CBCA 6650

Williams Building Company, Inc.

Apr 29, 2022Judge LesterDEPARTMENT OF STATE
DecisionRuled on a motion

Key Facts

Appellant
Williams Building Company, Inc.
Respondent agency
DEPARTMENT OF STATE
Judge
Lester
Case number
CBCA 6650
Decided
Apr 29, 2022The decision states Apr 29, 2022 on its own face, which agrees with the listing.
Decision type
Decision
Law firm for the appellant
Camardo Law Firm, P.C.
Outcome
Ruled on a motion
For the foregoing reasons, WBC's motion for summary judgment as to entitlement is DENIED.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Changes and equitable adjustmentDelay, suspension and accelerationJurisdiction and timelinessContract interpretationCosts and quantum

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Kevin M. Cox
Camardo Law Firm, P.C.
Auburn, NY
For the respondent
Jeffrey A. Regner and Randal W. Wax
Office of the Legal Adviser, Buildings and Acquisitions, Department of State
Washington, DC
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision6 pages, 12,627 characters, read from the Board's own documentDecided Apr 29, 2022 on its own faceRespondent DEPARTMENT OF STATE Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Cases cited

9 cases this decision cites, grouped by the forum that decided each, in the order it first names them. 8 of them open at a publisher; the rest are shown without a link because no published copy of them was confirmed.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

MOTION FOR SUMMARY JUDGMENT ON ENTITLEMENT DENIED:

April 29, 2022

CBCA 6650

WILLIAMS BUILDING COMPANY, INC.,

Appellant,

v.

DEPARTMENT OF STATE,

Respondent.

Kevin M. Cox of Camardo Law Firm, P.C., Auburn, NY, counsel for Appellant.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Jeffrey A. Regner and Randal W. Wax, Office of the Legal Adviser, Buildings and Acquisitions, Department of State, Washington, DC, counsel for Respondent.

Before Board Judges LESTER, VERGILIO, and O’ROURKE.

LESTER, Board Judge.

Appellant, Williams Building Company, Inc. (WBC), seeks summary judgment in its favor on entitlement. It asserts that, as part of a settlement agreement resolving two other contract claims that WBC had previously submitted to the Department of State’s Office of Overseas Building Operations (OBO), the OBO contracting officer conceded that WBC’s contract breach claim was valid and bound OBO to pay some as-yet-undefined damages amount for that breach. Because the language in the settlement agreement to which WBC cites does not concede liability for breach, we deny WBC’s motion.

Background

WBC’s Submission of Claims

On June 15, 2016, WBC entered into a firm fixed-price contract, contract no.

SAQMMA-16-C-0015 (the contract), with OBO for a tenant retrofit in an office building in Wuhan, China, that was expected to serve as an office of the United States Consulate. The contract anticipated contract completion by June 10, 2018. After various delays before and during contract performance, OBO and WBC entered into contract modification no. P00008, which extended the completion date to December 31, 2018; provided monetary compensation to WBC for past delays and anticipated future work; and contained WBC’s written release of claims predating February 22, 2018.

Beginning in late November 2018, WBC submitted what became a series of separate, but somewhat overlapping and seemingly duplicative, requests for additional monies and time extensions under the contract. Ultimately, the various submissions culminated in the following three claims:

WBC’s Customs Storage Fees Claim. On February 9, 2019, WBC submitted a claim to the OBO contracting officer seeking storage fees associated with a shipment of construction materials that WBC had to pay after the Government of China completed a customs review and clearance process. That claim incorporated a previously-submitted proposed change order (PCO), PCO 067.

WBC’s Time-Related Cost Claim. On May 9, 2019, WBC submitted a certified claim for time-related cost adjustments (Appeal File, Exhibit 621) in which it sought compensation for delays and associated time-related costs. This claim incorporated and expanded upon previously-submitted PCO 075. Through the claim, WBC sought a time extension of 341 days beyond December 31, 2018 – part of the extension was for excusable delays and part was for compensable delays – and sought an equitable adjustment of $3,203,679.38 in time-related costs.

