No. 2018-2206

Hejran Hejrat Co. Ltd. v. United States Corps of Engineers

Jul 17, 2019opinionAppeal from the ASBCA
ReversedContract disputePrecedentialContractor appealed

Disposition

REVERSED AND REMANDED

Reversed. Read from the standalone disposition line the opinion closes on. The court held the decision below wrong and reversed it. The appellant prevailed.

Key Facts

Appellant
Hejran Hejrat Co. Ltd.
Appellee
United States Army Corps of Engineers
Appeal taken by
Contractor appealed

The contractor or protester lost below and brought the appeal.

Docket number
No. 2018-2206
Decided
Jul 17, 2019

From the opinion's own decided line.

Matter
Contract dispute
Panel
NEWMAN, DYK, WALLACH
Opinion by
DYK

Appealed From

The Armed Services Board of Contract Appeals, the Contract Disputes Act board for the defense agencies and NASA.

Appeal from the Armed Services Board of Contract Ap peals in No. 61234, Administrative Judge Donald Evan Kinner, Administrative Judge J. Reid Prouty, Administra tive Judge Richard Shackleford

Counsel

Also appearing
JOSEPH ALOYSIUS HENNESSEY
The Law Office of Jo- seph Hennessey, LLC
Chevy Chase, MD
For the appellee
JESSICA R. TOPLIN
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
For the appellee
JOSEPH H
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
Opinion PDF (cafc.uscourts.gov)The disposition, the side that appealed and the appearances above are read deterministically from the opinion's own words. The court's document is the source of record.

Research This Decision

Create a free account to open this decision in the Federal Circuit workspace: the filtered browser over every appeal, the outcome dashboard, and the reading that follows an appeal down to the decision under review and across the cases it cites.

Browse with Filters

Every government-contracts appeal in the corpus, filtered by the tribunal below, the disposition, precedential status and matter, with full-text search over the opinions.

Insights

Contractor relief by disposition and by the side that appealed, per tribunal below and per year, with every denominator visible beside its rate.

Cross-Corpus Reading

The Appealed-from join into the Court of Federal Claims, ASBCA and CBCA corpora, and the cited-cases panel that names every prior decision this opinion relies on.

Full Opinion

Full text of the opinion7 pages, 13,023 characters, read from the court's own documentDecided Jul 17, 2019 on the opinion's own line Decision documentOfficial source: U.S. Court of Appeals for the Federal Circuit opinions and orders
PanelNEWMAN, DYK, WALLACHOpinion byDYKPrecedentialReversed
Appealed fromArmed Services Board of Contract Ap peals61234Judge Donald Evan KinnerThe opinion states: Appeal from the Armed Services Board of Contract Ap peals in No. 61234, Administrative Judge Donald Evan Kinner, Administrative Judge J. Reid Prouty, Administra tive Judge Richard Shackleford
The opinion closes: REVERSED AND REMANDED(the standalone disposition line)

Authorities cited

4 authorities read from this opinion's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Tucker Act and the Judicial Code1
Federal Acquisition Regulation1

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

11 cases this opinion cites, grouped by the forum that decided each, in the order it first names them. 11 of them open at a publisher.

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

United States Court of Appeals

for the Federal Circuit

HEJRAN HEJRAT CO. LTD,

Appellant

v.

UNITED STATES ARMY CORPS OF ENGINEERS,

Appellee

2018-2206

Appeal from the Armed Services Board of Contract Ap-

peals in No. 61234, Administrative Judge Donald Evan

Kinner, Administrative Judge J. Reid Prouty, Administra-

tive Judge Richard Shackleford.

Decided: July 17, 2019

The case caption as the opinion prints it. Every word is kept; only a line that is nothing but a drawn rule is left out.

For the appellee
JESSICA R. TOPLIN
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
As the opinion writes it

JESSICA R. TOPLIN, Commercial Litigation Branch, Civil Division, United States Department of Justice, Wash- ington, DC, argued for appellee. Also represented by JOSEPH H. HUNT, ROBERT EDWARD KIRSCHMAN, J R., PATRICIA M. MC CARTHY.

JOSEPH H
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
As the opinion writes it

Also represented by JOSEPH H.

Other appearances
JOSEPH ALOYSIUS HENNESSEY
The Law Office of Jo- seph Hennessey, LLC
Chevy Chase, MD
As the opinion writes it

JOSEPH ALOYSIUS HENNESSEY, The Law Office of Jo- seph Hennessey, LLC, Chevy Chase, MD, argued for appel- lant.

J OSEPH ALOYSIUS HENNESSEY , The Law Office of Joseph Hennessey, LLC, Chevy Chase, MD, argued for appellant.

J ESSICA R. T OPLIN, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for appellee. Also represented by J OSEPH H. HUNT , ROBERT E DWARD K IRSCHMAN, J R., P ATRICIA M. MC CARTHY .

Before NEWMAN, DYK, and WALLACH, Circuit Judges.

DYK, Circuit Judge.

