No. 2019-1330

DAI Global, LLC fka Development Alternatives, Inc. v. Administrator of the United States Agency for International Development

Dec 27, 2019opinionAppeal from the CBCA
ReversedContract disputePrecedentialContractor appealed

Disposition

REVERSED AND REMANDED

Reversed. Read from the standalone disposition line the opinion closes on. The court held the decision below wrong and reversed it. The appellant prevailed.

Key Facts

Appellant
DAI Global, LLC fka Development Alternatives, Inc.
Appellee
Administrator of the United States Agency for International Development
Appeal taken by
Contractor appealed

The contractor or protester lost below and brought the appeal.

Docket number
No. 2019-1330
Decided
Dec 27, 2019

From the opinion's own decided line.

Matter
Contract dispute
Panel
MOORE, SCHALL, TARANTO
Opinion by
MOORE

Appealed From

The Civilian Board of Contract Appeals, the Contract Disputes Act board for the civilian executive agencies.

Appeal from the Civilian Board of Contract Appeals in Nos. 5942, 5943, 5944, 5945, 5946, Administrative Judge Jonathan D. Zischkau, Administrative Judge Catherine B

Counsel

For the appellant
JONATHAN DAVID SHAFFER
Smith, Pachter, McWhorter, PLC
Vienna, VA
For the appellant
ARMANI VADIEE; TODD MATTHEW GARLAND
Smith, Pachter, McWhorter, PLC
Vienna, VA
For the appellant
ZACHARY DAVID PRINCE
Smith, Pachter, McWhorter, PLC
Vienna, VA
For the appellant
Tysons Corner
Smith, Pachter, McWhorter, PLC
Vienna, VA
For the appellee
GEOFFREY MARTIN LONG
Commercial Litigation Branch, Civil Division, United States Department of Jus- tice
Washington, DC
For the appellee
JOSEPH H
Commercial Litigation Branch, Civil Division, United States Department of Jus- tice
Washington, DC
Opinion PDF (cafc.uscourts.gov)The disposition, the side that appealed and the appearances above are read deterministically from the opinion's own words. The court's document is the source of record.

Research This Decision

Create a free account to open this decision in the Federal Circuit workspace: the filtered browser over every appeal, the outcome dashboard, and the reading that follows an appeal down to the decision under review and across the cases it cites.

Browse with Filters

Every government-contracts appeal in the corpus, filtered by the tribunal below, the disposition, precedential status and matter, with full-text search over the opinions.

Insights

Contractor relief by disposition and by the side that appealed, per tribunal below and per year, with every denominator visible beside its rate.

Cross-Corpus Reading

The Appealed-from join into the Court of Federal Claims, ASBCA and CBCA corpora, and the cited-cases panel that names every prior decision this opinion relies on.

Full Opinion

Full text of the opinion8 pages, 11,866 characters, read from the court's own documentDecided Dec 27, 2019 on the opinion's own line Decision documentOfficial source: U.S. Court of Appeals for the Federal Circuit opinions and orders
PanelMOORE, SCHALL, TARANTOOpinion byMOOREPrecedentialReversed
Appealed fromCivilian Board of Contract Appeals5942, 5943, 5944, 5945, 5946Judge Jonathan D. ZischkauThe opinion states: Appeal from the Civilian Board of Contract Appeals in Nos. 5942, 5943, 5944, 5945, 5946, Administrative Judge Jonathan D. Zischkau, Administrative Judge Catherine B
The opinion closes: REVERSED AND REMANDED(the standalone disposition line)

Authorities cited

4 authorities read from this opinion's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Tucker Act and the Judicial Code1
Federal Acquisition Regulation1

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

3 cases this opinion cites, grouped by the forum that decided each, in the order it first names them. 3 of them open at a publisher.

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

United States Court of Appeals

for the Federal Circuit

DAI GLOBAL, LLC, FKA DEVELOPMENT

ALTERNATIVES, INC.,

Appellant

v.

