CBCA 5527

Hawk Contracting Group, LLC

Dec 2, 2016Judge LesterDEPARTMENT OF VETERANS AFFAIRS
DecisionDenied

Key Facts

Appellant
Hawk Contracting Group, LLC
Respondent agency
DEPARTMENT OF VETERANS AFFAIRS
Judge
Lester
Case number
CBCA 5527
Decided
Dec 2, 2016The decision states Dec 2, 2016 on its own face, which agrees with the listing.
Decision type
Decision
Law firm for the appellant
Oles Morrison Rinker & Baker LLP
Outcome
Denied
For the foregoing reasons, we DENY Hawk's petition.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Termination for convenienceJurisdiction and timelinessDelay, suspension and accelerationChanges and equitable adjustment

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Thomas R. Krider and Alix K. Town
Oles Morrison Rinker & Baker LLP
Seattle, WA
For the respondent
Jennifer L. Hedge
Office of General Counsel, Department of Veterans Affairs
Pittsburgh, PA
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision5 pages, 11,751 characters, read from the Board's own documentDecided Dec 2, 2016 on its own faceRespondent DEPARTMENT OF VETERANS AFFAIRS Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

5 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Federal Acquisition Regulation1
Agency FAR supplements1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

3 cases this decision cites, grouped by the forum that decided each, in the order it first names them. 2 of them open at a publisher; the rest are shown without a link because no published copy of them was confirmed.

District courts1
Navajo Health Foundation-Sage Memorial Hospital, Inc. v. Burwell110 F. Supp. 3d 1140(D.N.M. 2015)

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

DENIED: December 2, 2016

CBCA 5527

HAWK CONTRACTING GROUP, LLC,

Petitioner,

v.

DEPARTMENT OF VETERANS AFFAIRS,

Respondent.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Thomas R. Krider and Alix K. Town of Oles Morrison Rinker & Baker LLP, Seattle, WA, counsel for Petitioner.

Jennifer L. Hedge, Office of General Counsel, Department of Veterans Affairs, Pittsburgh, PA, counsel for Respondent.

Before Board Judges VERGILIO, KULLBERG, and LESTER.

LESTER, Board Judge.

Pursuant to section 7103(f)(4) of the Contract Disputes Act (CDA), 41 U.S.C.

§§ 7101-7109 (2012), and Board Rules 1(b)(7) and 2(a)(2) (48 CFR 6101.1(b)(7), .2(a)(2) (2015)), petitioner, Hawk Contracting Group, LLC (Hawk), requests that the Board direct the Department of Veterans Affairs (VA) contracting officer to issue a decision earlier than the date that the contracting officer has identified for its expected issuance. For the reasons set forth below, we deny Hawk’s request.

Background

On September 17, 2013, the VA awarded contract no. VA69D-13-C-0289 (the contract) to Hawk to remodel and expand the material management area at the Jesse Brown Veterans Affairs Medical Center in Chicago, Illinois. The VA terminated the contract for the convenience of the Government on June 11, 2015, and requested that Hawk submit a termination settlement proposal. Hawk submitted that proposal on December 31, 2015, along with a cover letter expressing a desire for a prompt resolution of the negotiation and settlement process.

On January 29, 2016, in response to a status update request from Hawk, the VA indicated that, pursuant to the requirements of the Federal Acquisition Regulation (FAR), it would need to audit Hawk’s proposal because Hawk was seeking recovery of more than $100,000. Over the course of the next few months, Hawk sought further updates from the VA and was eventually informed that the VA Office of the Inspector General (OIG) had declined the contracting officer’s request for an audit of Hawk’s proposal, requiring the VA to search for a private contractor if it wished to have an audit conducted. Subsequently, the VA informed Hawk that an audit had been deemed not to be feasible.

After further negotiations did not result in a settlement, Hawk on August 4, 2016, converted its termination settlement proposal into a certified claim and requested that the VA contracting officer issue a decision within sixty days, in accordance with the contract’s Disputes clause. On October 3, 2016, the VA contracting officer notified Hawk that he anticipated a decision on or before January 20, 2017.

