B-404855.2

Odle Management Group, LLC

Mar 26, 2012.Department of LaborDepartment of Labor
GrantedCosts

A request that GAO recommend the protester recover its protest costs.

GAO Digest

Odle Management Group, LLC (OMG) requests that we recommend that it be reimbursed the costs associated with filing and pursuing its bid protest against the Department of Labor’s (DOL) award of a contract to CHP International under solicitation No. DOLJ10UA00032, for outreach and admissions, and career training services. We grant OMG’s request in part and deny it in part.

Key Facts

Decision date
Mar 26, 2012.
Publicly released
Mar 27, 2012.
Agency
Department of Labor
Department
Department of Labor
Decided by
Lynn H. Gibson, General Counsel

Counsel

Protester
Malyszek & Malyszek
Cynthia Malyszek
Agency
Department of Labor
Peter J. Dickson
GAO
Office of the General Counsel, GAO
Scott H. Riback, David A. Ashen

Procurement

Awardee
CHP International
Solicitation
DOLJ10UA00032
Instrument
Contract
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision7,326 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Authorities cited

1 authority read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

GAO Bid Protest Regulations1

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

7 cases this decision cites, in the order it first names them. 2 of them open in this app; the rest are shown without a link because no published copy of them was confirmed.

B-404855AAR Aircraft Servs.--CostsB-291670.6Inc.--CostsB-296699.3Inc.-Claim for Attorneys’ FeesB-225439.5Inc.--CostsB-289605.3Inc.--CostsB-404029.6Recreation Resource Mgmt. of America, Inc.B-406072

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

Odle Management Group, LLC (OMG) requests that we recommend that it be reimbursed the costs associated with filing and pursuing its bid protest against the Department of Labor’s (DOL) award of a contract to CHP International under solicitation No. DOLJ10UA00032, for outreach and admissions, and career training services.

We grant OMG’s request in part and deny it in part.

Decision

Matter of: Odle Management Group, LLC--Costs

File: B-404855.2

Date: March 26, 2012

Cynthia Malyszek, Esq., Malyszek & Malyszek, for the protester.

Peter J. Dickson, Esq., Department of Labor, for the agency.

Scott H. Riback, Esq., and David A. Ashen, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

DIGEST

1. GAO recommends reimbursement of the costs of filing and pursuing protest challenging the agency’s conduct of misleading discussions, where issue was clearly meritorious but agency unduly delayed taking corrective action.

2. Protest costs are not recommended with respect to issues concerning agency’s evaluation of proposals and source selection decision where such issues were readily severable from challenge to agency’s conduct of misleading discussions, the only issue found to be clearly meritorious at Government Accountability Office “outcome prediction” alternative dispute resolution conference.

DECISION

Odle Management Group, LLC (OMG) requests that we recommend that it be reimbursed the costs associated with filing and pursuing its bid protest against the Department of Labor’s (DOL) award of a contract to CHP International under solicitation No. DOLJ10UA00032, for outreach and admissions, and career training services.

In its initial submission, OMG also requested that we recommend that it be reimbursed its proposal preparation costs. The agency responded to OMG’s request and, in its subsequent submission to our Office, OMG made no further mention of its request for proposal costs. We consider this aspect of OMG’s request abandoned. Recreation Resource Mgmt. of America, Inc., B-406072, Feb. 1, 2012, 2012 CPD ¶ 60 at 6 n.3.

We grant OMG’s request in part and deny it in part.

OMG initially protested the agency’s award of a contract to CHP, arguing that the agency misevaluated proposals and made an unreasonable best value source selection decision. OMG also asserted that the agency misled it during discussions. Specifically, the agency advised OMG during discussions that its proposed staffing appeared to be high; in response to the agency’s discussion question, OMG lowered its proposed staffing, and the agency ultimately identified OMG’s proposed staffing as a weakness.

