR and Vectrus in support of U.S. military installations in the African Command (AFRICOM), European Command (EUCOM), Central Command (CENTCOM), Pacific Command (PACOM), and Afghanistan. All three protesters primarily challenge the agency’s evaluation of proposals, and resulting selection decisions.

URS Federal Services, Inc. submitted the original proposal in this acquisition, but during the competition, it changed its name to AECOM Management Services, Inc.

We dismiss the protests because the subject matter of the protests is currently pending before a court of competent jurisdiction.

BACKGROUND

LOGCAP fulfills the Department of the Army’s requirements to provide global logistical support capabilities through the Army Sustainment Command to Geographical Combatant Commands (GCCs) and Army Service Component Commands (ASCCs) so that military units can carry out critical missions without having to focus on base operation activities. LOGCAP establishes contracted solutions and capabilities, incorporating an extensive portfolio of services, such as: “Setting the Theater”; supply operations; transportation services; engineering services; base camp services; and other logistics and sustainment support services. These services are detailed in more than 200 work breakdown structure (WBS) references in the Performance Work Statement (PWS), including: minor construction; food services; laundry; morale, welfare and recreation services; billeting; and facility management. See Agency Report (AR), Tab 120-1, Source Selection Plan, at 5.

The RFP, which was issued on November 20, 2017, and subsequently amended 11 times, sought proposals for the award of multiple indefinite-delivery, indefinite-quantity (IDIQ) contracts for the Army’s fifth generation LOGCAP, LOGCAP V. The RFP contemplated the award of between four and six IDIQ contracts, with each contract having an initial five-year ordering period and five, 1-year optional ordering periods. RFP at 2. Task orders can be awarded using fixed-price, cost-reimbursable, or labor-hour type contract line item numbers. Id. at 3. The cumulative maximum anticipated dollar amount for all of the IDIQ contracts is $82 billion. Id.

References herein to the RFP and its associated attachments are to the version produced by the Army that is conformed through RFP amendment No. 11.

In addition to the award of the IDIQ contracts, the RFP also contemplated the issuance of the first seven task orders in support of U.S. military operations in: Northern Command (NORTHCOM); Southern Command (SOUTHCOM); EUCOM; AFRICOM; CENTCOM; PACOM; and Afghanistan. Id. at 115-116.

The regions were divided into 3 operational groups. Operational group 1 included EUCOM and PACOM; an offeror was eligible to receive only one task order award in operational group 1. RFP at 115-116. Operational group 2 included CENTCOM, NORTHCOM, AFRICOM, and SOUTHCOM; an offeror was eligible to receive only one task order award in operational group 2. Id. at 116. Operational group 3 included only Afghanistan; all offerors that were selected for an operational group 1 or 2 award, with the exception of the CENTCOM awardee, were eligible for award of the Afghanistan task order. Id.

Offerors were required to submit only one proposal encompassing all six GCCs/ASCCs and Afghanistan. RFP at 101. Award of the IDIQ contracts and issuance of the corresponding seven initial task orders was to be made on a best-value tradeoff basis, considering the following four factors, which are listed in descending order of importance: (1) technical/management; (2) past performance; (3) small business participation; and (4) cost/price. Id. at 114-115. With respect to the technical/ management factor, the Army was to assign a separate adjectival rating for each GCC/ASCC. Id. at 115. With respect to the past performance and small business participation factors, the agency was to assign one overall adjectival rating for each factor. Id. With respect to cost/price, the Army was to determine a separate total evaluated cost/price for each GCC/ASCC and Afghanistan. Id.

The RFP specified that the Army would make seven best-value decisions and “all awards would be made concurrently.” Id. For example, with respect to EUCOM, the RFP provided that the Army would “make an award (Basic IDIQ and associated Task Order(s)).” Id. Thus, the selection decision for each GCC/ASCC and Afghanistan would be for both the base LOGCAP V IDIQ contract and the associated task order for the specific GCC/ASCC and Afghanistan. If an offeror’s proposal was not selected for any GCC/ASCC or Afghanistan, it would not receive an IDIQ contract.

The Army received six proposals in response to the RFP from DynCorp International LLC, AECOM, Fluor, P2GLS, KBR, and Vectrus. On April 9, the Army issued its source selection decision memorializing the seven best‑value decisions contemplated by the RFP. Specifically, the Army determined that the following proposals offered the best value to the government:

GCC/ASCCAwardeeTotal Evaluated Cost/Price
Operational Group 1
EUCOMKBR$183,304,832
PACOMVectrus$349,187,574
Operational Group 2
CENTCOMVectrus$1,033,852,367
NORTHCOMKBR$393,988,698
AFRICOMFluor$137,222,538
SOUTHCOMP2GLS$34,596,500
Operational Group 3
AfghanistanKBR$1,372,043,985

AR, Tab 123, Source Selection Decision, at 7, 12, 15, 18, 19, 22, 23.

