61178

Khenj Logistics Group

February 15, 2018Judge Kinner
DismissedStatute of Limitations / Timeliness

Khenj Logistics Group appealed a government decision regarding a contract termination for convenience, claiming reimbursement for costs incurred. The Board dismissed the appeal as time-barred under the Contract Disputes Act.

Material Facts

  • Khenj Logistics Group was awarded a contract on May 14, 2009, to construct a facility in Afghanistan.
  • The contract required KLG to obtain worker compensation insurance pursuant to the Defense Base Act.
  • KLG received the notice to proceed on May 27, 2009, and commenced performance on June 1, 2009.
  • The Army issued a stop-work order on June 5, 2009, and terminated the contract for convenience on June 10, 2009.
  • KLG submitted a claim to the Army Contracting Command on March 6, 2017, requesting $2,192,884 for costs incurred.

Parties

Appellant
Khenj Logistics Group
Respondent Agency
Department of the Army
Contract Number
W91B4M-09-C-7173
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.