B-403475.2

Tiger Enterprises, Inc.

Feb 15, 2011.ArmySmall Business Administration
DeniedDiscussions / Competitive RangeSet-Aside / Small BusinessSmall Business

GAO Digest

Tiger Enterprises, Inc., protests its elimination from the competitive range under request for proposals (RFP) No. W91247-10-R-0017, a small business set-aside issued by the Department of the Army for the lease of washers and dryers. We deny the protest.

Key Facts

Decision date
Feb 15, 2011.
Publicly released
Feb 15, 2011.
Agency
Army
Department
Small Business Administration
Decided by
Lynn H. Gibson, General Counsel

Counsel

Protester
Lillian K. Mauldin
Intervenor
McCarthy, Sweeney & Harkaway, P.C
Richard D. Lieberman, Garry S. Grossman, Gabriel D. Soll
Agency
Department of the Army
GAO
Office of the General Counsel, GAO
Eric M. Ransom, Edward T. Goldstein

Procurement

Solicitation
W91247-10-R-0017 (RFP)
Instrument
Contract
Issued by
Department of the Army
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision6,160 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Cases cited

2 cases this decision cites, in the order it first names them. No published copy of any of them was confirmed, so each is shown without a link.

Grove Resource Solutions, Inc.B-296228B-296228B-296228.2

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

Tiger Enterprises, Inc., protests its elimination from the competitive range under request for proposals (RFP) No. W91247-10-R-0017, a small business set-aside issued by the Department of the Army for the lease of washers and dryers.

Decision

Matter of: Tiger Enterprises, Inc.

File: B-403475.2

Date: February 15, 2011

Lillian K. Mauldin, for the protester.

Richard D. Lieberman, Esq., Garry S. Grossman, Esq., and Gabriel D. Soll, Esq., McCarthy, Sweeney & Harkaway, P.C., for the intervenor.

CPT Tudo Pham, Department of the Army, for the agency.

Eric M. Ransom, Esq., and Edward T. Goldstein, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Protest that agency improperly excluded protester from the competitive range is denied where record shows that evaluation was reasonable and consistent with the solicitation's evaluation criteria.

DECISION

Tiger Enterprises, Inc., protests its elimination from the competitive range under request for proposals (RFP) No. W91247-10-R-0017, a small business set-aside issued by the Department of the Army for the lease of washers and dryers.

We deny the protest.

The Army Mission & Installation Contracting Command issued the RFP on June 30, 2010, for the purpose of awarding a requirements contract for the lease of washers and dryers at Fort Bragg, Simmons Army Airfield, and Camp Mackall, North Carolina. The RFP contemplated a best value source selection considering past performance and price, with past performance being more important than price. The RFP stated that past performance would be rated on an adjectival scale of excellent, good, adequate, marginal, poor, and neutral. The RFP also advised that price would not be assigned an adjectival rating, but that "unreasonably high or unrealistically low proposed prices may be grounds for eliminating a proposal from the competitive range." RFP at 59.

The Army received a total of six proposals in response to the RFP, including the proposal submitted by Tiger. After an initial evaluation, the Army determined that discussions were necessary and established a competitive range consisting of the two most highly rated proposals. Tiger's proposal, rated excellent under the past performance factor with a price of $6,330,576, was not among the two most highly rated proposals as determined by the agency. Tiger received a letter from the contracting officer on Novermber 3, which stated that Tiger's proposal was not selected for the competitive range, and that the determination was "based primarily on [Tiger's] Price." Competitive Range Letter, at 1. This protest followed.

Tiger asserts that because it received the highest possible rating under the past performance factor, the only permissible basis in the RFP for excluding its proposal from the competitive range would be a determination that its price was unreasonably high or unrealistically low. Tiger argues that, because the November 3 competitive range letter did not indicate that Tiger's price was unreasonably high or unrealistically low, the Army did not make such a determination, and therefore had no basis to exclude Tiger from the competition.

Tiger also alleges that the awardee is not a small business, and is therefore not eligible to receive the award. The Small Business Act, 15 U.S.C. sect. 637(b)(6), gives the Small Business Administration (SBA), not our Office, the conclusive authority to determine matters of small business size status for federal procurements. Bid Protest Regulations, 4 C.F.R. sect. 21.5(b)(1) (2010); Randolph Eng'g Sunglasses, B'280270, Aug. 10, 1998, 98'2 CPD para. 39 at 3. We therefore will not review a protester's challenge to another company's size status, nor will we review a decision by the SBA that a company is, or is not, a small business for purposes of federal procurements. Randolph Eng'g Sunglasses, supra.

The determination of whether a proposal is in the competitive range is principally a matter within the judgment of the procuring agency. Dismas Charities, Inc., B'284754, May 22, 2000, 2000 CPD para. 84 at 3. We will review that judgment--and the evaluation judgments on which it was based--only to ensure that it was reasonable and in accord with the solicitation and applicable statutes and regulations. Grove Resource Solutions, Inc., B-296228, B-296228.2, July 1, 2005, 2005 CPD para. 133 at 4. Here, the agency's determination was reasonable and in accordance with the RFP.

The record confirms that the Army excluded Tiger from the competitive range based on its conclusion that Tiger's price was unreasonable. In this regard, the Army's basis for excluding Tiger from the competitive range is documented in the agency's competitive range determination, dated October 26, and included in the record as Agency Report (AR) Tab 8. The determination shows that, of the four offerors excluded from the competitive range, two were excluded on the basis of their past performance rating and unreasonably high price, and two, including Tiger, were excluded on the basis of unreasonably high price alone. With regard to Tiger specifically, the competitive range determination stated:

[Tiger's] proposal is excluded from the competitive range because their price was unreasonably high when compared to other offerors with the same past performance rating of Excellent. There were no deficiencies or weaknesses noted. Also when compared to other offerors price with the same rating, [Tiger's] price was 100.8% higher.

AR, Tab 8, Competitive Range Determination, at 2.

As noted, the RFP stated that "unreasonably high or unrealistically low proposed prices may be grounds for eliminating a proposal from the competitive range." RFP at 59. Where, as here, the protester's price was more than twice as much as the price offered by an equally-rated, lower cost offeror, there is no basis to question the Army's determination that Tiger's price was unreasonably high, or its decision to exclude Tiger from the competitive range.

The protest is denied.

Lynn H. Gibson

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Protest Ground

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.