No. 2019-2449

Red Cedar Harmonia, LLC v. United States

Dec 18, 2020opinionAppeal from the Court of Federal Claims
AffirmedBid protestNonprecedentialContractor appealed

Disposition

AFFIRMED

Affirmed. Read from the standalone disposition line the opinion closes on. The court left the decision below standing. That is a win for whoever prevailed below, which is the appellee.

Key Facts

Appellant
Red Cedar Harmonia, LLC
Appellee
United States, Nextgen Federal Systems LLC
Appeal taken by
Contractor appealed

The contractor or protester lost below and brought the appeal.

Docket number
No. 2019-2449
Decided
Dec 18, 2020

From the opinion's own decided line.

Matter
Bid protest
Panel
PROST, MOORE, STOLL
Opinion by
MOORE

Appealed From

Court of Federal Claims19-405Read the decision below on this site

The Article I trial court whose contract and bid protest judgments this court reviews under 28 U.S.C. 1295(a)(3).

Appeal from the United States Court of Federal Claims in No. 1:19-cv-00405-CFL, Senior Judge Charles F. Lettow

Counsel

For the appellant
WALTER BRAD ENGLISH
Maynard, Cooper & Gale, PC
Huntsville, AL
For the appellant
EMILY J
Maynard, Cooper & Gale, PC
Huntsville, AL
Also appearing
RICH
For the appellee
SONIA W. MURPHY
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
For the appellee
JEFFREY B
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
For the appellee
CHE PETER DUNGAN
Miles & Stockbridge P.C
Wash- ington, DC
For the appellee
ALFRED M
Miles & Stockbridge P.C
Wash- ington, DC
Opinion PDF (cafc.uscourts.gov)The disposition, the side that appealed and the appearances above are read deterministically from the opinion's own words. The court's document is the source of record.

Research This Decision

Create a free account to open this decision in the Federal Circuit workspace: the filtered browser over every appeal, the outcome dashboard, and the reading that follows an appeal down to the decision under review and across the cases it cites.

Browse with Filters

Every government-contracts appeal in the corpus, filtered by the tribunal below, the disposition, precedential status and matter, with full-text search over the opinions.

Insights

Contractor relief by disposition and by the side that appealed, per tribunal below and per year, with every denominator visible beside its rate.

Cross-Corpus Reading

The Appealed-from join into the Court of Federal Claims, ASBCA and CBCA corpora, and the cited-cases panel that names every prior decision this opinion relies on.

Full Opinion

Full text of the opinion6 pages, 10,617 characters, read from the court's own documentDecided Dec 18, 2020 on the opinion's own line Decision documentOfficial source: U.S. Court of Appeals for the Federal Circuit opinions and orders
PanelPROST, MOORE, STOLLOpinion byMOORENonprecedentialAffirmed
Appealed fromUnited States Court of Federal Claims1:19-cv-00405-CFLJudge Charles F. LettowThe opinion states: Appeal from the United States Court of Federal Claims in No. 1:19-cv-00405-CFL, Senior Judge Charles F. Lettow
The opinion closes: AFFIRMED(the standalone disposition line)

Authorities cited

3 authorities read from this opinion's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Tucker Act and the Judicial Code2
Administrative Procedure Act1

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

4 cases this opinion cites, grouped by the forum that decided each, in the order it first names them. 3 of them open at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

N OTE: This disposition is nonprecedential.

United States Court of Appeals

for the Federal Circuit

RED CEDAR HARMONIA, LLC,

Plaintiff-Appellant

v.

UNITED STATES, NEXTGEN FEDERAL SYSTEMS, LLC,

Defendants-Appellees

2019-2449

Appeal from the United States Court of Federal Claims

in No. 1:19-cv-00405-CFL, Senior Judge Charles F. Lettow.

Decided: December 18, 2020

The case caption as the opinion prints it. Every word is kept; only a line that is nothing but a drawn rule is left out.

For the appellant
WALTER BRAD ENGLISH
Maynard, Cooper & Gale, PC
Huntsville, AL
As the opinion writes it

WALTER BRAD ENGLISH, Maynard, Cooper & Gale, PC, Huntsville, AL, for plaintiff-appellant. Also represented by EMILY J. CHANCEY, MICHAEL W.

EMILY J
Maynard, Cooper & Gale, PC
Huntsville, AL
As the opinion writes it

Also represented by EMILY J.

For the appellee
SONIA W. MURPHY
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
As the opinion writes it

SONIA W. MURPHY, Commercial Litigation Branch, Civil Division, United States Department of Justice, Wash- ington, DC, for defendant-appellee United States. Also represented by JEFFREY B. CLARK, STEVEN JOHN GILLINGHAM, ROBERT EDWARD KIRSCHMAN, J R.

