CBCA 5395-R

CB&I AREVA MOX Services, LLC

Jun 1, 2017Judge DanielsDEPARTMENT OF ENERGY
DecisionRuled on a motion

Key Facts

Appellant
CB&I AREVA MOX Services, LLC
Respondent agency
DEPARTMENT OF ENERGY
Judge
Daniels
Case number
CBCA 5395-R
Decided
Jun 1, 2017The decision states Jun 1, 2017 on its own face, which agrees with the listing.
Decision type
Decision
Law firm for the appellant
The decision's own appearances block names no outside firm, which happens when the appellant appeared pro se, through one of its own officers, or through its in-house counsel.
Outcome
Ruled on a motion
The motion for reconsideration is consequently DENIED.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Procedure and sanctionsContract interpretation

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Noah M. Hicks II and James A. Ouellette Jr.
CB&I AREVA MOX Services, LLC
Aiken, SC
For the respondent
Matthew Butsick
Office of the General Counsel, National Nuclear Security Administration, Department of Energy
Washington, DC
For the respondent
Mary-Ellen Noone
Office of the General Counsel, National Nuclear Security Administration, Department of Energy
Aiken, SC
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision3 pages, 5,106 characters, read from the Board's own documentDecided Jun 1, 2017 on its own faceRespondent DEPARTMENT OF ENERGY Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Agency FAR supplements1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

MOTION FOR RECONSIDERATION DENIED: June 1, 2017

CBCA 5395-R

CB&I AREVA MOX SERVICES, LLC,

Appellant,

v.

DEPARTMENT OF ENERGY,

Respondent.

Noah M. Hicks II and James A. Ouellette Jr. of CB&I AREVA MOX Services, LLC,

Aiken, SC, counsel for Appellant.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Matthew Butsick, Office of the General Counsel, National Nuclear Security Administration, Department of Energy, Washington, DC; and Mary-Ellen Noone, Office of the General Counsel, National Nuclear Security Administration, Department of Energy, Aiken, SC, counsel for Respondent.

Before Board Judges DANIELS (Chairman), KULLBERG, and SULLIVAN.

DANIELS, Board Judge.

CB&I AREVA MOX Services, LLC (MOX Services) believes that it is entitled to a fee of .25% more than the Department of Energy’s (DOE’s) National Nuclear Security Administration paid, during a specified period of time, for work performed under a contract between the two parties. MOX Services has expressed this belief through two separate claims – one that the language of the contract, as amended, mandates this result, and the other that the contractor is entitled to the additional fee because the agency did not negotiate the matter in good faith.

We have issued two decisions in this case. In the first, we held that because the second claim had not been presented to the contracting officer, the Board had no jurisdiction to hear it. CB&I AREVA MOX Services, LLC v. Department of Energy, CBCA 5395, 17-1 BCA ¶ 36,591 (2016). MOX Services did not seek reconsideration of that decision. Instead, it has presented the claim to the contracting officer and awaits his decision on it.

In our second decision, we held, on cross-motions for summary relief, that the language of the contract, as amended, mandates the result sought by the agency and not the result sought by the contractor. CB&I AREVA MOX Services, LLC v. Department of Energy, CBCA 5395, 17-1 BCA ¶ 36,697. MOX Services seeks reconsideration of that decision.

MOX Services advances two arguments in support of its motion. First, it contends that “[t]he Board should reconsider its denial of MOX Services’ appeal and issue a stay in the present proceeding to prevent a manifest injustice.” The contractor urges that because [t]he facts of [the second] [c]laim are intertwined with the facts before the Board in the instant appeal . . . , it would directly and obviously (i.e., manifestly) result in an injustice to MOX Services to allow those factual findings made by the Board in reaching its decision to stand, without the Board considering the context of those additional and material facts asserted by MOX Services in its [second] [c]laim.

MOX Services’ second argument is that “[t]he Board should reconsider its decision because it is clear error for the Board to have made factual determinations in the absence of discovery between the Parties and also in light of MOX Services[’] opposition to the Government’s statement of uncontested facts.”

As DOE maintains, neither of these justifications for reconsideration is valid. As to the first: The Board has already held, and the contractor has accepted, that the facts relevant to the second claim (lack of good faith) are different from the facts relevant to the first claim (contract interpretation). 17-1 BCA ¶ 36,591, at 178,217-18. In other words, the facts relevant to the two claims are not “intertwined,” as the contractor suggests. If the contracting officer grants the second claim, or if he denies that claim and the contractor appeals his decision to the Board, the facts relevant to that claim may lead to a result different from the one we reached on the first claim. What MOX Services deems a “manifest injustice” will then have been avoided. But that result will be based on different facts, and reconsidering the analysis of the first claim will be unnecessary. The contractor has not shown us any facts relevant to the first claim that would mandate a different result as to that claim.

As to MOX Services’ second justification for reconsideration: The contractor’s assertion that discovery is necessary is at odds with its contention, in advancing its motion for summary relief, that the facts in this case are clear and unambiguous, so the Board may not resort to extrinsic evidence to interpret them. Further, the Board made no findings of fact in resolving the case; it relied on facts which were uncontested. Although MOX Services fancies that some of the facts were contested, the disputes concerned either legal argument or, as exemplified in footnote 1 of our decision, addressed facts which were not really in dispute. See 17-1 BCA ¶ 36,697, at 178,712 n.1. The contractor does not identify any issues which are both contested and relevant to the resolution of the claim which was before us.

Decision

MOX Services has not cited any valid ground for reconsideration. See Board Rules 26, 27(a) (48 CFR 6101.26, .27(a) (2016)). The motion for reconsideration is consequently DENIED.

_________________________

STEPHEN M. DANIELS

Board Judge

We concur:

H. CHUCK KULLBERG

Board Judge

MARIAN E. SULLIVAN

Board Judge

This is a verbatim capture of the text layer of the Board's own document in CB&I AREVA MOX Services, LLC, CBCA 5395-R. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.