The Davis Group, Inc.

December 1, 2011Judge James
Denied / Government PrevailedOther

The Davis Group, Inc. appealed the ASBCA's prior decision regarding delays in notifying the government of site conditions. The Board denied the motion for reconsideration, affirming its earlier findings.

Material Facts

  • Davis contends that some of the Board's findings were erroneous, not supported by the record, or clearly contrary to the preponderance of the evidence.
  • Davis' delay in notifying the COE of a possible changed site condition was found to be the proximate cause of the later delay in government approval.
  • The contract required Whitaker's final geotechnical evaluation report to be submitted along with the first foundation design submittal.
  • Davis submitted its design on 2 December 2009 but failed to establish that it submitted the final geotechnical evaluation report.
  • The COE was found to have knowledge of buried wood at the site on 6 January 2010.
  • Davis' 18 January 2010 notice prompted the COE's subsequent investigation on 28-29 January 2010.

Parties

Appellant
The Davis Group, Inc.
Respondent Agency
U.S. Army Engineer District, Mobile
Contracting Agency
U.S. Army Engineer District, Savannah
Contract Number
W912HN-08-D-0037
Open Official Decision PDF (asbca.mil)AI-analyzed, grounded in the decision text. Verify against the official PDF before relying on it.

Full Legal Analysis

Create a free account to read the complete grounded legal brief for this decision, including the holding, every issue the Board decided, quantum, verified citations, and the case's citation graph.

Holding & Legal Reasoning

The Board's holding, background, and procedural posture for this decision.

Issues Presented

Every issue the Board decided, with its determination, reasoning, and supporting authority.

Quantum & Recovery

The claimed, awarded, and net dollar amounts at issue, itemized where the record supports it.

Verified Authorities & Citations

Every cited FAR, DFARS, CAS, and case-law authority, cross-checked against the source text.

Practitioner Takeaways

Practical guidance for contractors and counsel, distilled from the Board's ruling.

Similar Cases

Related decisions surfaced by semantic search across the full analyzed corpus.

Citation Graph

An interactive graph of this case's cited authorities, judge, agency, and related decisions.

Related Decisions

Same Judge

Same Year

Same Issue

Newsletter

New decisions every Monday

GovConDash Weekly lists the decisions GAO, the boards, the courts and SBA OHA released that week, alongside the FAR Overhaul deviations and proposed rules that reach every contractor. Free.

Free, weekly, and one click to unsubscribe. We send a confirmation email first. See our Privacy Policy.