JEFFREY B
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
As the opinion writes it

Also represented by JEFFREY B.

CHE PETER DUNGAN
Miles & Stockbridge P.C
Wash- ington, DC
As the opinion writes it

CHE PETER DUNGAN, Miles & Stockbridge P.C., Wash- ington, DC, for defendant-appellee NextGen Federal Sys- tems, LLC. Also represented by ALFRED M. WURGLITZ, Rockville, MD.

ALFRED M
Miles & Stockbridge P.C
Wash- ington, DC
As the opinion writes it

Also represented by ALFRED M.

Other appearances
RICH
As the opinion writes it

RICH.

WALTER BRAD ENGLISH , Maynard, Cooper & Gale, PC, Huntsville, AL, for plaintiff-appellant. Also represented by EMILY J. CHANCEY , MICHAEL W. RICH .

SONIA W. M URPHY , Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, for defendant-appellee United States. Also represented by J EFFREY B. CLARK, STEVEN J OHN G ILLINGHAM , ROBERT EDWARD K IRSCHMAN, J R.

CHE P ETER D UNGAN, Miles & Stockbridge P.C., Washington, DC, for defendant-appellee NextGen Federal Systems, LLC. Also represented by ALFRED M. WURGLITZ, Rockville, MD.

Before PROST, Chief Judge, MOORE and STOLL, Circuit

Judges.

MOORE, Circuit Judge.

Red Cedar Harmonia, LLC, appeals a final decision of the United States Court of Federal Claims granting the government and NextGen Federal Systems, LLC, judgment on the administrative record regarding the government’s contract award to NextGen. Red Cedar Harmonia, LLC v. United States, 144 Fed. Cl. 11, 29 (2019). Because the government’s contract award was not arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law, we affirm.

BACKGROUND

The Defense Information Systems Agency (the agency) issued a solicitation for independent verification and validation of software across four major agency command and control programs. J.A. 100034. The solicitation included three evaluation factors: (1) Technical/Management Approach; (2) Past Performance; and (3) Price. J.A. 100164. The Technical/Management Approach factor included six subfactors: (1) security clearance requirements; (2) technical approach to test execution; (3) technical approach to test event build support; (4) technical approach to cybersecurity and information compliance; (5) technical approach to test process improvements and test automation support; and (6) management/staffing approach. Id. As relevant here, subfactor three was evaluated based on the offerors’ proposed approaches to perform independent verification and validation on multiple system builds. J.A. 100166. Subfactor six focused on offerors’ respective abilities to

staff and manage the tasks identified in the solicitation. J.A. 100167.

The agency received initial proposals from five offerors. After three offerors were excluded, the agency established a competitive range including the two remaining offerors: NextGen and Red Cedar. J.A. 102539–40. During its initial analysis, the agency found two weaknesses with NextGen’s management/staffing approach (subfactor six), including weaknesses in the hours NextGen proposed for thirty-eight labor positions, and four weaknesses with Red Cedar’s approach, including weaknesses in the hours Red Cedar proposed for fifty-eight positions. J.A. 102511–18 (NextGen), 102530–37 (Red Cedar). The contracting officer issued evaluation notices to NextGen and Red Cedar to address these weaknesses. J.A. 102563–102568 (NextGen), 102574–84 (Red Cedar).

After another round of proposals and evaluation notices, NextGen and Red Cedar submitted their final proposals. The agency found weaknesses in Red Cedar’s proposed hours for thirty-seven positions under subfactor six. J.A. 105164–105185. The agency revised Red Cedar’s final proposal, noting that Red Cedar’s approach appeared low for the demands of the contract and increasing the proposed hours across a number of positions. J.A. 105405–15. After adjustments, the agency found that NextGen’s total proposed cost was equal to the agency’s total probable cost, whereas Red Cedar’s total proposed cost varied from the agency’s total probable cost by 55.35% resulting in a “significant[] increase[] [in] the Government’s cost risk during performance.” J.A. 105138. The Source Selection Authority issued a memorandum memorializing the agency’s determination that NextGen was the “highest[-]rated offeror, taking into consideration all non-price factors” and was “also the lowest-priced (evaluated) offer[or].” J.A. 105237. Red Cedar filed a bid protest in the Court of Federal Claims, challenging the agency’s contract award to

NextGen. NextGen intervened. Red Cedar, NextGen, and the government filed cross-motions for judgment on the administrative record. The Court of Federal Claims granted the government and NextGen judgment on the administrative record and denied Red Cedar’s motion. The court concluded that the agency’s decision to select NextGen was reasonable because NextGen’s proposal was “the lowest priced and highest technically rated proposal” and because the agency “properly determined [that NextGen] represented the best value for the government.” J.A. 34. Red Cedar appeals. We have jurisdiction under 28 U.S.C.

