No. 2023-2229

Balfour Beatty Constr., LLC v. Administrator, GSA

Mar 13, 2025opinionAppeal from the CBCA
VacatedContract disputeNonprecedentialContractor appealed

Disposition

VACATED AND REMANDED

Vacated. Read from the standalone disposition line the opinion closes on. The court set the decision below aside, usually with a remand for further proceedings. The appellant obtained relief.

Key Facts

Appellant
Balfour Beatty Construction, LLC
Appellee
Administrator of the General Services Administration
Appeal taken by
Contractor appealed

The contractor or protester lost below and brought the appeal.

Docket number
No. 2023-2229
Decided
Mar 13, 2025

From the opinion's own decided line.

Matter
Contract dispute
Panel
REYNA, SCHALL, HUGHES
Opinion by
HUGHES

Appealed From

The Civilian Board of Contract Appeals, the Contract Disputes Act board for the civilian executive agencies.

Appeal from the Civilian Board of Contract Appeals in No. 6750, Administrative Judge Harold C. Kullberg, Ad ministrative Judge Kathleen J. O'Rourke, Administrative Judge Patricia J. Sheridan

Counsel

For the appellant
THOMAS HENDERSON DUPREE
JR, Gibson Dunn & Crutcher, LLP
Washington, DC
For the appellant
REGINALD JONES
JR, Gibson Dunn & Crutcher, LLP
Washington, DC
For the appellant
DIANA LYN CURTIS SHUTZER
JR, Gibson Dunn & Crutcher, LLP
Washington, DC
For the appellant
NICHOLAS SOLOSKY
JR, Gibson Dunn & Crutcher, LLP
Washington, DC
For the appellant
Fox Rothschild LLP
JR, Gibson Dunn & Crutcher, LLP
Washington, DC
For the appellant
Wash- ington
JR, Gibson Dunn & Crutcher, LLP
Washington, DC
For the appellee
BRYAN MICHAEL BYRD
Commercial Litigation Branch, Civil Division, United States Department of Justice
Washington, DC
For the appellee
BRIAN M
Commercial Litigation Branch, Civil Division, United States Department of Justice
Washington, DC
Also appearing
MCC ARTHY
CORINNE ANNE NIOSI
Opinion PDF (cafc.uscourts.gov)The disposition, the side that appealed and the appearances above are read deterministically from the opinion's own words. The court's document is the source of record.

Research This Decision

Create a free account to open this decision in the Federal Circuit workspace: the filtered browser over every appeal, the outcome dashboard, and the reading that follows an appeal down to the decision under review and across the cases it cites.

Browse with Filters

Every government-contracts appeal in the corpus, filtered by the tribunal below, the disposition, precedential status and matter, with full-text search over the opinions.

Insights

Contractor relief by disposition and by the side that appealed, per tribunal below and per year, with every denominator visible beside its rate.

Cross-Corpus Reading

The Appealed-from join into the Court of Federal Claims, ASBCA and CBCA corpora, and the cited-cases panel that names every prior decision this opinion relies on.

Full Opinion

Full text of the opinion6 pages, 9,727 characters, read from the court's own documentDecided Mar 13, 2025 on the opinion's own line Decision documentOfficial source: U.S. Court of Appeals for the Federal Circuit opinions and orders
PanelREYNA, SCHALL, HUGHESOpinion byHUGHESNonprecedentialVacated
Appealed fromCivilian Board of Contract Appeals6750Judge Harold C. KullbergThe opinion states: Appeal from the Civilian Board of Contract Appeals in No. 6750, Administrative Judge Harold C. Kullberg, Ad ministrative Judge Kathleen J. O'Rourke, Administrative Judge Patricia J. Sheridan
The opinion closes: VACATED AND REMANDED(the standalone disposition line)

Authorities cited

2 authorities read from this opinion's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Contract Disputes Act1
Tucker Act and the Judicial Code1

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

3 cases this opinion cites, in the order it first names them. 2 of them open at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

N OTE : This disposition is nonprecedential.

United States Court of Appeals

for the Federal Circuit

BALFOUR BEATTY CONSTRUCTION, LLC,

Appellant

v.

ADMINISTRATOR OF THE GENERAL SERVICES

ADMINISTRATION,

Appellee

2023-2229

Appeal from the Civilian Board of Contract Appeals in

No. 6750, Administrative Judge Harold C. Kullberg, Ad-

ministrative Judge Kathleen J. O'Rourke, Administrative

Judge Patricia J. Sheridan.

Decided: March 13, 2025

The case caption as the opinion prints it. Every word is kept; only a line that is nothing but a drawn rule is left out.

