No. 2023-2337

Williams Bldg. Co. v. Sec'y of State

Jul 23, 2025opinionAppeal from the CBCA
AffirmedContract disputeNonprecedentialContractor appealed

Disposition

AFFIRMED

Affirmed. Read from the standalone disposition line the opinion closes on. The court left the decision below standing. That is a win for whoever prevailed below, which is the appellee.

Key Facts

Appellant
Williams Building Company, Inc.
Appellee
Secretary of State
Appeal taken by
Contractor appealed

The contractor or protester lost below and brought the appeal.

Docket number
No. 2023-2337
Decided
Jul 23, 2025

From the opinion's own decided line.

Matter
Contract dispute
Panel
LOURIE, DYK, CHEN
Opinion by
LOURIE

Appealed From

The Civilian Board of Contract Appeals, the Contract Disputes Act board for the civilian executive agencies.

Appeal from the Civilian Board of Contract Appeals in Nos. 6650, 7147, Administrative Judge Harold D. Lester, Jr, Administrative Judge Joseph A. Vergilio, Administra tive Judge Kathleen J. O’Rourke

Counsel

For the appellant
KEVIN MICHAEL COX
Camardo Law Firm, P.C
Au- burn, NY
For the appellee
GEOFFREY M. LONG
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
For the appellee
BRIAN M
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
Opinion PDF (cafc.uscourts.gov)The disposition, the side that appealed and the appearances above are read deterministically from the opinion's own words. The court's document is the source of record.

Research This Decision

Create a free account to open this decision in the Federal Circuit workspace: the filtered browser over every appeal, the outcome dashboard, and the reading that follows an appeal down to the decision under review and across the cases it cites.

Browse with Filters

Every government-contracts appeal in the corpus, filtered by the tribunal below, the disposition, precedential status and matter, with full-text search over the opinions.

Insights

Contractor relief by disposition and by the side that appealed, per tribunal below and per year, with every denominator visible beside its rate.

Cross-Corpus Reading

The Appealed-from join into the Court of Federal Claims, ASBCA and CBCA corpora, and the cited-cases panel that names every prior decision this opinion relies on.

Full Opinion

Full text of the opinion10 pages, 18,113 characters, read from the court's own documentDecided Jul 23, 2025 on the opinion's own line Decision documentOfficial source: U.S. Court of Appeals for the Federal Circuit opinions and orders
PanelLOURIE, DYK, CHENOpinion byLOURIENonprecedentialAffirmed
Appealed fromCivilian Board of Contract Appeals6650, 7147Judge Harold D. LesterThe opinion states: Appeal from the Civilian Board of Contract Appeals in Nos. 6650, 7147, Administrative Judge Harold D. Lester, Jr, Administrative Judge Joseph A. Vergilio, Administra tive Judge Kathleen J. O’Rourke
The opinion closes: AFFIRMED(the standalone disposition line)

Authorities cited

3 authorities read from this opinion's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Contract Disputes Act1
Tucker Act and the Judicial Code1
Agency FAR supplements1

Read from the opinion's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the opinion cites.

Cases cited

3 cases this opinion cites, in the order it first names them. 2 of them open at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Read from the opinion's own words with no model involved: the party names and the citation are as the opinion prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the opinion cites.

N OTE: This disposition is nonprecedential.

United States Court of Appeals

for the Federal Circuit

WILLIAMS BUILDING COMPANY, INC.,

Appellant

v.

SECRETARY OF STATE,

Appellee

2023-2337

Appeal from the Civilian Board of Contract Appeals in

Nos. 6650, 7147, Administrative Judge Harold D. Lester,

Jr, Administrative Judge Joseph A. Vergilio, Administra-

tive Judge Kathleen J. O’Rourke.

Decided: July 23, 2025

The case caption as the opinion prints it. Every word is kept; only a line that is nothing but a drawn rule is left out.

For the appellant
KEVIN MICHAEL COX
Camardo Law Firm, P.C
Au- burn, NY
As the opinion writes it

KEVIN MICHAEL COX, Camardo Law Firm, P.C., Au- burn, NY, argued for appellant.

For the appellee
GEOFFREY M. LONG
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
As the opinion writes it

GEOFFREY M. LONG, Commercial Litigation Branch, Civil Division, United States Department of Justice, Wash- ington, DC, argued for appellee. Also represented by BRIAN M. BOYNTON, PATRICIA M. MCCARTHY, CORINNE ANNE NIOSI; RANDAL WAX, Office of Legal Adviser for Buildings and Acquisitions, United States Department of State, Washington, DC.

BRIAN M
Commercial Litigation Branch, Civil Division, United States Department of Justice
Wash- ington, DC
As the opinion writes it

Also represented by BRIAN M.

