B-418798.3

PNS Holdings, LLC- Costs

Oct 1, 2020.Defense Logistics AgencyDepartment of War
DeniedCostsCorrective ActionSmall Business

A request that GAO recommend the protester recover its protest costs.

GAO Digest

PNS Holdings, LLC, a small business of Webster, New York, requests that our Office recommend it be reimbursed the costs associated with pursuing its protest under request for proposals (RFP) No. SPE1C1-20-R-0103, issued by the Department of Defense, Defense Logistics Agency (DLA), for isolation gowns. PNS argues that it prevailed in its protest because the agency took corrective action. We deny the request.

Key Facts

Decision date
Oct 1, 2020.
Publicly released
Oct 1, 2020.
Agency
Defense Logistics Agency
Department
Department of War

Formerly the Department of Defense

Decided by
Thomas H. Armstrong, General Counsel

Counsel

Protester
Pavel Sivokonev
Agency
Defense Logistics Agency
Allison C. Eck
GAO
Office of the General Counsel, GAO
Jacob M. Talcott, Jennifer D. Westfall-McGrail

Procurement

Solicitation
SPE1C1-20-R-0103 (RFP)
Issued by
Department of Defense
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision4,987 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

GAO Bid Protest Regulations1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

1 case this decision cites, in the order it first names it. 1 of them opens in this app.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

PNS Holdings, LLC, a small business of Webster, New York, requests that our Office recommend it be reimbursed the costs associated with pursuing its protest under request for proposals (RFP) No. SPE1C1-20-R-0103, issued by the Department of Defense, Defense Logistics Agency (DLA), for isolation gowns. PNS argues that it prevailed in its protest because the agency took corrective action.

Decision

Matter of: PNS Holdings, LLC- Costs

File: B-418798.3

Date: October 1, 2020

Pavel Sivokonev for the protester.

Allison C. Eck, Esq., Defense Logistics Agency, for the agency.

Jacob M. Talcott, Esq., and Jennifer D. Westfall-McGrail, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Request for recommendation that protest costs be reimbursed is denied where the record does not establish that the agency unduly delayed taking corrective action in the face of a clearly meritorious protest.

DECISION

PNS Holdings, LLC, a small business of Webster, New York, requests that our Office recommend it be reimbursed the costs associated with pursuing its protest under request for proposals (RFP) No. SPE1C1-20-R-0103, issued by the Department of Defense, Defense Logistics Agency (DLA), for isolation gowns. PNS argues that it prevailed in its protest because the agency took corrective action.

We deny the request.

BACKGROUND

On May 20, 2020, DLA posted the RFP on beta.Sam.gov. Resp. to Req. for Costs, exh. 2 at 1. The closing date for the RFP, as listed on beta.Sam.gov, was May 28 at 10:00 p.m. Eastern Daylight Savings Time (EDT). Id. The RFP, however, listed two different closing times. Page one of the RFP provided that proposals were due by May 28 at 10:00 p.m. local time; page four of the RFP provided that proposals were due by May 28 at 10:00 p.m. Eastern Standard Time (EST). Resp. to Req. for Costs, exh. 1, RFP at 1, 4. Following the posting of the RFP on beta.Sam.gov, the agency issued six amendments. Resp. to Req. for Costs at 1. As relevant here, amendment 0004 extended the due date from May 28 at 10:00 p.m. EST to June 1 at 10:00 p.m. EST. Resp. to Req. for Costs, exh. 4, amend. 0004 at 3.

In this context, local time refers to EDT. Resp. to Req. for Costs at 2.

Although amendment 0004 identified the solicitation closing date as 10:00 p.m. EST, the listing on beta.Sam.gov identified the due date for offers as 10:00 p.m. EDT. Resp. to Req. for Costs, exh. 3 at 12.

PNS submitted its proposal at 10:22 p.m. EDT on June 1. Resp. to Req. for Costs, exh. 5, Protest at 1. Upon learning its proposal submission was untimely, PNS filed a protest with our Office on June 2, contending that beta.Sam.gov provided that the closing time was 10:00 p.m. Central Daylight Savings Time (CDT). Id. On June 17, prior to the due date for the agency report, DLA informed our Office that it intended to take corrective action. Resp. to Req. for Costs at 2. Specifically, DLA stated that it would accept PNS’s proposal as timely. Id. Our Office dismissed the protest as academic on June 22. On June 26, PNS filed a request for a recommendation for the reimbursement of costs with our Office. Req. for Costs at 1.

DISCUSSION

PNS argues that reimbursement of its protest costs is warranted here because the agency took corrective action, which according to PNS, indicates that PNS prevailed in its protest. For the reasons discussed below, we deny the request.

When an agency takes corrective action in response to a protest, we may recommend the agency reimburse the protester its protest costs if, under the circumstances, we determine the agency unduly delayed taking corrective action in the face of a clearly meritorious protest. 4 C.F.R. § 21.8(e); Information Ventures, Inc.‑Costs, B‑294580.2 et al., Dec. 6, 2004, 2004 CPD ¶ 244 at 2-3. In other words, to prevail in its request, the protester must show (1) the agency unduly delayed taking corrective action, and (2) its protest was not only meritorious, but clearly meritorious. Triple Canopy, Inc.‑Costs,B‑310566.9, B‑400437.4, Mar. 25, 2009, 2009 CPD ¶ 62 at 3.

Here, the record does not indicate that agency unduly delayed taking corrective action in the face of a clearly meritorious protest. As stated above, the agency took corrective action on June 17, which was prior to the due date for the agency report, and only 15 days after the protest was filed. Resp. to Req. for Costs at 2. Our Office generally views an agency’s action as prompt, that is, the agency did not unduly delay taking corrective action, when the corrective action is taken prior to the due date and time for submission of the agency report. LGS Innovations LLC, B-405932.3, Apr. 26, 2012, 2012 CPD ¶ 147 at 2. Because DLA took corrective action prior to that due date, there was no undue delay.

The request for a recommendation for the reimbursement of costs is denied.

Thomas H. Armstrong

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Protest Ground

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.