§ 1295(a)(3).

DISCUSSION

We review de novo Court of Federal Claims decisions granting judgment on the administrative record in bid protest cases. Bannum, Inc. v. United States, 404 F.3d 1346, 1351 (Fed. Cir. 2005). Under this standard, we consider whether the agency’s action was “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” See 5 U.S.C. § 706(2)(A); 28 U.S.C. § 1491(b)(4). We may set aside a procurement decision “if it lacked a rational basis or if the agency’s decision-making process involved a clear and prejudicial violation of statute, regulation, or procedure.” Croman Corp. v. United States, 724 F.3d 1357, 1363 (Fed. Cir. 2013). An agency is “entitled to a high degree of deference when faced with challenges to procurement decisions.” Orion Tech., Inc. v. United States, 704 F.3d 1344, 1351 (Fed. Cir. 2013).

Red Cedar contends that the trial court erred in determining that the agency’s evaluation of Red Cedar’s proposed price was reasonable. It argues the agency’s evaluation under subfactor six, which affected the agency’s overall price evaluation (factor three), improperly focused on Red Cedar’s interim proposals, rather than its final hours and labor mix. We do not agree.

As the trial court noted, the “[a]gency provided a consistent and coherent explanation at each stage of the evaluation.” J.A. 27. The technical evaluators gave Red Cedar a marginal rating for its initial proposed labor mix, indicating that the “[p]roposal [did] not demonstrate an adequate approach and understanding of the requirements.”

J.A. 105157; 102532. And despite repeated notices that its hours were deficient, Red Cedar issued a final labor mix that failed to adequately remedy weaknesses for over thirty positions. The agency, therefore, rationally adjusted Red Cedar’s proposed hours and price to determine a probable cost to the agency in conformance with the solicitation’s price evaluation instructions. J.A. 30. On this record, we hold that the Court of Federal Claims did not err in holding that the agency’s evaluation of Red Cedar’s proposed price was not arbitrary, capricious, or in violation of law.

Red Cedar also contends the trial court erred in determining that Red Cedar was neither treated unequally nor evaluated based on unstated criteria. It argues that the agency evaluated Red Cedar based on unstated criteria when it improperly considered allegedly redundant aspects of NextGen’s technical approach under subfactor three, rather than limiting its consideration of those aspects to the agency’s subfactor five analysis. It further argues that the agency treated Red Cedar unfairly by improperly relying on evidence of NextGen’s experience under subfactor six while discounting Red Cedar’s evidence. These contentions are unavailing.

The agency acted within its broad discretion in awarding NextGen a strength for its technical approach under subfactor three. See Orion Tech., 704 F.3d at 1351. Pursuant to the solicitation, the agency considered NextGen’s and Red Cedar’s proposed approaches for the contract’s testbed event support. There is no evidence that the agency relied upon criteria outside of the designated criteria under subfactor three. There is, therefore, no support in the administrative record for Red Cedar’s contention that it was evaluated based on unstated criteria.

To the extent Red Cedar argues that the agency should have decreased hours in other labor categories to offset any increase in hours, the administrative record does not support any such offset requirement.

With respect to subfactor six, the solicitation indicated that it would evaluate the appropriateness of the offeror’s proposed labor mix in meeting or exceeding the agency’s requirements. The solicitation expressly noted that the demonstration of “breadth and depth of staff and expertise” was encouraged and could result in a higher rating. J.A. 100167. The agency rationally evaluated the totality of evidence presented under these criteria and concluded that NextGen’s proposal was more technically sound than Red Cedar’s proposal. Therefore, Red Cedar’s claim of unequal treatment under subfactor six is likewise without merit. On this record, we hold that the Court of Federal Claims did not err in holding that the agency’s evaluation of Red Cedar’s and NextGen’s respective strengths under subfactors three and six was not arbitrary, capricious, or in violation of law.

CONCLUSION

We have considered the parties’ remaining arguments and do not find them persuasive. Because the Court of Federal Clams did not err in granting the government and NextGen judgment on the administrative record, we affirm.

AFFIRMED

This is a verbatim capture of the text layer of the court's own document in Red Cedar Harmonia, LLC v. United States. Nothing is summarized or reworded, and the sections run in the order the court wrote them. One thing the page shows is not repeated in the text: the pagination furniture, which is the page numbers, the docket footer and the electronic filing stamp printed across the top of each page.

Related Decisions

Appeals From the Court of Federal Claims

Also Affirmed

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.