K EVIN MICHAEL COX , Camardo Law Firm, P.C., Auburn, NY, argued for appellant.

G EOFFREY M. L ONG, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for appellee. Also represented by BRIAN M. BOYNTON, P ATRICIA M. MCCARTHY , CORINNE A NNE N IOSI; RANDAL WAX , Office of Legal Adviser for Buildings

and Acquisitions, United States Department of State, Washington, DC.

Before LOURIE, DYK, and CHEN, Circuit Judges.

LOURIE, Circuit Judge.

Williams Building Company, Inc. (“Williams”) appeals from the decision of the Civilian Board of Contract Appeals (“the Board”) that granted summary judgment in favor of the Department of State’s Bureau of Overseas Building Operations (“OBO”) on all three counts of its appeal to the Board. Williams Bldg. Co. v. Dep’t of State, CBCA 23-1 B.C.A. ¶ 38328, 2023 WL 3144494 (Apr. 26, 2023) (“Decision”), J.A. 1–33. For Count I and most of Count II, the Board determined that prior bilateral contract modifications and releases barred recovery. For the remainder of Count II and Count III, the Board determined that Williams could not prove damages. For the following reasons, we affirm.

BACKGROUND

As the Board noted, this case has “had a somewhat torturous history.” Decision, at J.A. 2. With that in mind, only the details most salient to the issues on appeal are summarized below. See id. at J.A. 2–14 (providing a more detailed history).

On June 15, 2016, Williams entered into a firm-fixedprice contract with the OBO for renovations of an office space in Wuhan, China. J.A. 1657–60. Following delays and disputes over the original “issued for construction” documents, the parties agreed to contract modifications P00007 (“modification-7”), J.A. 1793–99, and P00008 (“modification-8”), J.A. 1800–06, on March 16 and June 15, 2018, respectively. The modifications replaced the original “issued for construction” documents with new documents, provided for an extension of time, and each included an

agreement by Williams to release the government from further liability “attributable to such facts or circumstances giving rise to the proposals for adjustment.” J.A. 1799; J.A. 1806 (same).

Beginning in November 2018, Williams submitted a series of requests seeking additional money under the contract. See Decision, at J.A. 5. Among those requests were proposed change order (“PCO”) 075 requesting an extension of time and a request for equitable adjustment (“REA”) for alleged breaches of contract for a cardinal change due to the deficient original “issued for construction” documents and interference with Williams’ subcontractor, Huashi. Id. at J.A. 5–6. Those requests eventually evolved into two certified claims submitted to OBO on May 9, 2019: (1) seeking a time extension—beyond what was granted in modification-8—for alleged government-caused delays after January 31, 2018, and (2) seeking compensation for a cardinal change claim and a breach of contract claim for alleged interference with Huashi. Id. at J.A. 7–8. On August 13, 2019, the OBO contracting officer issued a final decision denying both claims. Id. at J.A. 8; J.A. 2676–701. Subsequently, on September 28, 2019, OBO and Williams settled the first claim seeking a time extension and a separate claim for customs storage fees with contract modification P00020 (“modification-20”). See J.A. 1839–50. Modification-20 provides that “[t]he contractor has three open certified legal claims related to customs storage fees, time delays, and cardinal changes to the contract. This [request for contract action (“RFCA”)] represents a partial settlement of the first two of these claims . . . . Additional funding to settle the Breach of Contract claims [e.g., the cardinal change claim] will be requested when additional funds are available.” J.A. 1847–48. The modification’s description of the scope of work provides additional details including PCO 067 for “Additional Storage Costs,” the aforementioned PCO 075 for “Time Extension,” and another contractor release for claims “attributable to the facts

or circumstances set forth in [Williams’] above-referenced PCOs.” J.A. 1850.

Then, on November 8, 2019, Williams appealed to the Board the contracting officer’s August 13, 2019 decision with respect to the second May 9, 2019 claim for breach. Williams’ complaint to the Board included three counts alleging breach of contract: (I) for a cardinal change to the contract, (II) for breach of the implied duty of good faith and fair dealing due to OBO’s untimely responses to Williams’ requests for information (“RFIs”) and submittals, and (III) for breach of the implied duty of good faith and fair dealing due to OBO’s alleged interferences with Williams’ relationship with its subcontractor, Huashi. J.A. 93–114. The complaint did not request a specific quantity of damages, but rather damages “in an amount to be determined at a hearing before the Board.” J.A. 115. OBO moved for a more definite statement on damages, which the Board granted. J.A. 40–44. The Board subsequently issued a scheduling order that required Williams to provide a detailed schedule of all costs it was seeking, along with identification of documentary support for said costs no later than October 16, 2020, and ordered that no other documentary support would be admitted at the hearing of the appeal. J.A. 47–48.

