Areyana Group of Construction Company appealed a contracting officer's final decision denying their request for a no-cost time extension and additional costs related to a groundwater storage tank. The Board dismissed the appeal due to lack of jurisdiction.

Material Facts

  • The government entered into a fixed-price contract with AGCC in a total amount of $4,754,401.51.
  • The project involved the design and construction of facilities to support the Afghanistan National Police program.
  • AGCC requested a 221-day, no-cost time extension due to supply issues and shipping delays.
  • The contracting officer issued a cure notice to AGCC citing failures in performance.
  • AGCC submitted several requests for time extensions and claims, none of which included the required certification.
  • The contracting officer found AGCC's request for a time extension to be baseless and without merit.

Parties

Appellant
Areyana Group of Construction Company
Respondent Agency
U.S. Army Engineer District
Contract Number
W5J9LE-12-C-0044
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.