57316

CCI, Inc.

March 14, 2014Judge Scott
Denied / Government PrevailedDiffering Site Conditions

CCI, Inc. appealed the denial of its differing site conditions claim under Contract No. W917BK-08-C-0059, which the Board ultimately denied.

Material Facts

  • CCI, Inc. submitted a claim for differing site conditions under its contract with the U.S. Army Corps of Engineers.
  • The contract was for a pier and seawall project in Iraq.
  • The Board held a 15-day hearing to address entitlement and quantum.
  • The CO denied CCI's claim, stating that the conditions were known or should have been known to an experienced marine contractor.
  • The Board found that CCI did not conduct adequate pre-proposal investigations or site visits.

Parties

Appellant
CCI, Inc.
Respondent Agency
U.S. Army Corps of Engineers
Contract Number
W917BK-08-C-0059
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.