WBC’s Cardinal Change/Implied Duty Breach Claim. WBC submitted a second certified claim on May 9, 2019, seeking damages for an alleged cardinal change to its contract and OBO’s alleged breach of the implied duty of good faith and fair dealing. In its claim, WBC repeatedly referenced and essentially incorporated an earlier request for equitable adjustment (REA) dated November 29, 2018, and indicated that its breach damages were $5,493,264, a figure that WBC asserted “[e]xcludes all costs subject to Time Related Cost Proposal.” Exhibit 63 at 1095. Other than an exhibit attached to the claim breaking down over $17 million that WBC had spent on the contract, there was nothing in the claim that identified specifically what costs were encompassed within that $5,493,264. Although WBC disavowed seeking any time-related costs through the breach claim, a timeline attached as exhibit no. 5 to the breach claim identified calendar days of delay that WBC thought were OBO’s responsibility.

1Unless otherwise noted, all exhibits cited in this decision are contained within the appeal file.

The OBO contracting officer denied the customs storage fees claim by decision dated March 31, 2019. On August 13, 2019, the OBO contracting officer issued a single, consolidated final decision denying both of the May 9, 2019, claims.

The Parties’ Settlement

On September 28, 2019, the parties executed bilateral modification no. P00020 (mod-20 or the modification) settling WBC’s “delay impact” claim for time delays and WBC’s claim for customs storage fees in exchange for an agreed-upon payment of just under $5 million. The parties indicated in the modification that they did not resolve, and expressly left open for further negotiation, WBC’s cardinal change/breach claim, as follows: This [modification] is for time delays experienced on the project related to design changes and a project shutdown caused by security concerns when the general contractor changed their major local subcontractor. The contractor has three open certified legal claims related to customs storage fees, time delays, and cardinal changes to the contract. This [modification] represents a partial settlement of the first two of these claims. Time delays compensated by this [modification] are related to the following changes during construction. This [modification] addresses PCO 067 Storage costs related to customs warehousing of critical materials -$185,663.90. PCO 075 Additional Time related Costs -$4,578,004.66 [Total: $4,763,668.56]. Bond Cost for the preceding of $235,657.17 to cover contract extension to new end date of 29 February 2020. [Grand total: $4,999.325.73]. Additional funding to settle the Breach of Contract claims will be requested when additional funds are available.

Exhibit 22 at 312-13 (emphasis added). The parties further agreed in the modification that PCOs 067 and 075 were fully resolved and released, as follows: 1. PCO 067 – Additional Storage Costs

Scope of Work: Government to provide reimbursement to the contractor for additional storage costs in China resulting from customs clearance delays.

Amount: $185,663.90 (No [Value-Added Tax (VAT)]) Time Extension: included in no. 2 below

2. PCO 075 – Time Extension

Scope of Work: Period of performance is extended from January 1, 2019 up through February 29, 2020. 358 days are compensable, 67 days non-compensable. (425 days total).

Amount: $4,813,661.83 – ($4,578,004.66 extended overhead costs + $235,657.17 costs) (No VAT)

Time Extension: None

Contractor’s Release

In consideration of the modification agreed to herein as a complete equitable adjustment in the amount of $4,999,325.73, WBC hereby releases the Government from any and all liability for further requests for equitable adjustments, claims or demands attributable to the facts or circumstances set forth in WBC’s above-referenced PCOs [067 and 075].

Id. at 315.

Proceedings Before the Board

On November 8, 2019, WBC filed with the Board an appeal of “the portion of the Contracting Officer’s Final Decision dated August 13, 2019, . . . denying its claim, as amended, for breach of contract/cardinal change/defective specifications/breach of implied duty of good faith and fair dealing.” Notice of Appeal at 1. WBC indicated in its notice that “[t]his appeal does not include the items negotiated and settled between the parties in Bilateral Modification No. P00020 in the amount of $4,999,325.73 (PCOs 067 and 075), which are specifically excepted out of this appeal,” although WBC did not include any kind of breakdown of the costs that were being claimed as part of this appeal or identify the total amount that it was seeking. Proceedings in this appeal, inclusive of discovery, have focused on OBO’s efforts to learn what costs WBC is claiming in this appeal that differ from what was a part of the time-related claim that was settled through mod-P20.

During the discovery process, WBC filed a motion seeking summary judgment on entitlement to damages under its cardinal change and implied duty breach claim, arguing that mod-P20 is “an express agreement as to entitlement regarding Appellant’s breach claim which is the subject of this appeal.” Appellant’s Reply Brief at 2. This decision addresses that motion.