ADMINISTRATOR OF THE UNITED STATES

AGENCY FOR INTERNATIONAL DEVELOPMENT,

Appellee

2019-1330

Appeal from the Civilian Board of Contract Appeals in

Nos. 5942, 5943, 5944, 5945, 5946, Administrative Judge

Jonathan D. Zischkau, Administrative Judge Catherine B.

Hyatt, Administrative Judge Jeri Kaylene Somers.

Decided: December 27, 2019

The case caption as the opinion prints it. Every word is kept; only a line that is nothing but a drawn rule is left out.

For the appellant
JONATHAN DAVID SHAFFER
Smith, Pachter, McWhorter, PLC
Vienna, VA
As the opinion writes it

JONATHAN DAVID SHAFFER, Smith, Pachter, McWhorter, PLC, Vienna, VA, argued for appellant. Also represented by ARMANI VADIEE; TODD MATTHEW GARLAND, ZACHARY DAVID PRINCE, Tysons Corner, VA.

ARMANI VADIEE; TODD MATTHEW GARLAND
Smith, Pachter, McWhorter, PLC
Vienna, VA
As the opinion writes it

Also represented by ARMANI VADIEE; TODD MATTHEW GARLAND.

ZACHARY DAVID PRINCE
Smith, Pachter, McWhorter, PLC
Vienna, VA
As the opinion writes it

Also represented by ZACHARY DAVID PRINCE.

Tysons Corner
Smith, Pachter, McWhorter, PLC
Vienna, VA
As the opinion writes it

Also represented by Tysons Corner.

For the appellee
GEOFFREY MARTIN LONG
Commercial Litigation Branch, Civil Division, United States Department of Jus- tice
Washington, DC
As the opinion writes it

GEOFFREY MARTIN LONG, Commercial Litigation Branch, Civil Division, United States Department of Jus- tice, Washington, DC, argued for appellee. Also represented by JOSEPH H. HUNT, ROBERT EDWARD KIRSCHMAN, J R., PATRICIA M. MCCARTHY.

JOSEPH H
Commercial Litigation Branch, Civil Division, United States Department of Jus- tice
Washington, DC
As the opinion writes it

Also represented by JOSEPH H.

J ONATHAN D AVID SHAFFER, Smith, Pachter, McWhorter, PLC, Vienna, VA, argued for appellant. Also represented by ARMANI V ADIEE ; T ODD MATTHEW G ARLAND, ZACHARY D AVID P RINCE, Tysons Corner, VA.

G EOFFREY MARTIN L ONG, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for appellee. Also

represented by J OSEPH H. HUNT , R OBERT EDWARD K IRSCHMAN, J R., P ATRICIA M. M CCARTHY .

Before MOORE, SCHALL, and TARANTO, Circuit Judges.

MOORE, Circuit Judge.

DAI Global, LLC (DAI), formerly known as Development Alternatives, Inc., appeals a decision by the Civilian Board of Contract Appeals (Board) dismissing DAI’s five appeals for lack of jurisdiction. See Developmental Alts., Inc. v. Agency for Int’l Dev., CBCA No. 5942, CBCA 5943, CBCA 5944, CBCA 5945, CBCA 5946, 18-1 BCA ¶ 37147.

Because the Board has jurisdiction to consider DAI’s appeals, we reverse and remand.

BACKGROUND

From 2006 to 2010, the United States Agency for International Development (USAID) awarded DAI five contracts for developmental services in Afghanistan. DAI subcontracted with a private security company, ERSM (Afghanistan) Limited, d/b/a Edinburgh International (EI). EI employed over 1,000 individuals to provide DAI with security services. On April 1, 2011, Afghanistan imposed a nearly $2 million fine on EI based on the size and composition of EI’s private security workforce. EI paid the fine and allocated a portion of the expense to each of DAI’s five contracts.

On May 10, 2017, DAI submitted a cover letter and EI’s five claims to USAID, seeking reimbursement for the fine. DAI’s cover letter characterized itself as a certification. Along with each claim, DAI also included EI’s certification stating that the claim was made in good faith. On July 10, 2017, USAID’s contracting officer sent DAI a letter stating that she would provide a decision on the claims by August 24, 2017. On July 19, 2017, 70 days after DAI submitted its claims, the contracting officer sent a second letter

informing DAI that the submission did not contain a contractor certification.