For the appellant
THOMAS HENDERSON DUPREE
JR, Gibson Dunn & Crutcher, LLP
Washington, DC
As the opinion writes it

THOMAS HENDERSON DUPREE, JR., Gibson Dunn & Crutcher, LLP, Washington, DC, argued for appellant. Also represented by REGINALD JONES, DIANA LYN CURTIS SHUTZER, NICHOLAS SOLOSKY, Fox Rothschild LLP, Wash- ington, DC.

REGINALD JONES
JR, Gibson Dunn & Crutcher, LLP
Washington, DC
As the opinion writes it

Also represented by REGINALD JONES.

DIANA LYN CURTIS SHUTZER
JR, Gibson Dunn & Crutcher, LLP
Washington, DC
As the opinion writes it

Also represented by DIANA LYN CURTIS SHUTZER.

NICHOLAS SOLOSKY
JR, Gibson Dunn & Crutcher, LLP
Washington, DC
As the opinion writes it

Also represented by NICHOLAS SOLOSKY.

Fox Rothschild LLP
JR, Gibson Dunn & Crutcher, LLP
Washington, DC
As the opinion writes it

Also represented by Fox Rothschild LLP.

Wash- ington
JR, Gibson Dunn & Crutcher, LLP
Washington, DC
As the opinion writes it

Also represented by Wash- ington.

For the appellee
BRYAN MICHAEL BYRD
Commercial Litigation Branch, Civil Division, United States Department of Justice
Washington, DC
As the opinion writes it

BRYAN MICHAEL BYRD, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for appellee. Also represented by BRIAN M. BOYNTON, PATRICIA M.

BRIAN M
Commercial Litigation Branch, Civil Division, United States Department of Justice
Washington, DC
As the opinion writes it

Also represented by BRIAN M.

Other appearances
MCC ARTHY
CORINNE ANNE NIOSI
As the opinion writes it

MCC ARTHY, CORINNE ANNE NIOSI.

T HOMAS HENDERSON DUPREE , JR ., Gibson Dunn & Crutcher, LLP, Washington, DC, argued for appellant.

Also represented by REGINALD J ONES, DIANA L YN C URTIS SHUTZER , N ICHOLAS SOLOSKY, Fox Rothschild LLP, Washington, DC.

BRYAN MICHAEL B YRD, Commercial Litigation Branch, Civil Division, United States Department of Justice,

Washington, DC, argued for appellee. Also represented by B RIAN M. B OYNTON, PATRICIA M. MCC ARTHY, C ORINNE A NNE N IOSI .

Before REYNA, SCHALL, and HUGHES, Circuit Judges.

HUGHES, Circuit Judge.

Balfour Beatty Construction, LLC, appeals the decision of the Civilian Board of Contract Appeals that granted in part some of Balfour’s claims to recover increased costs allegedly incurred because of compensable delay, errors in the solicitation bridging documents, differing site conditions, and changes to the contract. Balfour contends that it is entitled to recover the increased costs associated with the claims the Board denied. Because we conclude the Board erred in its design defect analysis, we vacate the Board’s denial of the design defect claim with respect to the mat slab foundation and remand for further proceedings not inconsistent with this opinion.

I

In 2016, the General Services Administration issued a solicitation for a Request for Proposals from a list of qualified offerors for a construction project. GSA selected the qualified firms based on responses to a Request for Qualifications it had issued earlier in 2016. The project entailed construction of phase two of the central utilities plant to support the U.S. Department of Homeland Security Headquarters on the grounds of the former St. Elizabeths Hospital. J.A. 1–2 & n.2; see also J.A. 151. The Request for Qualifications specified that GSA was using a design-build bridging project delivery method and that the bridging documents were approximately 30% complete. J.A. 151; 1334. The contract required that the selected contractor validate the design within 60 days of the notice to proceed, and then complete the design. The bridging documents also stated:

[t]he Bridging Documents are conceptual in nature and are intended to depict the overall intent of the project terms of general design concept, the major architectural elements, and describe the required performance of the other systems. As Bridging Documents they are preliminary in nature, are not fully coordinated and are not intended to indicate or describe the scope of work required for the full performance or completion of the project.

J.A. 5.

GSA awarded the contract to Balfour. Balfour alleges it ran into a variety of issues with the government’s design, the site conditions, and various delays. Appellant’s Opening Br. 8–20. Despite these issues, GSA accepted the project as substantially complete in 2019, and the project was deemed fully complete in early 2020. J.A. 156.

After the project was accepted as substantially complete, Balfour submitted a claim for increased costs. GSA’s contracting officer denied the claim in full. Balfour appealed to the Board. The Board granted Balfour’s claims in part and denied the remainder of the claims. Balfour timely filed its notice of appeal within 120 days of the Board’s decision. We have jurisdiction under 41 U.S.C. § 7107(a)(1)(A) and 28 U.S.C. § 1295(a)(10).

