B-420604

EBS Supply, Inc.

Jun 2, 2022.U.S. Marine CorpsDepartment of War
DeniedTechnical EvaluationSmall Business

GAO Digest

EBS Supply, Inc., a small business of San Diego, California, protests the award of a contract to Railroad Cleaners d/b/a RRC Commercial, a small business of Pittsburg, California, under request for quotations (RFQ) No. M0068122Q0004, issued by the United States Marine Corps (USMC) for protective equipment leasing and laundering services. The protester contends that the agency unreasonably evaluated its quotation as technically unacceptable. We deny the protest.

Key Facts

Decision date
Jun 2, 2022.
Publicly released
Jun 3, 2022.
Agency
U.S. Marine Corps
Department
Department of War

Formerly the Department of Defense

Decided by
Edda Emmanuelli Perez, General Counsel

Counsel

Protester
EBS Supply, Inc
Agency
United States Marine Corps
Kristopher Cronin
GAO
Office of the General Counsel, GAO
Christine Milne, Tania Calhoun

Procurement

Awardee
Railroad Cleaners d/b/a RRC Commercial
Solicitation
M0068122Q0004 (RFQ)
Instrument
Contract
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision8,258 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

GAO Bid Protest Regulations1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

4 cases this decision cites, in the order it first names them. 4 of them open in this app.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

EBS Supply, Inc., a small business of San Diego, California, protests the award of a contract to Railroad Cleaners d/b/a RRC Commercial, a small business of Pittsburg, California, under request for quotations (RFQ) No. M0068122Q0004, issued by the United States Marine Corps (USMC) for protective equipment leasing and laundering services. The protester contends that the agency unreasonably evaluated its quotation as technically unacceptable.

Decision

Matter of: EBS Supply, Inc.

File: B-420604

Date: June 2, 2022

Gilbert West, EBS Supply, Inc., for the protester.

Kristopher Cronin, Esq., United States Marine Corps, for the agency.

Christine Milne, Esq., and Tania Calhoun, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

Digest

Protest that the agency unreasonably evaluated the protester’s quotation as technically unacceptable is denied where the record shows that the evaluation was reasonable in light of the protester’s failure to submit an adequately written quotation.

Decision

EBS Supply, Inc., a small business of San Diego, California, protests the award of a contract to Railroad Cleaners d/b/a RRC Commercial, a small business of Pittsburg, California, under request for quotations (RFQ) No. M0068122Q0004, issued by the United States Marine Corps (USMC) for protective equipment leasing and laundering services. The protester contends that the agency unreasonably evaluated its quotation as technically unacceptable.

We deny the protest.

BACKGROUND

The RFQ, issued on February 1, 2022, as a small business set-aside, contemplated the award of a fixed-price indefinite-delivery, indefinite-quantity contract to provide shop towels, coveralls, shirts, and pants leasing and laundering services for the agency’s Southwest Regional Fleet Transportation department. Agency Report (AR), Exh. 1, RFQ Performance Work Statement (PWS) ¶ 1.0. The services were to be provided over a 1-year base period and four 1-year option periods at various installations in California and Arizona. Id. Under the contract, these installations could lease clothing and shop towels (also referred to as rags) for the protection of agency personnel in their handling of hazardous materials and waste. Id. at ¶ 2.0. The PWS set forth specific requirements for the laundering, pick-up, and delivery of these items. Id. at ¶¶ 3.0, 5.0.

Award was to be made to the firm with the lowest-priced, technically acceptable quotation, considering three factors: technical capability, price, and past performance factors. RFP at 44. Under the technical capability factor, quotations would be evaluated as acceptable or unacceptable based on three subfactors, including technical approach to the PWS requirements and quality control plan. Id. at 45. As to the technical approach subfactor, vendors were advised that their written technical approaches were required to clearly describe how they will accomplish “all the requirements in the PWS,” including those in paragraph 3.0. Id. As to the quality control plan subfactor, vendors’ plans were to demonstrate the ability to manage and control all of the PWS objectives, including those in the performance requirements summary in paragraph 5.0. Id.

Section 5 of the PWS includes a table that lists PWS requirements that correspond to standards that must be met to satisfy the requirements, the type of inspection to be performed to verify compliance, and the incentive to meet the standard.

