B-420698.2

RBVetCo, LLC d/b/a Rocky Bleier Construction Group

Jul 13, 2022.Department of Veterans AffairsDepartment of Veterans Affairs
DeniedCosts

A request that GAO recommend the protester recover its protest costs.

GAO Digest

RBVetCo, LLC d/b/a Rocky Bleier Construction Group, of Carnegie, Pennsylvania, requests that we recommend it be reimbursed the costs of filing and pursuing its protest challenging the award of a contract to PerformanceEPC, LLC, of Independence, Ohio, under solicitation No. 36C24421R0006, issued by the Department of Veterans Affairs (VA) for a boiler plant renovation project at the Lebanon VA Medical Center. In its protest, RBVetCo alleged the agency engaged in certain improper actions in connection with the award of the contract. We deny the request.

Key Facts

Decision date
Jul 13, 2022.
Publicly released
Jul 14, 2022.
Agency
Department of Veterans Affairs
Department
Department of Veterans Affairs
Decided by
Edda Emmanuelli Perez, General Counsel

Counsel

Protester
Burns White LLC
Agency
Department of Veterans Affairs
Steven E. Devine
GAO
Office of the General Counsel, GAO
Scott H. Riback, Tania Calhoun

Procurement

Awardee
PerformanceEPC, LLC
Solicitation
36C24421R0006
Instrument
Contract
View on GAO.gov Decision PDFThe outcome, grounds and appearances above are derived deterministically from GAO's published text. The decision on GAO.gov is the source of record.

Research This Decision

Create a free account to open this decision in the GAO Protest workspace: semantic search for similar protests, the citation graph, and the research agent over the whole corpus.

Similar Decisions

Protests that read like this one, ranked by the decision text across the whole corpus rather than by keyword.

Citation Graph

This decision's cited authorities, agency and related protests as an interactive knowledge graph.

Full Decision

Full text of the decision7,544 characters, captured from GAO's own published text Decision PDFOfficial source: GAO.gov

Authorities cited

2 authorities read from this decision's own text, grouped by the body of law each comes from. Select one to read it at its publisher.

GAO Bid Protest Regulations2

Read from the decision's own words with no model involved. Statutes, regulations, the acts these forums argue by name, and cases at the board, this office or the Comptroller General are recognized; any other citation form is left out rather than guessed at, so this is a floor on what the decision cites.

Cases cited

3 cases this decision cites, in the order it first names them. 2 of them open in this app; the rest are shown without a link because no published copy of them was confirmed.

Rocky Bleier Construction GroupB-420698MacroUSA Corp.-CostsB-408444.2Inc.-CostsB-412504.2

Read from the decision's own words with no model involved: the party names and the citation are as the decision prints them. A case named without a citation of any kind carries nothing to read, so it is left out rather than guessed at, and this is a floor on what the decision cites.

Highlights

RBVetCo, LLC d/b/a Rocky Bleier Construction Group, of Carnegie, Pennsylvania, requests that we recommend it be reimbursed the costs of filing and pursuing its protest challenging the award of a contract to PerformanceEPC, LLC, of Independence, Ohio, under solicitation No. 36C24421R0006, issued by the Department of Veterans Affairs (VA) for a boiler plant renovation project at the Lebanon VA Medical Center. In its protest, RBVetCo alleged the agency engaged in certain improper actions in connection with the award of the contract.

Decision

Matter of: RBVetCo, LLC d/b/a Rocky Bleier Construction Group--Costs

File: B-420698.2

Date: July 13, 2022

D. Matthew Jameson, III, Esq., Burns White LLC, for the protester.

Steven E. Devine, Esq., Department of Veterans Affairs, for the agency.

Elizabeth R. Walsh, Scott H. Riback, Esq., and Tania Calhoun, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.

Digest

Request for recommendation that protester be reimbursed costs associated with filing and pursuing protest is denied where record shows that agency took prompt corrective action before the deadline for submitting its agency report.

Decision

RBVetCo, LLC d/b/a Rocky Bleier Construction Group, of Carnegie, Pennsylvania, requests that we recommend it be reimbursed the costs of filing and pursuing its protest challenging the award of a contract to PerformanceEPC, LLC, of Independence, Ohio, under solicitation No. 36C24421R0006, issued by the Department of Veterans Affairs (VA) for a boiler plant renovation project at the Lebanon VA Medical Center. In its protest, RBVetCo alleged the agency engaged in certain improper actions in connection with the award of the contract.

We deny the request.

In its protest, RBVetCo alleged that the agency issued amendment No. 0007 to the solicitation in an attempt to favor PerformanceEPC over other offerors. RBVetCo alleged that this impropriety was admitted by a former contracting officer from the agency during a meeting with RBVetCo on April 11, 2022, well after the contract had been awarded in February.