II

We review the Board’s determinations on questions of law, including contract interpretation, de novo. Reliable Contracting Grp., LLC v. Dep’t of Veterans Affs., 779 F.3d 1329, 1331 (Fed. Cir. 2015) (internal citation omitted). The Board’s factual determinations may not be set aside unless they are “(A) fraudulent, arbitrary or capricious; (B) so grossly erroneous as to necessarily imply bad faith; or (C) not supported by substantial evidence.” 41 U.S.C. § 7107(b); see also Rockies Express Pipeline LLC v. Salazar,

730 F.3d 1330, 1335 (Fed. Cir. 2013). “Substantial evidence is such relevant evidence as a reasonable mind might accept as adequate to support a conclusion.” Braun v. Dep’t of Health & Hum. Servs., 983 F.3d 1295, 1301 (Fed. Cir. 2020) (internal quotation marks and citation omitted).

III

Balfour raises a number of issues on appeal, but we need only discuss two in detail: design defects with respect to (1) the mat slab foundation and (2) the ventilation requirements. Balfour alleges that it incurred increased costs from “additional design and work scope associated with the required redesign . . . that arose out of deficiencies in the Bridging Design Documents provided by GSA.” J.A. 81 (internal quotation marks omitted). Specifically, Balfour contends it needed to redesign and depart from the bridging design to accommodate a thicker mat slab, which was required to handle the loads of the equipment and building columns, and from having to increase the height of the space to accommodate the equipment needed to provide adequate ventilation. Appellant’s Opening Br. 9–10. The Board denied Balfour’s claims. J.A. 83.

In United States v. Spearin, the Supreme Court held that “if the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications.” 248 U.S. 132, 136 (1918) (internal citations omitted). We have since clarified that this implied warranty attaches in contracts that contain design specifications, which “explicitly state how the contract is to be performed and permit no deviations.” Stuyvesant Dredging Co. v. U.S., 834 F.2d 1576, 1582 (Fed. Cir. 1987). But if the contract contains a performance specification, which specifies the result to be obtained but leaves the contractor free to determine how to achieve those results, the implied warranty does not attach. Id.

In a design-build bridging project delivery method, the government provides a partial design with the expectation that the contractor will complete the design and build the project. The Board analyzed the provisions of the contract and “consider[ed] to what extent a thirty-percent design . . . was design or performance.” J.A. 82. The Board determined that the bridging documents did not contain a warranty for the design of the mat slab at a particular thickness. The Board noted that, in addition to the contract drawing that directed the contractor to match the existing foundation thickness of 18 inches, GSA provided calculations from GSA consultants that called for a 24-inch foundation. The Board concluded that because these documents “raised a question about the mat slab thickness that should have caused Balfour to raise the issue before contract award,” Balfour was not entitled to recover costs related to designing the thicker mat slab. J.A. 83. We disagree.

The contract drawing indicated that Balfour should “match existing building foundations,” which were 18 inches thick. J.A. 11, 83. We determine the language in the drawing is sufficiently definite to constitute a design specification, and the Board erred in construing this as a performance specification. We conclude that there was an implied warranty with respect to the mat slab thickness. Further, even if there were a conflict between the drawing and the calculations, the mat slab Balfour ended up having to build was between 43 and 53 inches thick—almost double what the calculations required.

The Board then considered the additional costs related to meeting ventilation requirements. Balfour argues it incurred additional costs in complying with ventilation requirements because compliant generators were too large to fit in the building space. See Appellant’s Opening Br. 34– 35. The Board noted that during the solicitation, GSA advised potential offerors that compliance with certain ventilation requirements “must be . . . assumed as the basis for bids.” J.A. 83. Therefore, the Board determined that

Balfour was not entitled to any increased costs incurred in complying with these ventilation requirements. J.A. 84. We agree. The ventilation requirements were set out as a performance specification, and therefore, no implied warranty attached.

IV

We have considered the remainder of Balfour’s arguments and find no reversible error. Because we conclude that the Board erred in determining that there was no implied warranty with respect to the mat slab thickness, we reverse and remand for further proceedings not inconsistent with this opinion.

VACATED AND REMANDED

COSTS

Costs to appellant Balfour.

This is a verbatim capture of the text layer of the court's own document in Balfour Beatty Constr., LLC v. Administrator, GSA. Nothing is summarized or reworded, and the sections run in the order the court wrote them. One thing the page shows is not repeated in the text: the pagination furniture, which is the page numbers, the docket footer and the electronic filing stamp printed across the top of each page.

Related Decisions

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.