Subsequent to the development of the record, including the filing of an agency report and receipt of comments, our Office conducted an “outcome prediction” alternative dispute resolution (ADR) conference. In the course of that ADR, the cognizant Government Accountability Office (GAO) attorney advised the agency that GAO likely would sustain OMG’s protest on the basis that the agency had misled OMG during discussions. The GAO attorney recommended that the agency reopen discussions, obtain and evaluate revised proposals, and make a new source selection decision. Because our recommendation involved the agency reopening the acquisition, we did not reach the merits of OMG’s other issues.

In response to the ADR, DOL advised our Office that it intended to take corrective action. In particular, the agency advised that it would reopen discussions with the competitive range offerors, obtain and evaluate revised proposals and make a new source selection decision. Based on the agency’s proposed corrective action, we dismissed OMG’s protest as academic. B-404855, May 18, 2011.

In response to OMG’s request for reimbursement, DOL concedes that the protester is entitled to a recommendation that it be reimbursed its protest costs. Agency Report at 2. The agency argues, however, that OMG’s recovery should be limited to those costs that were incurred in connection with its allegation relating to misleading discussions. According to the agency, although we found this aspect of the protest to be clearly meritorious (as evidenced by the view expressed during the ADR), we did not find the remainder of OMG’s allegations clearly meritorious. The agency further maintains that the facts and legal theories underpinning OMG’s misleading discussions argument are distinct from the facts and legal theories underpinning the remainder of its protest, such that the costs incurred in connection with the former allegation are clearly severable from the costs incurred in connection with the latter allegations.

We agree with the agency that reimbursement of OMG’s protest costs should be confined to the costs incurred in connection with its misleading discussions issue. As noted by the agency, and as reflected in the views of the GAO attorney expressed during the ADR, the only protest issue that we found clearly meritorious was that of misleading discussions. Although as a general rule, we may recommend that a successful protester be reimbursed its incurred costs with respect to all issues pursued and not merely those upon which it prevails, AAR Aircraft Servs.--Costs, B-291670.6, May 12, 2003, 2003 CPD ¶ 100 at 9, in appropriate cases we have limited our recommendation for the award of protest costs where a part of those costs is allocable to an unsuccessful protest issue that is so clearly severable from the successful issues as to essentially constitute a separate protest. BAE Tech. Servs., Inc.--Costs, B-296699.3, Aug. 11, 2006, 2006 CPD ¶ 122 at 3; Interface Flooring Sys., Inc.-Claim for Attorneys’ Fees, B-225439.5, July 29, 1987, 87-2 CPD ¶ 106 at 2-3. In determining whether protest issues are so clearly severable as to essentially constitute separate protests, we consider, among other things, the extent to which the issues are interrelated or intertwined--i.e., the extent to which successful and unsuccessful arguments share a common core set of facts, are based on related legal theories, or are otherwise not readily severable. See Sodexho Mgmt., Inc.--Costs, B-289605.3, Aug. 6, 2003, 2003 CPD ¶ 136 at 29.

Here, OMG’s technical evaluation and source selection issues were not clearly intertwined with its misleading discussions issue. Whether the agency’s evaluation of proposals and source selection decision were reasonable concern legal theories and underlying facts that are distinct and severable from those relevant to OMG’s misleading discussions issue. Focused Mgmt., Inc.--Costs, B-404029.6, Oct. 3, 2011, 2011 CPD ¶ 204 at 4-5. Under these circumstances, we conclude that OMG’s reimbursement of protest costs should be limited to those costs incurred in connection with its misleading discussions protest basis.

RECOMMENDATION

We recommend that OMG be reimbursed the costs associated with filing and pursuing its protest on the issue of misleading discussions, including reasonable attorneys’ fees. OMG should submit its certified claim, detailing the time spent and costs incurred, directly to the agency within 60 days of its receipt of this decision. Bid Protest Regulations, 4 C.F.R. § 21.8(f)(1) (2011).

The request is granted in part and denied in part.

Lynn H. Gibson

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.