Discussion

WBC argues that the OBO contracting officer, by signing a bilateral contract modification (mod-P20) in which he agreed to request “[a]dditional funding to settle the Breach of Contract claims . . . when the additional funds are available,” conceded that OBO had breached WBC’s contract. It says that, in mod-20, “the Government agreed that it would pay Appellant for its breach claim when the funding became available.” WBC seeks summary judgment in its favor as to entitlement on its breach claim, leaving only the amount of recoverable damages to be decided in further proceedings.

“The starting point for contract interpretation is ‘the plain language of the agreement.’” Belle Isle Investment Co. v. General Services Administration, CBCA 4734, 18-1 BCA ¶ 37,022 (2017) (quoting Foley Co. v. United States, 11 F3d 1032, 1034 (Fed. Cir. 1993)). We must “interpret the contract in a manner that gives meaning to all of its provisions and makes sense.” McAbee Construction, Inc. v. United States, 97 F.3d 1431, 1435 (Fed. Cir. 1996). If the “provisions are clear and unambiguous, they must be given their plain and ordinary meaning.” Id. (quoting Alaska Lumber & Pulp Co. v. Madigan, 2 F.3d 389, 392 (Fed. Cir. 1993)). Even if a particular provision is ambiguous, the ultimate interpretation adopted cannot conflict with or be unreasonable in light of the actual written language. See P.R. Burke Corp. v. United States, 277 F.3d 1346, 1356 (Fed. Cir. 2002) (“[A] contractor’s interpretation of a latent ambiguity will only be adopted if it is found to be reasonable.” (quoting Community Heating & Plumbing Co. v. Kelso, 987 F.2d 1575, 1579 n.6 (Fed. Cir. 1993)). Whatever the purpose of the reference to settlement funding, it is clear that OBO did not, through it, concede entitlement on WBC’s breach claim or affirmatively obligate itself to pay damages on that claim. To the extent that the agreement requires the contracting officer to request settlement funds, it does not require OBO actually to provide funding simply because the request is made or force a settlement if the parties cannot mutually agree to acceptable terms. This agreement to seek settlement funding is not, in and of itself, a concession of liability. See Chaparral Industries, Inc., ASBCA 34396, 91-2 BCA ¶ 23,813 (“[A] promise to use [certain] test results in the ‘resolution’ of the claim fell far short of an admission of legal liability contingent on those results” and “at most created an obligation to attempt in good faith to negotiate a settlement of the claim, if the . . . value derived from the test under the agreed formula exceeded the agreed threshold.”), aff’d sub nom. Chaparral Industries, Inc. v. Rice, 975 F.2d 870 (Fed. Cir. 1992) (table). To the extent that, as WBC appears to suggest, the sentence about seeking the settlement funding in question might be ambiguous, we normally could look to extrinsic evidence to assist in interpreting it. Metropolitan Area Transit, Inc. v. Nicholson, 463 F.3d 1256, 1260 (Fed. Cir. 2006). Here, though, WBC has not identified any extrinsic evidence in its motion to support its interpretation, leaving us with nothing to consider. In any event, even if WBC had presented evidence suggesting that OBO intended to concede liability on the breach claim, such evidence would conflict with the actual language in mod-P20, precluding our reliance on it. See Coast Federal Bank v. United States, 323 F.3d 1035, 1040 (Fed. Cir. 2003) (holding that a party “cannot rely on extrinsic evidence to interpret [contract phrases] to contradict the plain language of the Agreement”). Because the Government has not conceded liability through mod-P20, WBC cannot rely on that modification to avoid having to prove that OBO actually breached its contract. To prevail on its cardinal change/implied duty breach claim, the contractor will bear the burden of demonstrating liability, causation, and resultant injury. Servidone Construction Corp. v. United States, 931 F.2d 860, 861 (Fed. Cir. 1991); see Raytheon Co. v. United States, 747 F.3d 1341, 1352 (Fed. Cir. 2014) (“[A] contractor seeking an equitable adjustment for increased costs has the burden of proving entitlement and quantum to its claim.”).

Decision

For the foregoing reasons, WBC’s motion for summary judgment as to entitlement is DENIED.

Harold D. Lester, Jr.

Board Judge

We concur:

Joseph A. Vergilio

Board Judge

Kathleen J. O’Rourke

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Williams Building Company, Inc., CBCA 6650. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.