CBCA 7597

Alares Construction, Inc.

Mar 3, 2023Judge DrummondDEPARTMENT OF VETERANS AFFAIRS
DecisionRuled on a motion

Key Facts

Appellant
Alares Construction, Inc.
Respondent agency
DEPARTMENT OF VETERANS AFFAIRS
Judge
Drummond
Case number
CBCA 7597
Decided
Mar 3, 2023The decision states Mar 3, 2023 on its own face, which agrees with the listing.
Decision type
Decision
Law firm for the appellant
Bradley Arant Boult Cummings LLP
Outcome
Ruled on a motion
The VA's motion to dismiss for lack of jurisdiction and alternative motion for summary judgment are DENIED.
Read from the shouted disposition line the Board prints above this decision's own date, and quoted from its operative sentence above. No model is involved.

Topics

Jurisdiction and timelinessChanges and equitable adjustmentDiffering site conditions

Topics are derived from each decision's own text by keyword rules, not a classification by the Board. A decision matching several topics carries all of them, so topic counts sum above the number of decisions. They are ordered strongest first.

Appearances

For the appellant
Douglas L. Patin and Lee-Ann Brown
Bradley Arant Boult Cummings LLP
Washington, DC
For the respondent
Jennifer L. Hedge
Office of General Counsel, Department of Veterans Affairs
Pittsburgh, PA
For the respondent
Kathleen Ramos
Office of General Counsel, Department of Veterans Affairs
Arlington, TX
Decision PDF (cbca.gov) Civilian Board of Contract Appeals, Contract Disputes Act casesThe Board's year listing this row was read fromThe decision document is hosted by the Board itself, so it is an official copy, and the Board's own Contract Disputes Act case listing is the citable source. The topics, the disposition and the appearances above are read deterministically from the decision's own words; no model is involved.

Research This Decision

Create a free account to open this decision in the CBCA workspace: a grounded decision brief drafted from the Board's own words, the Insights dashboard over the whole corpus, and the filtered browser.

CBCA Decision Brief

A Workflows Hub brief on this decision, drafted from the captured text with every quote and authority checked against it.

Insights

Who prevails before the Board, by topic and by judge, with every denominator visible: merits rulings, not decisions.

Browse with Filters

The whole corpus by year, decision type, topic, judge and disposition, searchable across the decisions' own text.

Full Decision

Full text of the decision4 pages, 8,269 characters, read from the Board's own documentDecided Mar 3, 2023 on its own faceRespondent DEPARTMENT OF VETERANS AFFAIRS Decision documentOfficial source: Civilian Board of Contract Appeals, Contract Disputes Act cases

Authorities cited

3 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Federal Acquisition Regulation1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

MOTIONS TO DISMISS FOR LACK OF JURISDICTION AND

FOR SUMMARY JUDGMENT DENIED: March 3, 2023

CBCA 7597

ALARES CONSTRUCTION, INC.,

Appellant,

v.

DEPARTMENT OF VETERANS AFFAIRS,

Respondent.

Douglas L. Patin and Lee-Ann Brown of Bradley Arant Boult Cummings LLP,

Washington, DC, counsel for Appellant.

The case caption as the decision prints it. Every word is kept; the rule the Board draws around it is not text, so it is not repeated here.

Jennifer L. Hedge, Office of General Counsel, Department of Veterans Affairs, Pittsburgh, PA; and Kathleen Ramos, Office of General Counsel, Department of Veterans Affairs, Arlington, TX, counsel for Respondent.

Before Board Judges RUSSELL, DRUMMOND, and ZISCHKAU.

DRUMMOND, Board Judge.

Respondent, the Department of Veterans Affairs (VA), filed a motion to dismiss for lack of jurisdiction or, alternatively, a motion for summary judgment. The VA alleges the Board lacks jurisdiction to decide the claim because the claim lacks a sum certain and because appellant, Alares Construction, Inc. (Alares), released its claim when it signed its final release of claims. We find that there is a sum certain stated in the claim and that there remains an issue of material fact as to whether appellant released its claim when it signed its final release of claims.

Procedural Background

Alares was awarded contract VA241-16-C-0037 (the contract) by the VA in April 2016. The contract required Alares to relocate the Intensive Care Unit at the Providence VA Medical Center. Appeal File (CBCA 6149, et al.), Exhibit 1.1 In CBCA 6149, et al., Alares filed a “claim supplement” or “claim addendum” in which “Alares added facts, allegations, and new legal theories.” Complaint (CBCA 7597) at 15-16. The Board refused to add the addendum to the claim in that consolidated appeal because it was a new claim, meaning it contained new legal theories which had not received a contracting officer’s final decision. See Alares Construction, Inc. v. Department of Veterans Affairs, CBCA 6149, et al., 22-1 BCA ¶ 38,225. Alares responded by voluntarily dismissing three claims—CBCA 6396, 7082, and 7083—and presenting a claim addendum to the contracting officer. See Appellant’s Voluntary Motion to Dismiss (CBCA 6149, et al.); Appeal File (CBCA 7597), Exhibit 27. The contracting officer subsequently denied the claim addendum. See Appeal File (CBCA 7597), Exhibit 28. Alares promptly appealed that denial to the Board, which was docketed as CBCA 7597.

Sum Certain

The VA argues that the Board does not have jurisdiction because (1) Alares failed to submit a claim that includes a valid sum certain, (2) the submission included two other amounts previously certified as a sum certain, and (3) the present claim duplicates many of the facts and issues presented in CBCA 6149, et al. Under the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109 (2018), there must be both a valid claim and a contracting officer’s final decision on that claim in order for the Board to hear an appeal and to proceed to the merits of the case. Sage Acquisitions, LLC v. Department of Housing & Urban Development, CBCA 6631, 22-1 BCA ¶ 38,031, at 184,693 (2021).