On October 24, 2016, Hawk filed its current petition with the Board, asking that we direct the contracting officer to issue his decision no later than November 30, 2016. Hawk further requested that, to the extent that the VA contracting officer does not comply with that Board order and issue a decision by November 30, 2016, the Board permit Hawk to appeal the contracting officer’s “deemed denial” immediately thereafter. Finally, Hawk has requested that, to the extent that we do not shorten the contracting officer’s existing deadline of January 20, 2017, we preclude any further extensions beyond that date.

Discussion

Pursuant to the CDA, within sixty days of receiving a contractor’s written certified claim of more than $100,000, the contracting officer must either issue a decision on the claim or notify the contractor “of the time within which a decision will be issued.” 41 U.S.C. § 7103(f)(2). If the contracting officer fails to issue a decision on the claim “within the required time period,” that failure may be “deemed to be a decision by the contracting officer denying the claim and authorizes an appeal or action on the claim” before, respectively, a board of contract appeals or the Court of Federal Claims. Id. § 7103(f)(5). Here, before the sixty-day period for issuing a decision on Hawk’s claim had expired, the contracting officer indicated that he anticipated issuing a decision on or before January 20, 2017. We treat this as a commitment to issuing a decision no later than that date. Until there is a decision on Hawk’s claim, or the date for issuance passes, Hawk cannot maintain an appeal with the Board or a suit at the Court of Federal Claims on its claim. See Paragon Energy Corp. v. United States, 645 F.2d 966, 971 (Ct. Cl. 1981); John C. Grimberg Co., ASBCA 42695, 91-3 BCA ¶ 24,074, at 120,520-21.

While the CDA permits the contracting officer to extend the deadline, it also requires that any written decision “be issued within a reasonable time, . . . taking into account such factors as the size and complexity of the claim and the adequacy of information in support of the claim provided by the contractor.” 41 U.S.C. § 7103(f)(3); see Rudolph & Sletten, Inc. v. United States, 120 Fed. Cl. 137, 141 n.2 (2015) (“Section 7103(f)(3) places a reasonableness limitation on section 7103(f)(2)(B) and prevents the contracting officer from setting a final decision date far in the future.”); Monster Government Solutions, LLC v. Department of Justice, CBCA 2834, 12-2 BCA ¶ 35,153, at 172,529 (contracting officer’s decision must be issued within “a reasonable time”). If the contractor believes that the contracting officer’s extension of the deadline for deciding its claim is unreasonable, it “may request the tribunal concerned to direct [the] contracting officer to issue a decision in a specified period of time, as determined by the tribunal concerned, in the event of undue delay on the part of the contracting officer.” 41 U.S.C. § 7103(f)(4); see USProtect Corp. v. Department of Homeland Security, CBCA 65, 08-1 BCA ¶ 33,782, at 167,200 (“In the event of delay by a contracting officer in rendering a decision on a contractor’s claim, . . . a contractor may petition a board of contract appeals to direct the contracting officer to render a decision within a specified time.”). Under section 7103(f)(4), the Board is authorized to alter a time extension that the contracting officer has granted himself, and to allow a contractor to appeal on a “deemed denial” basis if the contracting officer fails to issue a decision by the Board’s revised deadline for a decision, if it finds that the contracting officer’s extension was unreasonable. See, e.g., Rudolph & Sletten, 120 Fed. Cl. at 141-42 n.2 (“If the contracting officer does set an unreasonable decision date, section 7103(f)(4) allows the contractor to ask a [tribunal] to direct the contracting officer to issue a decision within a specified period of time.”); Volmar Construction, Inc., ASBCA 60710-910, 16-1 BCA ¶ 36,519, at 177,904 (reducing the time extension that the contracting officer had identified for issuance of a decision); Brasfield & Gorrie, LLC v. Department of Veterans Affairs, CBCA 3728, slip op. at 2 (Feb. 21, 2014) (same); Inslaw, Inc., DOT BCA 1609, et al., 90-2 BCA ¶ 22,701, at 114,003 (remedy for non-compliance with a board order directing issuance of a contracting officer decision by a date certain is to allow appeal on deemed denial basis).