Among other things, the PWS required with respect to clothing that “[o]ff-the-shelf” sizes must be delivered within five days for new task orders, PWS ¶ 3.2.8, and that, after laundering, finished items must be hung on individual hangers and each employee’s clothing must be grouped separately and hangers bound together by a wire tie or rubber band. PWS ¶ 3.2.9. With respect to shop towels, the PWS required the contractor to provide freestanding containers with lids for soiled rags as well as a separate container for clean rags, and included specific requirements for the laundering, pick-up, and delivery of shop towels. Id. at ¶¶ 3.3.3, 3.3.4, 3.3.5, 5.

The agency received four quotations by the submission due date, including those from EBS, the incumbent contractor, and RRC. Contracting Officer’s Statement (COS) at 6. EBS’s quotation was found technically unacceptable for failing to meet the requirements under the technical approach and quality control plan subfactors. AR, Exh. 4, Award Decision at 2-3. Under the technical approach subfactor, the agency noted that EBS failed to describe how it would meet the PWS requirements regarding the five-day delivery of “off-the-shelf” sizes of clothing, and regarding the provision of fireproof bins for shop towels. Id. Under the quality control plan subfactor, the agency noted that EBS’s quotation did not provide that it would bind clothing together by a wire tie or rubber band, or state that it would provide shop towel services as required by the PWS. Id. The agency ultimately found RRC’s quotation technically acceptable and made award to RRC for $1,441,140.24. COS at 8. This protest followed.

DISCUSSION

EBS posits two reasons for arguing that the agency unreasonably evaluated its quotation as technically unacceptable. The firm first contends that, although its quotation does not state how it would meet several PWS requirements, it still meets them because it states generally that all requirements will be met. The firm next contends that its technical approach must be technically acceptable because it is the incumbent contractor. Protest at 1. We do not agree.

To the extent that EBS argues that the requirements it failed to meet do not require a technical approach (Comments at 3), this argument constitutes an untimely challenge to the terms of the solicitation, as the RFQ provided that a quotation must “clearly [describe] how the quoter will accomplish all the requirements in the PWS, to include PWS Sections 3.0” to satisfy the technical approach factor. RFQ at 45; 4 C.F.R. § 21.2(a)(1); Westar Aerospace & Defense Group, Inc., B-408285, B-408285.2, Aug. 9, 2013, 2013 CPD ¶ 212 at 4 n.3.

An offeror has the burden of submitting an adequately written quotation, and it runs the risk that its quotation will be evaluated unfavorably when it fails to do so. George T. Brown Associates, Inc., B-404398, Jan. 26, 2011, 2011 CPD ¶ 28 at 3. We have reviewed EBS’s quotation and find no basis to disagree with the agency’s evaluation. The quotation does not, in fact, describe how it will meet all the requirements of the PWS as required by the solicitation. EBS’s quotation does not describe how it will meet the requirements that “off-the-shelf” sizes be delivered in five days and that clothing on hangers be bound together, and does not reference shop towels at all, let alone describe an approach for providing fireproof bins or pick-up and delivery services for shop towels. See AR, Exh. 9, EBS Quotation.

EBS argues that the statement in its quotation that “[g]arments are then ordered or provided from existing product inventory” (AR, Exh. 9, EBS Quotation at 8) addresses the requirement to deliver off-the-shelf sizes in five days, but this statement contains no indication that this specific requirement will be met. EBS also argues that the statement in its quotation that “[a]ll garments will be professionally laundered, consistent with the requirements and standards of the industrial laundry industry, and consistent with the stated requirements of the PWS” (AR, Exh. 9, EBS Quotation at 8) demonstrates its commitment to meet all requirements but, again, this vague assertion does not establish how EBS will meet the specific PWS requirements referenced in the evaluation. EBS bore the risk that, by not stating how it would meet each of the requirements, the agency would evaluate its quotation as technically unacceptable. Liberty Test Equipment, B-409916, Aug. 25, 2014, 2014 CPD ¶ 246 at 3. Finally, EBS’s status as the incumbent is not a substitute for including required information in its quotation. MSN Services LLC, B-414900 et al., Oct. 4, 2017, 2017 CPD ¶ 310 at 4.

The protest is denied.

Edda Emmanuelli Perez

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Protest Ground

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.