CBCA 7281

Badland Truck Sales, Inc.

Jun 14, 2022Judge KullbergGENERAL SERVICES ADMINISTRATION
DecisionDenied

Key Facts

Appellant
Badland Truck Sales, Inc.
Respondent agency
GENERAL SERVICES ADMINISTRATION
Judge
Kullberg
Case number
CBCA 7281
Decided
Jun 14, 2022The decision states Jun 14, 2022 on its own face, which agrees with the listing.
Decision type
Decision
Law firm for the appellant
The decision's own appearances block names no outside firm, which happens when the appellant appeared pro se, through one of its own officers, or through its in-house counsel.
Outcome
Denied
The appeal is DENIED.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Small claims and accelerated procedure

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions.

Appearances

For the appellant
Jeremy Alley
Badland Truck Sales, Inc.
Glendive, MT
For the respondent
Neeraj Kumar and Keaton Norquist
Office of Regional Counsel, General Services Administration
San Francisco, CA
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision6 pages, 11,642 characters, read from the Board's own documentDecided Jun 14, 2022 on its own faceRespondent GENERAL SERVICES ADMINISTRATION Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

3 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Agency FAR supplements1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

2 cases this decision cites, in the order it first names them. 2 of them open at a publisher.

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case cited to a reporter is not held here, so where it opens was confirmed one citation at a time against an outside database and is labelled as leaving this app; a citation that database could not place, or matched to more than one case, is shown without a link rather than guessed at. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

DENIED: June 14, 2022

CBCA 7281

BADLAND TRUCK SALES, INC.,

Appellant,

v.

GENERAL SERVICES ADMINISTRATION,

Respondent.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Jeremy Alley, President of Badland Truck Sales, Inc., Glendive, MT, appearing for Appellant.

Neeraj Kumar and Keaton Norquist, Office of Regional Counsel, General Services Administration, San Francisco, CA, counsel for Respondent.

KULLBERG, Board Judge.

Appellant, Badland Truck Sales (BTS), claims the amount of $10,500 for the reduction in price of a John Deere 544J wheeled loader (loader) that it purchased from the General Services Administration’s (GSA’s) auction website. BTS contends that it is entitled to the reduction in price because of problems with the loader that were unknown at the time of the sale. GSA, the respondent, has filed a motion for summary judgment in this appeal on the grounds that BTS failed to timely submit written notice of misdescription as required under the terms and conditions of its contract or, in the alternative, that the terms and conditions of the sale did not provide a warranty for the condition of the loader. BTS has opposed the motion on the grounds that GSA was aware of the condition of the loader, and it should have been allowed additional time to file its notice.

Subsequent to GSA’s motion for summary judgment, BTS elected to have the Board hear this appeal under the Board’s small claims procedure. Rule 52 (48 CFR 6101.52 (2020)). Accordingly, this decision “is final and conclusive, shall not be set aside except for fraud, and is not precedential.” Rule 52(c). For the reasons stated below, the Board grants GSA’s motion for summary judgment and denies the appeal.

Background

The Board finds the facts set forth below to be not in dispute.

On July 1, 2021, GSA offered the loader for sale on its auction website. The description of the wheel loader was the following: 2006 John Deere 544J Wheeled Loader . . . . Loader was acquired in August 2006 with original cost of $102,565.73. Unknown deficiencies.

SOLD AS IS. Inspection is highly recommended prior to bidding. Successful bidder is responsible for packing and removal. Loader is located at South Rim, Grand Canyon National Park 1575 Shuttlebus Rd., Grand Canyon, AZ.

GSA required that participants in its auctions “acknowledge that they have read and accepted ALL terms and conditions detailed on this website and indicate that they agree by marking the required box during the registration process.” Those terms and conditions, in pertinent part, were the following:

Condition of property is not warranted. Deficiencies, when known, have been indicated in the property descriptions. However, absence of any indicated deficiencies does not mean that none exists. Therefore, the bidder should ascertain the condition of the item through physical inspection.

. . . .

The Government warrants to the original purchaser that the property listed on GSAAuctions.gov will conform to its written description. Features, characteristics, deficiencies, etc. not addressed in the description are excluded from this warranty. GSA further cautions bidders that GSA’s written description represents GSA’s best effort to describe the item based on the information provided to it by the owning agency. Therefore, gross omissions regarding the functionality of items, failures to cite major missing parts and/or restrictions with regards to usage may occur.

The Government does not warrant the merchantability of the property or its purpose. The purchaser is not entitled to any payment for loss or profit or any other money damages–special, direct, indirect, or consequential.

. . . .

If items have been awarded but paid for and the successful bidder feels that the property is mis-described, he/she must follow these procedures. A written claim needs to be submitted to the Sales Contracting Officer within 15 calendar days from the date of award requesting release of contractual obligation for reasons satisfying that of a mis-description. No verbal contact with the custodian or the Sales Contracting Officer or any other federal official will constitute a notice of mis-description.

When items are awarded and payment has been received, regardless of the removal status (removal may or may not have occurred), the successful bidder must submit a written notice to the Sales Contracting Officer within 15 calendar days from the date of payment e-mail (the Purchaser’s Receipt). If property has been removed and the claim is accepted by the Sales Contracting Officer, the purchaser must maintain the property in its purchased condition and return it at their expense to the location designated by the Sales Contracting Officer of their designated official.

BTS accepted those terms and conditions.

On July 8, 2021, GSA accepted BTS’ bid in the amount of $50,010, and awarded contract number GS09F21FBE7785 (contract) to BTS. GSA further advised BTS that payment was due within two days. On July 13, 2021, GSA informed BTS that it was in default for failure to make payment, and GSA directed BTS to make payment within two days. Exhibit 6. BTS submitted payment for the loader on July 14, 2021.