Hejran Hejrat Co. Ltd. (“HHL”) appeals from a decision by the Armed Services Board of Contract Appeals (“Board”) dismissing HHL’s case for lack of jurisdiction. Because we conclude that there was a request for a final decision by a contracting officer and a final decision entered by the contracting officer, we reverse and remand for further proceedings.

BACKGROUND

This appeal arises from HHL’s 2011 contract with the United States Army Corps of Engineers (“USACE”) to provide transportation services in Afghanistan. After the contract expired, HHL requested additional compensation from the USACE based on alleged violations of the contract: suspension of work, changes to the contract requirements, and termination of the original contract. After various preliminary submissions, on March 5, 2015, HHL submitted a document entitled “Request for Equitable Adjustment (REA)” with a sworn statement by HHL’s Deputy Managing Director having “full management [authority] to . . . close out . . . the contract.” J.A. 70. In that submission, HHL requested that the submission be “treated as a[n] REA,” J.A. 74, and requested $4,137,964 in compensation. The contracting officer denied HHL’s request on March 26, 2017, in what the contracting officer characterized as the “Government’s final determination in this matter.” J.A. 116. HHL appealed the decision, but the Board concluded that it did not have jurisdiction because “[a]t no point, in six years of communication with the [USACE], has HHL requested a contracting officer’s final decision.” J.A. 4.

HHL appealed to our court. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10). We review the Board’s

determination of its jurisdiction de novo. Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1575 (Fed. Cir. 1995) (en banc).

DISCUSSION

In order for the Board to have jurisdiction, there must be a final decision by a contracting officer on a claim. Parsons Glob. Servs. v. McHugh, 677 F.3d 1166, 1170 (Fed. Cir. 2012) (citing 41 U.S.C. § 7103). The issue on appeal is whether HHL requested a contracting officer’s final decision on a claim, such that the officer’s denial constituted a final decision that supported the Board’s jurisdiction. The statute provides that “[e]ach claim by a contractor against the Federal Government relating to a contract shall be submitted to the contracting officer for a decision.” 41 U.S.C. § 7103(a)(1). Thus, in order to constitute a claim a contractor must request a final decision by a contracting officer. M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323, 1327 (Fed. Cir. 2010) (citing James M. Ellet Const. Co., v. United States, 93 F.3d 1537, 1543 (Fed. Cir. 1996)) (“The CDA . . . requires that a claim indicate to the contracting officer that the contractor is requesting a final decision.”).

“[W]e evaluate whether a particular request for payment amounts to a claim based on the [Federal Acquisition Regulations (FARs),] . . . the language of the contract in dispute, and the facts of each case.” Parsons, 677 F.3d at 1170. Under the relevant FAR, a claim is defined as “a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in sum certain.” FAR 52.233-1(c) (2002).

HHL contends that its March 5, 2015, submission constituted a claim within the meaning of the CDA. There is no dispute that HHL’s March 5 submission was under the FAR a “written demand . . . seeking, as a matter of right, the payment of money in sum certain.” Id. Indeed, the Board found that in its submissions “HHL adequately

described five grounds why it is owed more money, and the sum certain being requested for each.” J.A. 4.

On appeal the government makes three arguments as to why HHL’s submission did not constitute a request for a final decision. First, the government’s “[f]oremost” argument is that “HHL’s March 5, 2015, submission is styled as a[n] REA, not as a claim. HHL also expressly requested that the document be ‘treated as an REA.’” Gov’t Br. at 12 (internal citations omitted) (emphasis added). The government’s argument that an REA cannot constitute a claim is directly contrary to this court’s en banc decision in Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed. Cir. 1995) (en banc), and subsequent cases. Just as in the current appeal, in Reflectone “[the contractor’s] REA satisfie[d] all the requirements listed for a [Contract Disputes Act (CDA)] ‘claim’ according to the first sentence of FAR [52.233-1(c)],” and thus we “conclude[d] that the Board ha[d] jurisdiction to review the [contracting officer]’s denial of [the contractor’s] REA.” Id. at 1578.

Second, the government argues that “the [March 5] document fails to include any language requesting a final decision.” Gov’t Br. at 12. Although the government agrees that magic words are not required under our cases, the government’s position appears to be that a contractor must include particular words in its submission in order to constitute a request for a contracting officer’s final decision. This argument is also squarely inconsistent with our caselaw, which recognizes that “a CDA claim need not be submitted in any particular form or use any particular wording,” Maropakis, 609 F.3d at 1327, so long as it has “a clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim,” id. (quoting Contract Cleaning Maint., Inc. v. United States, 811 F.2d 586, 592 (Fed. Cir. 1987)); see, e.g., K-Con Bldg. Sys., Inc. v. United States, 778 F.3d 1000, 1005 (Fed. Cir. 2015); Parsons, 677 F.3d at 1170; Ellett, 93 F.3d at 1542.

