CBCA 4111

Capitol Construction, Inc.

Jan 14, 2015Judge KullbergDEPARTMENT OF HOUSING AND URBAN DEVELOPMENT
DecisionDismissed for lack of jurisdiction

Key Facts

Appellant
Capitol Construction, Inc.
Respondent agency
DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT
Judge
Kullberg
Case number
CBCA 4111
Decided
Jan 14, 2015The decision states Jan 14, 2015 on its own face, which agrees with the listing.
Decision type
Decision
Law firm for the appellant
The decision's own appearances block names no outside firm, which happens when the appellant appeared pro se, through one of its own officers, or through its in-house counsel.
Outcome
Dismissed for lack of jurisdiction
The appeal is DISMISSED FOR LACK OF JURISDICTION.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Jurisdiction and timelinessChanges and equitable adjustment

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Jeffrey L. Byroade
Capitol Construction, Inc.
Windber, PA
For the respondent
William R. Taylor and Julie Kelley Cannatti
Office of the General Counsel, Department of Housing and Urban Development
Washington, DC
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision4 pages, 5,880 characters, read from the Board's own documentDecided Jan 14, 2015 on its own faceRespondent DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

2 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

1 case this decision cites, in the order it first names it. 1 of them opens at a publisher.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

DISMISSED FOR LACK OF JURISDICTION: January 14, 2015

CBCA 4111

CAPITOL CONSTRUCTION, INC.,

Appellant,

v.

DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT,

Respondent.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Jeffrey L. Byroade, President of Capitol Construction, Inc., Windber, PA, appearing for Appellant.

William R. Taylor and Julie Kelley Cannatti, Office of the General Counsel, Department of Housing and Urban Development, Washington, DC, counsel for Respondent.

Before Board Judges STERN, KULLBERG, and ZISCHKAU.

KULLBERG, Board Judge.

Respondent, the Department of Housing and Urban Development (HUD), has requested that the Board dismiss this appeal for lack of jurisdiction. Appellant, Capitol Construction, Inc. (CCI), brought this appeal after the denial of its claim under a contract with the County of Blair Redevelopment and Housing Authorities (COBRAH) in Hollidaysburg, Pennsylvania. The Board finds that it has no jurisdiction in this appeal because no executive agency of the Federal Government was a party to any contract with CCI that is at issue in this appeal. Accordingly, we dismiss this appeal for lack of jurisdiction.

Facts

On February 6, 2014, CCI and COBRAH executed contract 14-1 (contract) for kitchen counter top replacement in apartment units at a HUD-financed housing project. The contract between COBRAH and CCI incorporated a set of HUD clauses for public housing construction contracts. The definitions section in the HUD clauses defined a contracting officer (CO) as a person delegated by the public housing authority (PHA) to “enter into, administer, and/or terminate this contract and designated as such in writing to the Contractor.” The disputes clause in the HUD clauses provided that claims were to be submitted to the CO, and appeals of the CO’s decision were to be submitted “to a higher level in the PHA in accordance with the PHA’s policy and procedures.”

Funding for the contract was provided to COBRAH from HUD under an annual contributions contract (ACC). HUD provided COBRAH with funding for the ACC for the 2014 fiscal year under a capital funds program amendment, which was executed on May 13, 2014. CCI was not a party to the ACC.

On or about March 24, 2014, CCI commenced work, but the CO ordered CCI to stop work on April 1, 2014. Work resumed on July 8, 2014. CCI then submitted a request for a change order to COBRAH for the cost of delay, and by letter dated July 30, 2014, COBRAH denied CCI’s request. Subsequently, CCI filed its appeal with the Board on September 5, 2014. On September 30, 2014, HUD filed a motion to dismiss this appeal for lack of jurisdiction.

Discussion

HUD contends that the Board lacks jurisdiction to hear this appeal because “the subject of this appeal is not a contract for the procurement of property or services by a federal governmental agency, but instead this appeal pertains to a contract between a [PHA] and a service contractor to perform construction work to a public housing development owned and maintained by the relevant PHA.” Respondent’s Motion to Dismiss at 3. This Board has recognized that an appellant “bear[s] the burden of establishing subject matter jurisdiction by a preponderance of the evidence.” Opportunities for the Aging Housing Corp.

v. Department of Housing & Urban Development, CBCA 1501, 10-1 BCA ¶ 34,311, at 169,488 (2009). Under the Contract Disputes (CDA), 41 U.S.C. §§ 7101-7109 (2012), a contractor is defined as “a party to a Federal Government contract other than the Federal Government.” Id. § 7101(7). An executive agency is defined under the CDA as follows: (A) an executive department as defined in section 101 of title 5;

(B) a military department as defined in section 102 of title 5; (C) an independent establishment as defined by section 104 of title 5 . . . ; and

(D) a wholly owned Government corporation as defined in section 9101(3) of title 31.”

Id. § 7101(8).

The dispute in this appeal is between CCI and COBRAH, which is a PHA. A PHA is not an executive agency of the Federal Government, and a dispute between a contractor and a PHA, consequently, is not within the jurisdiction of this Board. See Management Strategies, Inc. v. Department of Housing & Urban Development, CBCA 2192, 11-1 BCA ¶ 34,683, at 170,835; Opportunities for the Aging Housing Corp., 10-1 BCA at 169,489. Accordingly, this Board has no jurisdiction over the dispute between CCI and COBRAH.

HUD, the respondent in this appeal, provided COBRAH with funding under an ACC, but such funding did not create a contractual relationship with CCI. The CDA states the following in pertinent part:

Unless otherwise specifically provided in this chapter, this chapter applies to any express or implied contract . . . made by an executive agency for–

(1) the procurement of property, other than real property in being;

(2) the procurement of services;

(3) the procurement of construction, alteration, repair or maintenance of real property; or,

(4) the disposal of personal property.

41 U.S.C. § 7102(a). It is well established that HUD’s funding of a PHA through an ACC is not a contract under the CDA, and such funding does not create a contractual relationship between HUD and those companies that contract with a PHA. New Era Construction v. United States, 890 F.2d 1152, 1155 (Fed. Cir. 1989), aff’g New Era Construction, HUD BCA 88-3406-C6, 89-1 BCA ¶ 21,376 (1988); Giljoy Technology, Inc. v. Department of Housing & Urban Development, CBCA 1988, 10-2 BCA ¶ 34,552. In this appeal, HUD only provided funding for COBRAH to enter into contracts related to housing projects under the terms of an ACC. HUD, consequently, did not become party to any contract over which the Board would have jurisdiction in this appeal.

Decision

The appeal is DISMISSED FOR LACK OF JURISDICTION. _________________________ H. CHUCK KULLBERG

Board Judge

We concur:

JAMES L. STERN

Board Judge

JONATHAN D. ZISCHKAU

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Capitol Construction, Inc., CBCA 4111. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.