A claim is not defined in the CDA, but the Board has adopted the definition located in the Federal Acquisition Regulation (FAR). See Sage Acquisitions, 22-1 BCA at 184,693 (citing 48 CFR 2.101 (2021) (FAR 2.101)). The FAR definition of a claim requires, among other things, “a sum certain.” FAR 2.101. “[T]he sum certain requirement demands a fixed amount be stated in the claim.” Sage Acquisitions, 22-1 BCA at 184,694 (quoting ARI University Heights, LP v. General Services Administration, CBCA 4660, 15-1 BCA ¶ 36,085 at 176,186).

1Multiple appeals concerning this contract are pending before the Board. For clarity, all citations to the record reference the applicable CBCA docket number.

The VA cites to Sage Acquisitions as a similar case to the present but misconstrues the Board’s holding. In Sage Acquisitions, the Board dismissed the case for lack of jurisdiction because the number held out to be a sum certain was not anywhere in the documentation. It was instead the sum of two separate numbers, one of which was an estimate, and thus the total was not a sum certain. Sage Acquisitions, 22-1 BCA at 184,695. Here, Alares stated in its claim a fixed number as its sum certain—$1,679,495.60. Appeal File (CBCA 7597), Exhibit 27 at 1, 47.

The VA correctly asserts that Alares also included the claim addendum and Capital Project Management, Inc. report as attachments to its claim in CBCA 6149, et al. It is also accurate that those documents had calculations that listed a sum certain of $1,657,353.24 and $1,673,926.77. However, a plain reading of the claim shows that Alares included the claim addendum and rebuttal report for the facts and information enclosed within, not as a demonstration of the sum certain. Alares explicitly stated in its letter to the contracting officer that Alares “rel[ies] upon the information enclosed within the [claim] addendum” but that “Exhibit 2 to this letter revises slightly the amount claimed to $1,679,495.60.” Appeal File (CBCA 7597), Exhibit 27 at 1.

The VA is also correct that this claim duplicates many of the facts and issues present in CBCA 6149, et al., as Alares itself states that the claim addendum “added facts, allegations, and new legal theories” to the extended general conditions claim (the basis of CBCA 6149). Complaint (CBCA 7597) at 15-16. This claim also acts, therefore, to cure the jurisdictional issues that were present in the claim addendum when it was filed as part of CBCA 6149, et al. We conclude that there is a claim with a sum certain stated in the amount of $1,679,495.60, and that the VA’s motion to dismiss for lack of jurisdiction is denied. Final Release of Claims

The VA also moved for summary judgment. The VA alleges that by signing the final release of claims, Alares is precluded from bringing this claim. To succeed on a motion for summary judgment, there must be no material facts in dispute, and the moving party must prove it is entitled to judgment as a matter of law. Grand Strategy, LLC v. Department of Veterans Affairs, CBCA 6795, 21-1 BCA ¶ 37,895, at 184,039. “A material fact is one that will affect the outcome of the case. . . . [A]ll reasonable inferences and presumptions are resolved in favor of the non-moving party.” Id.

On October 29, 2019, Alares signed a final release of claims, discharging the Government from all liabilities under the contract, except for twenty-nine specified requests for equitable adjustment (REAs). Appeal File (CBCA 6149, et al.), Exhibit 81. Included within those twenty-nine REAs is REA 20, extended general conditions. REA 20 was converted to the claim that is at issue in CBCA 6149.

The first version of REA 20 was submitted on May 23, 2019, before the final release of claims. It requested an equitable adjustment due to alleged government delays and differing site conditions that led to increases in the cost of the project. See Appeal File (CBCA 6149, et al.), Respondent’s Response to Appellant’s Second Addendum, Exhibit A. In REA 20, Alares included broad language that preserved its rights to seek costs for other impacts on the schedule or time-related extended performance costs: In accordance with VAAR [Veterans Affairs Acquisition Regulation] 852.228-70 and VAAR 852.236-88 Alares Construction, Inc. reserves its rights to receive a bond premium adjustment at the time of final settlement under this contract for Alares Construction, Inc. and its subcontractors[’] increased Bond Premiums. Alares Construction, Inc. reserves it’s [sic] rights to additional costs for impact of this change, alone or in combination with other changes, on unchanged work; for additional time, due to impacts, if any, on the schedule; and for time-related extended time of performance costs, all of which will be evaluated separately.

Id. at 5 (emphasis added). The broad nature of this language presents some doubt as to the material fact of whether appellant’s claim addendum is barred by the final release of claims. Thus, summary judgment is not appropriate.

Decision

The VA’s motion to dismiss for lack of jurisdiction and alternative motion for summary judgment are DENIED.

Jerome M. Drummond

Board Judge

We concur:

Beverly M. Russell

Board Judge

Jonathan D. Zischkau

Board Judge

This is a verbatim capture of the text layer of the Board's own document in Alares Construction, Inc., CBCA 7597. Nothing is summarized or reworded, and the sections run in the order the Board wrote them. What the page shows and the text does not repeat is the pagination furniture: the page numbers and the rules the Board draws around its caption and under its signatures. The signatures are set back into the columns the Board prints them in, each judge under the name he or she signed, and the typed copy of that name the page carries beneath each signature is not repeated.

Related Decisions

Same Judge

Same Topic

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.