In an email dated August 5, 2021, BTS advised GSA of the following: I would like to submit a claim on this front end wheel loader.

. . . .

The main loader scoop bucket which is a 4&1 bucket has a very large bow and bend in it and it doesn’t close appropriately as it should.

The other deficiency is that upon starting it up on the truck to back it off; none of the gauges are working and it is not shifting out of first gear. The loader does run and drive, but there is not a single working gauge currently.

BTS acknowledged that it failed to inspect the loader before purchasing it. Finally, BTS requested “a discount of $8500 for the bucket and $2000 for the instrument cluster problem.” On October 1, 2021, the contracting officer (CO) denied BTS’ claim. The CO noted that BTS had no remedy under the contract because the loader was sold “as is” and BTS had failed to inspect the loader before purchasing it. BTS subsequently appealed the CO’s decision.

Discussion

The issue before the Board is whether GSA has established grounds for summary judgment. The Board’s authority is pursuant to the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101–7109 (2018). In ruling upon a motion for summary judgment, the Board recognizes the following:

Summary judgment is only appropriate where there is no genuine issue of material fact. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986).

“Only disputes over facts that might affect the outcome of the suit under the governing law will properly preclude the entry of summary judgment.” Id. It is not the judge’s function “to weigh the evidence and determine the truth of the matter.” Id. at 249. All justifiable inferences and presumptions are to be resolved in favor of the nonmoving party. Id. at 255.

The moving party has the initial responsibility of stating the basis for its motion and “identifying those portions of ‘the pleadings, depositions, answers to interrogatories, and admissions on file, together with affidavits, if any,’ which it believes demonstrate the absence of a genuine issue of material fact.” Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). “‘[A]llegations without support are not evidence.’” McAllen Hospitals LP v. Department of Veterans Affairs, CBCA 2774, et al., 14-1 BCA ¶ 35,758, at 174,970 (quoting Max Castle, AGBCA 97-128-1, 97-1 BCA ¶ 28,833, at 143,845).

Optimum Services, Inc. v. Department of the Interior, CBCA 4968, 19-1 BCA ¶ 37,383, aff’d, Optimum Services, Inc. v. Secretary of the Interior, 829 F. App’x 527 (Fed. Cir. 2020) (table).

GSA contends that BTS’ notice of misdescription was not submitted within the fifteen-day period after award as required under the terms and conditions of the contract. The Board has recognized that “the failure to submit a claim within the requisite time-frame of fifteen days defeats any claim a purchaser might otherwise have under the Description Warranty clause.” Stephen D. Bradley v. General Services Administration, CBCA 5040, 16-1 BCA ¶ 36,327 (quoting Joseph M. Hutchison v. General Services Administration, CBCA 725, 08-1 BCA ¶ 33,804). GSA awarded the contract on July 8, 2021, but BTS did not submit any notice regarding the loader until August 5, 2021, which was more than fifteen days after award.

BTS contends that circumstances beyond its control, which were the result of the pandemic, prevented it from filing timely notice. The Board finds no merit in that assertion as there is no contract provision that excuses failure to comply with its terms. Additionally, BTS also delayed payment until July 14, 2021, which, due to its own fault, further limited its time in which to file its notice.

Even if the Board were to find that BTS submitted a timely misdescription claim, there is no evidence that GSA misdescribed the loader, and, consequently, BTS has no recourse under the warranty provision of the contract. The Board has recognized the following:

The terms and conditions do warrant “that the property listed in the GSAAuctions.gov website will conform to its description.” The description on the website may have been incomplete, but it was not a misdescription. A misdescription is an inaccurate—meaning an erroneous or wrong—description of something with which the describer is familiar. Webster’s Third New International Dictionary 1143 (“misdescribe,” “misdescription”) (1986); see also id. 1139 (“inaccurate”), 2642 (“wrongly”).

Randy Preston v. General Services Administration, CBCA 1465, 10-1 BCA ¶ 34,317 (2009) (quoting Larry J. McKinney v. General Services Administration, GSBCA 16720, 05-2 BCA ¶ 33,119, at 164,128). It is also well established that “to the extent deficiencies could reasonably have been discerned during an in-person inspection, the purchaser cannot establish a misdescription.” Id. (quoting Fred M. Lyda v. General Services Administration, CBCA 493, 07-2 BCA ¶ 33,631, at 166,572). In Preston, the Board held that appellant had failed to show a misdescription of the paddle boats that he had purchased at a GSA auction where the damage to the boats could have been determined by inspection before bidding. Id. GSA properly described the loader, which was a 2006 John Deere 544J Wheeled Loader, and BTS has not denied that it purchased such a piece of equipment. Instead, BTS has cited issues related to its condition, which included the scoop bucket, gear shift, and gauges. All of those issues could have been discovered upon inspection of the loader, but BTS failed to do so.

BTS has also suggested that government personnel were aware of the condition of the loader. Even if BTS is correct in its allegation, it is of no avail because the terms and conditions of the contract, and not the knowledge of government personnel, determined BTS’ rights under its contract with GSA. Those terms and conditions were explicit and blunt in advising prospective bidders “that gross omissions regarding the functionality of items, failures to cite major missing parts and/or restrictions with regards to usage may occur.” Finally, BTS in its claim seeks a reduced price for the loader, $10,500, which is not an available remedy under the contract. The terms and conditions of the contract did not include “any payment for loss or profit or any other money damages–special, direct, indirect, or consequential.” At most, BTS has only alleged a hypothetical reduction in the value of the loader, which is not recoverable under the terms and conditions of the contract.

Decision

The motion for summary judgment is granted. The appeal is DENIED.

H. Chuck Kullberg

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Badland Truck Sales, Inc., CBCA 7281. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.