B-402800.2

Metasoft, LLC

Feb 17, 2011.NavySmall Business Administration
DeniedReconsiderationSet-Aside / Small BusinessSmall Business

A request to reconsider an earlier decision, not a new protest.

GAO Digest

Metasoft, LLC, of San Diego, California requests that we reconsider our July 23, 2010, decision denying its protest of the terms of request for proposals (RFP) No. N66001-10-R-0057, issued by the Department of the Navy for support services, including software maintenance and upgrades. Metasoft argued that the solicitation should have been set aside for small businesses. We deny the request for reconsideration.

Key Facts

Decision date
Feb 17, 2011.
Publicly released
Feb 17, 2011.
Agency
Navy
Department
Small Business Administration
Decided by
Lynn H. Gibson, General Counsel

Counsel

Protester
Cohen Mohr LLP
Andrew Mohr
Agency
Department of the Navy
Sandra Cain
GAO
Office of the General Counsel, GAO
Cherie J. Owen, Sharon Larkin

Procurement

Solicitation
N66001-10-R-0057 (RFP)
Issued by
Department of the Navy
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision7,644 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Cases cited

4 cases this decision cites, in the order it first names them. 1 of them opens in this app; the rest are shown without a link because no published copy of them was confirmed.

B-257634.4B'402490B-402490.2University Research Co., LLCB-294358.8B'298288B-298164.2

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

Metasoft, LLC, of San Diego, California requests that we reconsider our July 23, 2010, decision denying its protest of the terms of request for proposals (RFP) No. N66001-10-R-0057, issued by the Department of the Navy for support services, including software maintenance and upgrades. Metasoft argued that the solicitation should have been set aside for small businesses.

Decision

Matter of: Metasoft, LLC--Reconsideration

File: B-402800.2

Date: February 17, 2011

Andrew Mohr, Esq., Cohen Mohr LLP, for the protester.

Sandra Cain, Esq., Department of the Navy, for the agency.

Cherie J. Owen, Esq., and Sharon Larkin, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Our Office will dismiss a protester's piecemeal presentation of arguments that could have been raised earlier in the protest process.

DECISION

Metasoft, LLC, of San Diego, California requests that we reconsider our July 23, 2010, decision denying its protest of the terms of request for proposals (RFP) No. N66001-10-R-0057, issued by the Department of the Navy for support services, including software maintenance and upgrades. Metasoft argued that the solicitation should have been set aside for small businesses.

We deny the request for reconsideration.

Prior to issuing the RFP, the agency issued a sources sought notice to identify qualified small businesses interested in competing for the requirement. Eight firms--five small and three large--submitted responses to the notice. The agency evaluated the responses and determined that each of the large firms was capable of providing the services sought, but that none of the small firms were capable of providing at least 50 percent of the services themselves. Because the agency did not expect to receive offers from at least two capable small businesses, the contracting officer recommended that the acquisition be conducted as a full and open competition. The agency's small business specialist and the local district office of the Small Business Administration concurred in the recommendation. Therefore, the agency issued the RFP on April 26, 2010 on an unrestricted basis.

In its protest filed with our office on April 30, Metasoft raised a number of arguments that it claimed supported its position that the RFP should be set aside for small businesses. One of the protester's arguments was that the agency evaluated responses to the sources sought notice on the basis of overstated technical requirements not included in the RFP itself. Comments at 22-27. This argument first appeared in the protester's June 7 comments on the agency report. Id.

We denied the protest, finding that the record supported the agency's determination that it could not expect to receive offers from at least two responsible small businesses capable of providing at least 50 percent of the services. Metasoft, LLC, B'402800, July 23, 2010, 2010 CPD para. 170 at 4. We declined to address the protester's argument that the agency overstated its technical requirements, finding the argument to be untimely. Id. at 3. In our decision, we stated that the argument was untimely because it was based on information furnished to the protester on April 9 and on the contents of the RFP released on April 26 and amended on May 20 and May 25; yet the protest argument was not raised until June 7 in the protester's comments on the agency report. Id. at 3-4.

Metasoft has requested that we reconsider our decision. It maintains that GAO erred when it determined that its argument regarding overstated technical requirements was untimely. Request at 1-2. Metasoft also contends that GAO erred in failing to address an argument raised in the protester's supplemental comments that the independent verification and validation test task order portion of the RFP could be severed and set aside for small businesses. Id. at 4-5. In addition, Metasoft argues that GAO made an error of fact in its statement that no other small businesses had contested the agency's conclusions. Id. at 3-4.

To prevail on a request for reconsideration, the requesting party must either show that our decision contains an error of fact or law, or present information not previously considered that warrants the decision's reversal or modification. 4 C.F.R. sect. 21.14(a) (2010). A request for reconsideration that reiterates arguments made previously and merely expresses disagreement with the prior decision does not meet the standard for granting reconsideration. Gordon R. Fishman--Recon., B-257634.4, Sept. 9, 1996, 1996 CPD para. 110 at 2-3. Here, we conclude that the standard for reconsideration has not been satisfied.

The protester contends that GAO erred in rejecting as untimely an argument that the protester raised for the first time on June 7--over a month after its initial protest filing. In challenging our decision, the protester argues that our Bid Protest Regulations provide for the dismissal of untimely bases of protest, not untimely arguments. Essentially, the protester contends that so long as a protester files a timely protest containing a broad basis of protest in its initial filing, it may supply the specific facts and arguments in support of that basis of protest at any time during the protest process.

We find that the rejection of the protester's argument was proper. Our Bid Protest Regulations do not contemplate the piecemeal presentation or development of protest issues through later submissions citing examples or providing alternate or more specific legal arguments missing from earlier general allegations of impropriety. CapRock Gov't Solutions, Inc.; ARTEL, Inc.; Segovia, Inc., B'402490, B-402490.2, et al., May 11, 2010, 2010 CPD para. 124 at 24. University Research Co., LLC, B-294358.8 et al., Apr. 6, 2006, 2006 CPD para. 66 at 16. Our Office will dismiss a protester's piecemeal presentation of arguments that could have been raised earlier in the protest process. Alfa Consult S.A., B'298288, B-298164.2, Aug. 3, 2006, 2006 CPD para. 127 at 3. Because the protester did not present its argument earlier in the protest process, even though it could have done so, the protester's argument was properly rejected as untimely.

Similarly, Metasoft's argument regarding the severability of the independent verification and validation test task order is also untimely. This argument appeared for the first time in the protester's supplemental comments, filed on June 21, which was 52 days after the initial protest filing. Supplemental Comments at 6. This argument is based on information contained in the RFP and a GAO report issued in 2009. Therefore, because the protester did not present this argument earlier in the protest process, even though it could have done so, the argument was untimely.

The protester also contends that GAO made an error of fact in a footnoted statement that "[n]one of the other small businesses has contested the agency's technical evaluation or the issuance of the RFP on an unrestricted basis." Metasoft, LLC, supra, at 3 n.4. The protester contends that this statement is incorrect because two other small businesses filed declarations in support of, and attached to, Metasoft's protest comments. Request at 3.

We find that the statement in our decision was correct. While it is true that two other small businesses filed declarations in support of Metasoft's comments, the fact remains that no small businesses, other than Metasoft, protested these issues.

The request for reconsideration is denied.

Lynn H. Gibson

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Protest Ground

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.