“Whether the date stated by a [contracting officer] for issuance of a final decision is reasonable must be determined on a case-by-case basis.” Kelly-Ryan, Inc., ASBCA 57168, 11-1 BCA ¶ 34,629, at 170,634 (2010). Typically, in evaluating undue delay and reasonableness, a tribunal considers a number of factors, including the underlying claim’s complexity, the adequacy of contractor-provided supporting information, the need for external technical analysis by experts, the desirability of an audit, and the size of and detail contained in the claim. See Navajo Health Foundation-Sage Memorial Hospital, Inc. v. Burwell, 110 F. Supp. 3d 1140, 1190-91 (D.N.M. 2015) (citing and summarizing several board of contract appeals decisions on standards applicable to reviews under section 7103(f)(4)); VECO, Inc., DOT BCA 2961, 96-1 BCA ¶ 28,108, at 140,299 (1995). Matters that are wholly and exclusively within the Government’s control, such as internal staffing and agency funding levels, are generally not factors used to determine whether a time extension is “reasonable” under the CDA. See Volmar, 16-1 BCA at 177,904; VECO, 96-1 BCA at 140,299.

During a telephonic conference that the Board conducted with the parties on November 8, 2016, the VA reported that a significant reason for the contracting officer’s need to extend the decision deadline was his recent recognition that, pursuant to FAR 49.107 (48 CFR 49.107), he had been required to obtain an audit of Hawk’s settlement proposal – something that he initially had pursued, but then abandoned because of the unavailability of the OIG audit team and the cost of an outside auditor. The VA’s delay in commencing the current audit is plainly something that was within the VA’s control. The VA has had Hawk’s settlement proposal since December 31, 2015, meaning that it has had almost a year to conduct an audit. Although Hawk did not formally convert its termination settlement proposal into a “claim” under the CDA until August 2016, we cannot ignore the agency’s pre-claim awareness and ability to act when considering the reasonableness of the contracting officer’s extension of his decision deadline. See VECO, 96-1 BCA at 140,299 (“we cannot take the position that the time between the date of a request for equitable adjustment and the date it is perfected into a claim is to be completely disregarded in determining what is a reasonable time for purposes of § [7103(f)(4)]”); Fru-Con Construction Corp., ASBCA 53544, 02-1 BCA ¶ 31,729, at 156,758 (“it is appropriate to consider the Government’s prior familiarity with the issues raised in the claim for purposes of determining whether additional time is reasonably necessary”). The contracting officer’s delayed realization that an audit of termination settlement proposals exceeding $100,000 was mandatory is not Hawk’s fault and should not normally be a basis for delaying Hawk’s right to pursue action on its claim. At this time, the termination settlement proposal period has passed, and the contracting officer has a certified claim before him for a decision. Notwithstanding the time that the contracting officer has already had to review Hawk’s settlement proposal and claim, we conclude, considering all of the existing circumstances, that the January 20, 2017, date for the issuance of a decision does not represent undue delay. In setting that deadline, we recognize that an audit of Hawk’s claim, followed by a thorough contracting officer’s decision on that claim, would benefit Hawk, the Government, and any tribunal asked to review Hawk’s claim. We further recognize that the VA now appears (albeit belatedly) to be attempting to expedite the conduct of an audit. With only a few weeks remaining before the contracting officer’s stated decision deadline, we will not disrupt the existing schedule. Nevertheless, given the amount of time that has already elapsed since the VA received Hawk’s settlement proposal (and its claim), we can see no justification for any further extensions that would preclude Hawk from immediately beginning the litigation process after January 20 if that is what it wants to do. If the VA contracting officer does not issue a written decision by January 20, 2017, Hawk may consider its claim to have been deemed denied and may immediately file an appeal. See Design One Building Systems, Inc. v. Department of Veterans Affairs, CBCA 2423, 11-1 BCA ¶ 34,766, at 171,106.

Decision

For the foregoing reasons, we DENY Hawk’s petition. The VA contracting officer is to issue his decision no later than January 20, 2017.

________________________________

HAROLD D. LESTER, JR.

Board Judge

We concur:

JOSEPH A. VERGILIO

Board Judge

H. CHUCK KULLBERG

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Hawk Contracting Group, LLC, CBCA 5527. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.