CBCA 3704(1821)-REM

Rockies Express Pipeline LLC

Jun 3, 2016Judge GoodmanDEPARTMENT OF THE INTERIOR
DecisionGranted in partby agreement

Key Facts

Appellant
Rockies Express Pipeline LLC
Respondent agency
DEPARTMENT OF THE INTERIOR
Judge
Goodman
Case number
CBCA 3704(1821)-REM
Decided
Jun 3, 2016The decision states Jun 3, 2016 on its own face, which agrees with the listing.
Decision type
Decision
Law firm for the appellant
Baker & Hostetler LLP, Norton Rose Fulbright US LLP
Outcome
Granted in partEntered by agreement of the parties.
Pursuant to the parties' motion for stipulated award, the Board GRANTS the appeal IN PART.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Jurisdiction and timelinessPayment and interest

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
L. Poe Leggette
Baker & Hostetler LLP
Denver, CO
For the appellant
Osborne J. Dykes, III and Kristopher C. Kleiner
Norton Rose Fulbright US LLP
Denver, CO
For the respondent
Colleen M. Burnidge and Matthew J. Wheeler and Amy M. Siadak
Office of the Regional Solicitor, Department of the Interior
Lakewood, CO
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision2 pages, 2,953 characters, read from the Board's own documentDecided Jun 3, 2016 on its own faceRespondent DEPARTMENT OF THE INTERIOR Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

3 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Contract Disputes Act1
Other statutes1
Agency FAR supplements1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

1 case this decision cites, in the order it first names it. 1 of them opens at a publisher.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

GRANTED IN PART: June 3, 2016

CBCA 3704(1821)-REM

ROCKIES EXPRESS PIPELINE LLC,

Appellant,

v.

DEPARTMENT OF THE INTERIOR,

Respondent.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

L. Poe Leggette of Baker & Hostetler LLP, Denver, CO; and Osborne J. Dykes, III, and Kristopher C. Kleiner of Norton Rose Fulbright US LLP, Denver, CO, counsel for Appellant.

Colleen M. Burnidge, Matthew J. Wheeler, and Amy M. Siadak, Office of the Regional Solicitor, Department of the Interior, Lakewood, CO, counsel for Respondent.

Before Board Judges SOMERS, GOODMAN, and WALTERS.

GOODMAN, Board Judge.

On June 29, 2009, appellant, Rockies Express Pipeline LLC, appealed a denial of its certified claim by a contracting officer of respondent, the Department of the Interior. This case is presently before the Board on remand. See Rockies Express Pipeline LLC v. Salazar, 730 F.3d 1330, 1342 (Fed. Cir. 2013).

On May 24, 2016, pursuant to Board Rule 25(b) (48 CFR 6101.25(b) (2015)), the parties submitted a joint stipulation of settlement and motion for judgment in the amount of sixty-five million dollars ($65,000,000) which states in relevant part: [T]he Parties request that the Board enter an unconditional judgment in favor of Appellant awarding damages in the amount of $65,000,000.00 (Sixty-Five Million Dollars) to be paid within 60 days of the date of judgment entered by the Board. It is understood that payment of the judgment amount will be made by the Treasury Department on behalf of respondent, [Department of the Interior], from the permanent indefinite judgment fund. If payment is not received by [appellant] on or before 30 days after judgment is entered by the Board, interest on the judgment amount will accrue thereafter at the rate(s) prescribed by the Contract Disputes Act (CDA) and payment of any such accrued CDA interest will be made together with the judgment amount. Each party will bear its own costs, attorneys’ fees, and expenses. The parties agree that neither party will seek reconsideration of, nor relief from the Board’s decision, and neither party will appeal the decision.

Pursuant to Rule 25(b) of the Board’s Rules of Procedure, appellant and respondent certify that they will not seek review or reconsideration of this judgment. With respect to this decision of the Board issued pursuant to the motion for stipulated award, appellant and respondent have executed certificates of finality that waive their rights to reconsideration under Rule 26, rights to relief from judgment under Rule 27, and rights to appeal the decision.

Decision

Pursuant to the parties’ motion for stipulated award, the Board GRANTS the appeal IN PART. Appellant is awarded a total of $65,000,000. Payment, with interest stated above, may be made from the permanent indefinite judgment fund, 31 U.S.C. § 1304 (2012). __________________________________

ALLAN H. GOODMAN

Board Judge

We concur:

JERI KAYLENE SOMERS

Board Judge

RICHARD C. WALTERS

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Rockies Express Pipeline LLC, CBCA 3704(1821)-REM. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.