See also, e.g., Tip Top Constr., Inc. v. Donahoe, 695 F.3d 1276, 1279 (Fed. Cir. 2012) (treating the contractor’s REA as a claim); Daewoo Eng’g & Constr. Co. v. United States, 557 F.3d 1332, 1334 (Fed. Cir. 2009) (treating the contractor’s REA as a claim); Propellex Corp. v. Brownlee, 342 F.3d 1335, 1337–38 (Fed. Cir. 2003) (noting the contracting officer’s denial of an REA was the relevant final decision that was appealed to the Board); Oman-Fischbach Int’l (JV) v. Pirie, 276 F.3d 1380, 1383 (Fed. Cir. 2002) (noting that the contracting officer denied the contractor’s REA, which was treated as a denied claim).

Under our caselaw, HHL’s March 5 submission constitutes a request for a final decision on a claim. In the March 5 submission, HHL requested that the contracting officer provide specific amounts of compensation for each of the alleged grounds. HHL submitted a sworn statement attesting to the truth of the submission, included detailed factual bases for its alleged losses, and claimed a sum certain based on the losses. This submission bears all of the hallmarks of a request for a final decision on a claim, and “[t]his court is loathe to believe that in this case a reasonable contractor would submit to the contracting officer a letter containing a payment request after a dispute had arisen solely for the contracting officer’s information and without at the very least an implied request that the contracting officer make a decision as to entitlement. Any other finding offends logic.” Transamerica Ins. Corp. v. United States, 973 F.2d 1572, 1578 (Fed. Cir. 1992), overruled in part by Reflectone, 60 F.3d at 1579 & n.10.

Third, the government argues that the March 5 submission is not a request for a final decision because HHL expressly stated that its submissions did not constitute a request for a final decision by the contracting officer on a claim. The government is correct that before the March 5 submission, the contractor submitted a document similar

to the March 5 submission (though unsworn) and indicated an intent to later file a certified formal claim. See, e.g., J.A. 290 (“In the event that you decide to treat this [January 31, 2014 submission] as [an] REA and still reject our request for the adjustment of payments, we would then proceed with issuing a certified claim.”); id. (“[W]e are hopeful that you treat this [January 31 submission] as [an] REA and conclude in our favor, which will in turn eliminate the possibility of proceeding with a certified claim.”). But most of those communications occurred more than a year before HHL’s March 5, 2015, submission and no similar communications followed the March 5 submission. The March 5 submission purportedly provided the certification that HHL had earlier recognized would be necessary to proceed with a claim. The March 5 submission was sworn unlike earlier submissions, and thus had a formality lacking in the earlier submissions. “[C]ertification plays a serious role in the statutory scheme because it triggers a contractor’s potential liability for a fraudulent claim . . . . [and is] designed to discourage the submission of unwarranted contractor claims and to encourage settlement.”

Skelly & Loy v. United States, 685 F.2d 414, 418 n.11 (Ct.

During a nearly year-long communication hiatus by the USACE, HHL did inquire as to the status of its submission and whether it should “submit our claim.” J.A. 86. But, as is clear from the other communications sent during that time, HHL was seeking a final decision on its submission (whether it called it a claim, an REA, or something else). See, e.g., J.A. 109 (asking that the contracting officer “[p]lease let [HHL] know if the review of the case/information is going to be completed soon and when to expect the final result” (emphasis added)). To whatever extent there was uncertainty based on those communications, the contracting officer could have asked for clarification rather than issuing a “final determination” in the matter.

Cl. 1982) (citation omitted). It is also important that the contracting officer treated the denial of HHL’s REA as a “final determination” in the matter. See Transamerica, 973 F.2d at 1578 n.2 (“The fact that the Government referred to the operative submission(s) as ‘claims’ was found persuasive . . . .” (citing Contract Cleaning, 811 F.2d at 592)). The contracting officer suggested in an email the need to file a formal claim, but this occurred after the contractor’s submission was complete and the contracting officer had issued a “final determination” in the matter. The contracting officer could not retroactively turn a qualifying claim document into something else.

HHL’s March 5 submission constituted a request for a final decision by the contracting officer, and the contracting officer’s denial of that submission was a final decision on a claim. The Board erred when it concluded that it did not have jurisdiction over HHL’s appeal.

We note that the Board found that HHL’s March 5 submission did not contain a proper certification as required for a claim of more than $100,000. FAR 52.233-1(c); 41 U.S.C. § 7103(b)(1). “A contracting officer is not obligated to render a final decision on a claim of more than $100,000 that is not certified . . . .” 41 U.S.C. § 7103(b)(3). It is unclear how the certification was inadequate, but, as the Board and the government recognize, “[a] defect in the certification of a claim does not deprive a court or an agency board of jurisdiction over the claim.” Id. “Prior to the entry of a final judgment by a court or a decision by an agency board, the court or agency board shall require a defective certification to be corrected.” Id. Here, the government concedes that HHL could cure any issues with its certification on remand. Therefore, on remand the Board may require HHL to correct any defects in the certification for the March 5 submission.

REVERSED AND REMANDED

This is a verbatim capture of the text layer of the court's own document in Hejran Hejrat Co. Ltd. v. United States Corps of Engineers. Nothing is summarized or reworded, and the sections run in the order the court wrote them. One thing the page shows is not repeated in the text: the pagination furniture, which is the page numbers, the docket footer and the electronic filing stamp printed across the top of each page.

Related Decisions

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.