In response to the protest, the agency filed a preliminary request for summary dismissal, arguing that the protest was untimely and lacked a legal and factual basis. The agency also denied the allegations of impropriety in RBVetCo’s protest. RBVetCo filed a response to the agency’s request for summary dismissal. Based on a review of the pleadings that had been filed to date, we declined to dismiss the protest in response to the agency’s request at that juncture.

Subsequently, and before any agency report was due, the agency notified our Office that it was taking corrective action by terminating the award and advising that it would resolicit the project after reviewing its requirements. Based on the agency’s proposed corrective action, we dismissed the protest as academic. RBVetCo LLC d/b/a Rocky Bleier Construction Group, B-420698, May 23, 2022 (unpublished decision). After receiving our decision dismissing its protest, RBVetCo timely filed a request that we recommend that it be reimbursed the costs of filing and pursuing its protest.

We deny RBVetCo’s request. When a procuring agency takes corrective action in response to a protest, our Office may recommend reimbursement of protest costs if, based on the circumstances of the case, we determine that the agency unduly delayed taking corrective action in the face of a clearly meritorious protest, thereby causing the protester to expend unnecessary time and resources to make further use of the protest process to obtain relief. 4 C.F.R. § 21.8(e); MacroUSA Corp.-Costs, B-408444.2, Feb. 11, 2014, 2014 CPD ¶ 65 at 2. Where an agency takes corrective action by the due date for submission of its report, we generally regard the action as prompt, and will not recommend reimbursement of protest costs. Id. Here, the agency took corrective action prior to the deadline for submitting its report. Accordingly, the agency's corrective action was prompt.

RBVetCo alleges that it incurred costs for what it describes as a “successful defense” against the agency’s request for dismissal. However, the fact that our Office declined to dismiss the protest in response to the agency’s preliminary request does not show that the preliminary request lacked merit, or that the protester had successfully defended against the agency’s request. Rather, it shows no more than that we required further development of the record before conclusively ruling on the agency’s request.

As we noted in our docket entry, we did no more than decline to dismiss the protest at that time, and request that the agency file its report to develop the record further. B‑420698, Electronic Protest Docketing System No. 16. An agency’s submission of a colorable but unsuccessful dismissal request does not constitute undue delay, or provide a basis for our Office to find a protester entitled to protest costs when the agency ultimately takes corrective action before its report is filed. Abhe & Svoboda, Inc.-Costs, B-412504.2, Apr. 11, 2016, 2016 CPD ¶ 99; Livanta, LLC-Costs, B‑404215.2, Apr. 5, 2011, 2011 CPD ¶ 82 at 2.

The protester argues alternatively that the agency’s decision to take corrective action in terminating the award and cancelling the solicitation was no more than a pretext to avoid responding to the merits of the protest. RBVetCo argues that this shows its protest was meritorious.

The protester did not timely object to the agency’s proposed corrective action, or to our dismissal of its protest. The agency filed its corrective action letter on May 20, and our Office dismissed the protest on May 23. RBVetCo did not file its request for protest costs until June 3, more than 10 days after the date we dismissed its protest. Any challenge now to the agency’s corrective action therefore is untimely. 4 C.F.R. § 21.2(a)(2). In any event, the mere fact that the agency took corrective action does not establish that the protest was clearly meritorious. Diligent Consulting, Inc.-Costs, B‑299556.3, June 26, 2007, 2007 CPD ¶ 125 at 5.

Finally, the protester suggests that the agency’s corrective action was not “prompt” because it was taken almost five months after the agency issued amendment No. 0007 to the solicitation.

Although RBVetCo suggests that its protest objected to the substance of amendment No. 0007, in fact its protest was not focused on the terms of the amendment per se, but, rather, on the allegedly improper motive underlying the issuance of the amendment. As noted, RBVetCo argued that the agency improperly issued amendment No. 0007 in an alleged effort to steer the contract to PerformanceEPC. The adverse agency action that allegedly prompted that protest was RBVetCo’s claim that a former agency contracting official told a company official of the agency’s allegedly improper motive. The agency’s corrective action was taken promptly in response to that allegation, and not, as RBVetCo now claims, in response to a challenge to the terms of amendment No. 0007.

RBVetCo did not timely challenge the terms of amendment No. 0007. RBVet’s protest was filed on April 21, well after the deadline for submitting proposals, and also well after the agency made award of the subject contract in February. See 4 C.F.R. § 21.2(a)(1) (protests alleging an impropriety in a solicitation must be filed no later than the deadline for submitting proposals).

The request is denied.

Edda Emmanuelli Perez

General Counsel

This is a verbatim capture of GAO's own published decision. Nothing is summarized or reworded, and the sections run in the order GAO wrote them. One thing is moved: GAO collects its numbered notes at the foot of the document, and each is shown here under the paragraph that first cites it, with its own number carrying you back. A note the decision never cites stays where GAO printed it.

Related Decisions

Same Agency

Same Year

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.