Following conclusion of discovery on June 30, 2021, the parties moved for summary judgment, and the Board granted judgment in favor of OBO on all three counts. For Count I, the Board determined that the broad releases in modification-7 and -8 barred the cardinal change claim and that modification-20 did not waive those releases. Decision, at J.A. 16–21. For Count II, the Board determined that the majority of the identified responses were associated with the circumstances of modification-7 and -8 and were thus barred by the releases contained therein and that Williams failed to identify any damages associated with the remainder. Id. at J.A. 21–24. For Count III, the Board determined that a genuine issue of fact existed

precluding summary judgment as to the breach, but that Williams failed to properly identify any costs associated with the alleged interference with Huashi because the evidence was first submitted by Williams in response to OBO’s summary judgment motion. Id. at J.A. 24–29.

Williams timely appealed, and we have jurisdiction under 28 U.S.C. § 1295(a)(10).

DISCUSSION

We review the Board’s determinations on questions of law, including contract interpretation, de novo. Rockies Express Pipeline LLC v. Salazar, 730 F.3d 1330, 1335–36 (Fed. Cir. 2013). The Board’s factual determinations may not be set aside unless they are “(A) fraudulent, arbitrary, or capricious; (B) so grossly erroneous as to necessarily imply bad faith; or (C) not supported by substantial evidence.” 41 U.S.C. § 7107(b); see also Rockies Express Pipeline, 730 F.3d at 1335. The Board’s decisions regarding procedure relating to discovery and evidentiary issues shall not be overturned unless an abuse of discretion is clear and is harmful. Johnson Mgmt. Grp. CFC, Inc. v. Martinez, 308 F.3d 1245, 1252 (Fed. Cir. 2002).

On appeal, Williams argues that the Board erred in its interpretation of modification-20. Williams’ argument focuses on three sentences of the description of modification-20 included in the line-item summary table for the contract. The description is reproduced in its entirety herein below:

This RFCA is for time delays experienced on the project related to design changes and a project shutdown caused by security concerns when the general contractor changed their major local subcontractor. The contractor has three open certified legal claims related to storage fees, time delays, and cardinal changes to the contract. This RFCA represents a partial settlement of the first two of these

claims. Time delays compensated by this RFCA are related to the following changes during construction. (This RFCA addresses PCO 067 Storage costs related to customs warehousing of critical materials - $185,663.90. PCO 075 Additional Time related Costs - $4,578,004.66. [Total: $4,763,668.56]. Bond Cost for the preceding of $235,657.17 to cover contract extension to new end date of 29 February 2020. [Grand total: $4,999,325.73]. Additional funding to settle the Breach of Contract claims will be requested when additional funds are available. J.A. 1847–48 (emphases added). It is not clear whether the reference to the “Breach of Contract claims” in the last sentence includes more than the cardinal change claim, but both parties agree that the reference includes the cardinal change claim. Specifically, Williams argues that the final sentence, “[a]dditional funding to settle the Breach of Contract claims will be requested when additional funds are available,” represents an agreement to its entitlement to its cardinal change claim. Williams Br. at 24. According to Williams, the above language unambiguously provides that modification-20 was intended to be a global resolution of all Williams’ outstanding claims, “a partial settlement of the first two” claims relating to storage fees and time delays, and an agreement to Williams’ entitlement to the cardinal change claim by acknowledgement that those funds “will be requested when additional funds are available.” Id. at 25–26. We disagree. The plain language of modification-20 does not concede liability for Williams’ cardinal change claim. Contrary to Williams’ assertions, the above paragraph makes clear that modification-20 is meant to address the first two claims only. It specifically notes that there are “three open certified legal claims” and the agreement “represents a partial settlement of the first two.” J.A. 1847. The next two sentences go on to describe the settlement of the first two claims in greater detail without mentioning the cardinal

change claim. The final sentence then addresses the “Breach of Contract claims” which includes the cardinal change claim. At most, the final sentence can be read as an agreement to keep the cardinal change claim open for future settlement negotiations after additional funds have been requested. That understanding is bolstered by the scope of work description on the last page of the agreement, which provides additional details of the agreement with respect to the storage costs and the time extension, including a release of further liability from those claims for the government. See J.A. 1850. What the scope of work does not contain is of particular note; there is no agreement to liability for the cardinal change claim or any mention of the claim at all. See id. When viewed as a whole, it is clear that modification-20 was not intended to concede liability for the cardinal change claim.