On November 20, 2017, DAI filed five notices of appeal with the Board. The Board dismissed DAI’s claims on September 27, 2018, for lack of jurisdiction based on DAI’s failure to certify the claims. The Board stated that DAI’s May 10, 2017 certification bears no resemblance to the required statutory language. The Board also stated that only technical errors are correctable, and that DAI made its certification with reckless disregard for the certification requirements. It concluded that nontechnical mistakes in the certification and DAI’s recklessness rendered DAI’s purported certification unsalvageable. DAI appeals. We have jurisdiction under 28 U.S.C. § 1295(a)(10).

DISCUSSION

We review a contract board’s decision on a question of law de novo. Agility Logistics Servs. Co. KSC v. Mattis, 887 F.3d 1143, 1148 (Fed. Cir. 2018). Whether a contract board has jurisdiction over an appeal is such a question. Id. A government contractor seeking payment on a government contract must submit a claim to the contracting officer. 41 U.S.C. § 7103(a)(1). When the claim is for more than $100,000, an individual authorized to bind the contractor must certify that:

(A) the claim is made in good faith; (B) the supporting data are accurate and complete to the best of the contractor’s knowledge and belief; (C) the amount requested accurately reflects the contract adjustment for which the contractor believes the Federal Government is liable; and (D) the certifier is authorized to certify the claim on behalf of the contractor.

Id. § 7103(b)(1). However, “[a] defect in the certification of a claim does not deprive a court or an agency board of jurisdiction over the claim.” Id. § 7103(b)(3). Rather, when a certification is “defective,” the “court or agency board shall require a defective certification to be corrected.” Id. DAI argues that the Board erred in dismissing its appeals for lack of jurisdiction based on nontechnical defects and reckless or negligent disregard for the certification requirements. Appellant’s Br. at 16–19. We agree. Contrary to the Board’s statement of the law, there is no statutory requirement that a defect in a certification be merely “technical” to be correctable. See Developmental Alts., Inc., CBCA 5942 at 8. Nor is there a statutory basis for finding a defective certification uncorrectable based on “intentional, reckless, or negligent disregard for the applicable certification requirements.” See id. In reaching the opposite conclusion, the Board relied on the text of an unenacted version of the governing statute, which passed only in the Senate:

If the certification of a claim pursuant to this Act is technically defective, a court or agency board of contract appeals may permit the certification to be corrected at any time prior to a final decision by the court or agency board of contract appeals unless the 48 C.F.R. § 33.207(c).

The particular language required to certify a claim is prescribed by regulation: I certify that the claim is made in good faith; that the supporting data are accurate and complete to the best of my knowledge and belief; that the amount requested accurately reflects the contract adjustment for which the contractor believes the Government is liable; and that I am duly authorized to certify the claim on behalf of the contractor.

failure properly to certify in the first instance was fraudulent, in bad faith, or with reckless or grossly negligent disregard of the requirements of the relevant statutes or regulations.

138 Cong. Rec. 21,033, 21,036 (1992) (emphasis added).

The House removed the italicized language from the legislation prior to its vote. Id. at 31,172, 31,174. The Senate adopted the House version and it was signed into law. Id. at 33,632, 33,635.

The statute, as enacted, mentions only “defective certification[s]” without reference to the technical nature of the defect or mens rea. See 41 U.S.C. § 7103(b)(3). It is axiomatic that a statute should not be read to implicitly include language specifically rejected by Congress. I.N.S. v. Cardoza-Fonseca, 480 U.S. 421, 442 (1987). The Board’s statement to the contrary, declaring the differences to be irrelevant, is erroneous and inconsistent with the plain language of the statute itself. See Developmental Alts., Inc., CBCA 5942 at 9 n.3 (citing Engineered Demolition, Inc. v. United States, 60 Fed. Cl. 822, 828–29 (2004)). We hold that § 7103(b)(3) does not limit defects to those that are technical in nature nor does it limit a contractor’s right to correct a defect if the initial certification was made with “intentional, reckless, or negligent disregard for the applicable certification requirements.” See id. at 8.

