GAO Digest

Livanta, LLC, of Annapolis Junction, Maryland, requests that we recommend that the firm be reimbursed the costs of filing and pursuing its protest of the award of a contract under request for proposals (RFP) No. RFP-CMS-2010-0036, issued by the Centers for Medicare and Medicaid Services (CMS) for a payment error rate measurement contract. We deny the request.

Key Facts

Decision date
Apr 5, 2011.
Publicly released
Apr 5, 2011.
Agency
Centers for Medicare & Medicaid Services
Department
Department of Health and Human Services
Decided by
Lynn H. Gibson, General Counsel

Counsel

Protester
PilieroMazza PLLC
Jonathan T. Williams, Kelly E. Buroker, Devon E. Hewitt
Agency
Centers for Medicare and Medicaid Services
Christine Simpson
GAO
Office of the General Counsel, GAO
Kenneth Kilgour, Edward T. Goldstein

Procurement

Solicitation
RFP-CMS-2010-0036 (RFP)
Instrument
Contract
Issued by
Centers
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision7,209 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

Competition in Contracting Act1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

2 cases this decision cites, in the order it first names them. No published copy of any of them was confirmed, so each is shown without a link.

Inc.--CostsB-255078.3Carlson Wagonlit Travel--Request for Declaration of Entitlement to CostsB-266337.3

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

Livanta, LLC, of Annapolis Junction, Maryland, requests that we recommend that the firm be reimbursed the costs of filing and pursuing its protest of the award of a contract under request for proposals (RFP) No. RFP-CMS-2010-0036, issued by the Centers for Medicare and Medicaid Services (CMS) for a payment error rate measurement contract.

Decision

Matter of: Livanta, LLC-Costs

File: B-404215.2

Date: April 5, 2011

Jonathan T. Williams, Esq., Kelly E. Buroker, Esq., and Devon E. Hewitt, Esq., PilieroMazza PLLC, for the protester.

Christine Simpson, Esq., Centers for Medicare and Medicaid Services, for the agency.

Kenneth Kilgour, Esq., and Edward T. Goldstein, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Request that GAO recommend the reimbursement of costs of filing and pursuing a protest is denied where the agency took corrective action prior to the due date for the agency report, even though it produced relevant documents prior to that date.

DECISION

Livanta, LLC, of Annapolis Junction, Maryland, requests that we recommend that the firm be reimbursed the costs of filing and pursuing its protest of the award of a contract under request for proposals (RFP) No. RFP-CMS-2010-0036, issued by the Centers for Medicare and Medicaid Services (CMS) for a payment error rate measurement contract.

We deny the request.

Livanta filed its protest on October 12, 2010, and the due date for the agency report was November 12. The protest included the following three allegations: (1) the agency improperly evaluated the technical proposals, Protest at 12-18; (2) the agency's price evaluation was flawed, Protest at 18-19; and (3) the awardee had an unmitigable organizational conflict of interest. Protest at 7-12. Less than 2 weeks later, on October 25, the agency filed a request for partial summary dismissal, which was promptly granted. On November 1, the agency submitted an advance document production consisting of relevant documents pertaining to the remaining protest issues. No contracting officer's statement or legal memorandum responding to the protester's arguments or defending the agency's actions were provided at that time.

On November 3, based on a review of the early documents provided by the agency, Livanta requested an immediate outcome prediction alternative dispute resolution (ADR) teleconference, and the GAO attorney conducted an ADR teleconference the following day. During the ADR teleconference, the GAO attorney questioned whether the agency had properly evaluated the awardee's compliance with certain requirements of the RFP and advised the agency of the specific documents it would need to provide in the agency report in order to avoid a sustain of the protest. On November 9, 3 days before the due date for the agency report, CMS advised our Office that it would take corrective action to resolve the protest. We dismissed the protest as academic and Livanta filed its request for entitlement to its protest costs, arguing that the agency unduly delayed taking corrective action in response to a clearly meritorious protest. Request at 1.

Under the Competition in Contracting Act of 1984, our Office may recommend that protest costs be reimbursed only where we find that an agency's action violated a procurement statute or regulation. 31 U.S.C. sect. 3554(c)(1) (2010). Our Bid Protest Regulations provide that, where the contracting agency decides to take corrective action in response to a protest, we may recommend that the protester be reimbursed the costs of filing and pursuing its protest, including reasonable attorneys' fees. 4 C.F.R. sect. 21.8(e) (2010). This does not mean that costs should be reimbursed in every case in which an agency decides to take corrective action; rather, a protester should be reimbursed its costs where an agency unduly delayed its decision to take corrective action in the face of a clearly meritorious protest. Griner's-A-One Pipeline Servs., Inc.--Costs, B-255078.3, July 22, 1994, 94-2 CPD para. 41 at 5.

The protester recognizes that, as a general matter, when an agency takes corrective action before the due date set for receipt of the agency report, our Office views such action as prompt and will not recommend the reimbursement of costs, even where the protest is clearly meritorious. The Sandi-Sterling Consortium--Costs, B'296246.2, Sept. 20, 2005, 2005 CPD para. 173 at 2-3. Livanta argues, however, that this general rule should not apply here given the agency's active defense of the protest, which included the filing of a request for partial dismissal and the early submission of documents, which caused Livanta to incur significant costs that would have been unnecessary if the agency "had promptly and reasonably investigated the matter." Request at 2.

With regard to the agency's dismissal request, an agency's pursuit of a reasonable procedural litigation strategy before our Office does not constitute undue delay in taking corrective action. Carlson Wagonlit Travel--Request for Declaration of Entitlement to Costs, B-266337.3 et al., July 3, 1996, 96-2 CPD para. 99 at 4. A contracting agency, in defending protests filed with our Office, should be permitted to vigorously assert procedural and substantive defenses in good faith without having to risk the assessment of costs. Id. This is especially true where, as here, our Office granted the agency's motion for partial dismissal. See id. There is simply no basis to assert that the agency's good faith, successful efforts to narrow the scope of the protest should result in a recommendation that it pay the protester's costs, where the agency took corrective action prior to the due date for the agency report.

Moreover, we conclude that the agency's corrective action was prompt, notwithstanding the fact that the agency produced relevant documents in advance of the agency report due date, and thereby may have caused the protester to expend the time and expense in reviewing these documents. Early document production, which is something agencies provide voluntarily, facilitates the efficient resolution of protests since it allows for the early resolution of issues concerning the scope of the agency's document production in response to the protest and because it can lead to the identification of supplemental protest issues early in the protest process, thereby affording protesters and our Office greater flexibility in resolving such issues. Given these considerations, it would not be appropriate to penalize agencies, by subjecting them to the payment of protest costs, solely for utilizing this highly useful, but voluntary process. Thus, we find the agency's corrective action--initiated prior to the due date for the agency report--to have been prompt and to not warrant payment of protest costs.

Pursuant to our Bid Protest Regulations, our Office will, to the maximum extent practicable, resolve timely supplemental protest issues within the time limit established for decision on the initial protest. 4 C.F.R. sect. 21.9(c).

The request is denied.

Lynn H. Gibson

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.