Williams makes two arguments in the alternative regarding interpretation of the modifications. First, it argues that modification-20 vitiated the releases in the earlier modification-7 and -8 and thus allows for its Count I cardinal change claim. Williams Br. at 27–30. And second, it argues that modification-7 and -8 did not release all costs associated with its breach claims allowing for additional costs associated with its cardinal change claim. Id. at 30– 33. For similar reasons, those arguments also fail.

The basis for Williams’ cardinal change and first breach of implied duty for delayed responses claims is the substitution of the original “issued for construction” documents with new “issued for construction” documents. The substitution of those documents is expressly addressed by modification-7, J.A. 1793–99, and time delays associated with the unsuitable original documents is expressly covered by modification-8, J.A. 1800–06. The language of the contractor releases is clear. Williams agreed to release the government from “any and all liability . . . attributable to such facts or circumstances giving rise to the proposals for adjustment” for both modifications. J.A. 1799 (emphasis

added); see also J.A. 1806. At bottom, modification-7 and -8 released the government from “any and all” liability for additional claims associated with the document substitution, and nothing in the subsequent modification-20 demonstrates an intent to alter those original release agreements. We therefore agree with the Board’s conclusion that the prior bilateral contract modifications and releases barred Count I and the relevant portions of Count

II.

Notwithstanding the contract interpretation arguments, Williams argues that the Board erred in granting summary judgment in favor of OBO on Count III because it erred in granting OBO’s earlier motion for a more definite statement on costs. According to Williams, the Board violated its Rule 6(d) because it provides that “[t]he Board may allow a party . . . to move for a more definite statement in lieu of filing an answer.” Williams Br. at 33–36 (quoting 48 C.F.R. § 6101.6). That is because OBO both failed to seek leave to file its motion and filed its answer while the motion was still pending. Id. However, the Board specifically addressed that precise issue in its order. See J.A. 42. It interpreted OBO’s motion as seeking to enforce Rule 6(a) that requires a complaint to “stat[e] in simple, concise, and direct terms the factual basis for each claim and the amount in controversy,” and determined that Williams’ complaint failed to satisfy that requirement. J.A. 42 (quoting 48 C.F.R. § 6101.6). The Board has discretion regarding issues of case management, and we see no abuse of discretion in its enforcement of its rules in that manner. See Johnson Mgmt. Grp., 308 F.3d at 1252 (finding no abuse of discretion in denial of discovery motions).

Williams further argues that the Board abused its discretion by issuing a scheduling order that required it to provide a detailed breakdown of its costs and supporting documentation because “requiring [Williams] to provide proof of all damages prior to discovery” was prejudicial. Williams Br. at 35–36. We disagree. As an initial matter,

Williams was not required to provide proof of all damages prior to discovery. There was a nearly five-month window after the opening of discovery until the final breakdown of costs and supporting documentation were due. See J.A. 47–49 (opening discovery on May 27, 2020, and ordering a complete schedule of cost with supporting documentation due on October 16, 2020). Furthermore, Williams has offered no explanation as to why that time was insufficient for it to understand and identify its own costs that it was seeking as part of its breach claim and provide its own documentation supporting those costs. Williams has therefore failed to establish an abuse of discretion in the Board’s order or demonstrate prejudice. See Curtin v. Off. of Pers. Mgmt., 846 F.2d 1373, 1379 (Fed. Cir. 1988) (“If an abuse of discretion did occur with respect to the discovery and evidentiary rulings, in order for petitioner to prevail on these issues he must prove that the error caused substantial harm or prejudice to his rights which could have affected the outcome of the case.”).

Williams’ argument continues that the Board erred by refusing to consider its evidence of costs first submitted in its opposition to summary judgment because it “did not have a full understanding of th[o]se costs until it reviewed documents provided by OBO.” Williams Br. at 36. Again, we disagree. Williams’ brief goes on to identify a wide variety of evidence from discovery that speaks to the merits of its breach claim, but none that demonstrates that Williams was unaware of the costs of the alleged breach or that it could not have identified those costs and the supporting documents in accordance with the Board’s scheduling order. See id. at 38–52. Because the Board did not abuse its discretion in issuing the scheduling order, we see no abuse of discretion in enforcing it later in the proceeding to grant summary judgment in favor of OBO on Count III.

CONCLUSION

We have considered Williams’ remaining arguments and find them unpersuasive. For the foregoing reasons, we affirm the decision of the Board.

AFFIRMED

This is a verbatim capture of the text layer of the court's own document in Williams Bldg. Co. v. Sec'y of State. Nothing is summarized or reworded, and the sections run in the order the court wrote them. One thing the page shows is not repeated in the text: the pagination furniture, which is the page numbers, the docket footer and the electronic filing stamp printed across the top of each page.

Related Decisions

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.