The plain language of the statute that “[a] defect in the certification of a claim does not deprive a court or an agency board of jurisdiction over the claim” requires that we reverse the contract board’s contrary conclusion. The contract board erred in its statutory interpretation regarding a defective certification.

DAI argues that its May 10 submission to USAID contained a defective certification. Appellant’s Br. at 11–16. Under a proper reading of the statute, DAI is correct that its submission constitutes a defective certification. The May 10, 2017 cover letter conveys a clear intent to certify

the underlying claims and expressly states that it is an attempt to comply with the Contract Disputes Act: As DAI believes there is a sound basis for these claims, we are sponsoring these . . . certified claims. [EI], DAI’s Security Service Provider, was not able to receive an exemption to the five-hundred-person [c]ap imposed by the changes in the local laws of [Afghanistan]. Therefore, [EI] incurred the resulting fines during [its] performance under the abovereferenced awards.

Given that [EI] is the real party in interest and is the only one who can logically and realistically certify these claims, DAI hereby submits this certification in satisfaction of the requirements of the Contract Disputes Act. As DAI is not the real party in interest, DAI must accept and rely on the [EI] certification at face value. In addition, DAI has no knowledge, which suggests that [EI] has knowingly or intentionally failed to comply with the requirements of the Contract[] Disputes Act or has acted in bad faith.

J.A. 29. EI’s certifications, which mirror the certification language required by 48 C.F.R. § 33.207(c), further evidence an intent to certify the claims: I certify that the claim is made in good faith; that the supporting data are accurate and complete to the best of my knowledge and belief; that the amount requested accurately reflects the contract adjustment for which the subcontractor believes DAI and the Government to be liable; and that I am duly authorized to certify the claim on behalf of the subcontractor.

See, e.g., J.A. 47. Taken together, these documents are sufficient to constitute a defective certification within the meaning of § 7103(b)(3).

A contracting officer must, within 60 days of receiving a submitted certified claim, issue a decision or notify the contractor of the time within which a decision will be issued. 41 U.S.C. § 7103(f)(2). If the contracting officer fails to issue a decision in the specified time, the claim is deemed denied and becomes appealable to the Board. Id.

§§ 7103(f)(5), 7105(e)(1)(B). The contracting officer is relieved of the obligation to issue a decision, however, if “within 60 days after receipt of the claim, the contracting officer notifies the contractor in writing of the reasons why any attempted certification was found to be defective.” Id. § 7103(b)(3).

It is undisputed that the contracting officer failed to notify DAI of the defect within the statutory period. Appellee’s Br. at 28. DAI submitted its claims on May 10, 2017 and did not receive notice of the defect until July 19, 2017, more than 60 days after DAI filed its claim. The contracting officer was therefore required to issue a decision on DAI’s claims. See 41 U.S.C. §§ 7103(f)(2), (b)(3). But the contracting officer failed to do so. Because the contracting officer failed to issue a decision within the statutory period, DAI’s claim was deemed denied and became appealable to the Board. 41 U.S.C. §§ 7103(f)(5), 7105(e)(1)(B).

CONCLUSION

Because the Board has jurisdiction over DAI’s appeals of its deemed denied claims, we reverse the Board’s decision and remand for further proceedings.

REVERSED AND REMANDED

We do not decide whether DAI’s May 10, 2017 cover letter alone constitutes a “defective certification.”

COSTS

Costs to appellant.

This is a verbatim capture of the text layer of the court's own document in DAI Global, LLC fka Development Alternatives, Inc. v. Administrator of the United States Agency for International Development. Nothing is summarized or reworded, and the sections run in the order the court wrote them. One thing the page shows is not repeated in the text: the pagination furniture, which is the page numbers, the docket footer and the electronic filing stamp printed across the top of each page.

Related Decisions

Appeals From the CBCA

Also Reversed

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.