As a result of the selection decisions, KBR, Vectrus, Fluor, and P2GLS simultaneously received both LOGCAP V IDIQ contracts and the associated task orders. In contrast, because DynCorp and AECOM were not found to offer the government the best value in any GCC/ASCC or Afghanistan, neither offeror received an IDIQ contract.

On April 22, DynCorp filed a protest with our Office challenging the agency’s award of the contracts and issuance of the task orders. DynCorp primarily challenged the agency’s evaluation of proposals, and the resulting best-value decisions. On May 1, AECOM also filed a protest with our Office challenging the agency’s award of the contracts and issuance of the task orders. AECOM similarly challenged the agency’s evaluation of proposals, and the resulting best-value decisions. Also on May 1, Fluor and P2GLS, both of which had been awarded IDIQ contracts and the associated task orders for AFRICOM and SOUTHCOM, respectively challenged discrete GCC/ASCC task order award decisions. Specifically, Fluor challenged the agency’s decisions with respect to EUCOM, PACOM, CENTCOM, and Afghanistan, while P2GLS challenged the PACOM and AFRICOM decisions. Our Office separately developed each protest.

On July 31, our Office issued a decision denying DynCorp’s protest, DynCorp Int’l, LLC, B-417506, B-417506.10, July 31, 2019, 2019 CPD ¶ __. Subsequent to our decision, DynCorp notified our Office on August 5 that it filed a protest with respect to the LOGCAP V procurement with the United States Court of Federal Claims.

DISCUSSION

Our Bid Protest Regulations provide that we will not decide a protest where the matter involved is the subject of litigation before a court of competent jurisdiction. 4 C.F.R. § 21.11(b). Even where the issues before the court are not the same as those raised in our Office by a protester, or are brought by a party other than the protester, we will not consider the protest if the court’s disposition of the matter would render a decision by our Office academic. Consolidated Serv. Grp., Inc., et al., B-416443.3 et al., Nov. 19, 2018, 2018 CPD ¶ 393 at 4-5; Schuerman Dev. Co., B-238464.3, Oct 3, 1991, 91‑2 CPD ¶ 286 at 2-3. Here, the matter involved in the protests is currently before a court of competent jurisdiction.

Specifically, DynCorp is challenging before the Court of Federal Claims its non-award of a LOGCAP V IDIQ contract (and the resulting task order awards) in any of the GCCs/ASCCs or Afghanistan. AECOM’s protest currently pending before our Office similarly challenges its non-award of a LOGCAP V IDIQ contract (and the associated task orders) in any of the GCCs/ASCCs or Afghanistan. Additionally, although Fluor and P2GLS were awarded IDIQ contracts (and the associated task orders for AFRICOM and SOUTCHOM, respectively), they nevertheless challenge the agency’s decisions with respect to the issuance of other specific GCC/ASCC task orders. The unique circumstances of this procurement, however, inextricably intertwined the agency’s contract award and task order issuance decisions.

In this regard, the RFP sought proposals for the award of between four and six LOGCAP V IDIQ contracts. RFP at 2. The RFP also contemplated the simultaneous issuance of the first seven task orders. Id. at 115-116. To this end, the RFP required offerors to submit only one proposal encompassing all GCCs/ASCCs and Afghanistan that would be covered by the seven initial task orders, and specifically provided that the agency would conduct seven best-value decisions and make all awards “concurrently.” Id. at 101, 115. Furthermore, the RFP provided that the selection decision for each GCC/ASCC and Afghanistan would be for both the underlying IDIQ contract, as well as the associated task orders. Id. at 115. Additionally, the Army issued one source selection decision encompassing all contract and task order awards. Agency Report, Tab 123, Source Selection Decision.

Therefore, the court’s resolution of DynCorp’s protest challenging the agency’s evaluation of proposals and resulting award decisions could render a decision by our Office on AECOM’s, Fluor’s, and P2GLS’ similar challenges academic. See, e.g., Robinson Enters.--Request for Recon., B‑238594.2, Apr. 19, 1990, 90-1 CPD ¶ 402 at 2 (affirming dismissal of a protest challenging the protester’s exclusion from the competitive range where a second disappointed offeror filed a protest in court challenging the agency’s evaluation of proposals because the potential relief our Office could grant in the dismissed protest, i.e., reevaluation of proposals, was virtually identical to the remedies that could be granted by the court in the second protest); Snowblast-Sicard, Inc., B‑230983.2, Aug. 30, 1989, 89-2 CPD ¶ 190 at 2 (similarly

dismissing a protest filed before our Office when a second disappointed offeror’s protest filed before a court requested the same remedy of re-solicitation of the requirements).

The protests are dismissed.

Thomas H. Armstrong

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Protest Ground

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.